Professional Documents
Culture Documents
JSO BUILDING
Subtotal
II. INSURANCE, TAX, OCCUPANCY PERMIT
Occupancy Permit
City Tax
Insurance (CARI) lot
Bonds
Performance Bond lot
Surety Bond lot
Guarantee Bond lot
Subtotal
III. TEMPORARY FACILITY & SAFETY REQUIREMENTS
A. Field Office & Storage
B. Security & Safety lot
C. Uniforms, First Aid, ID, fire extinguishers, lot
hard hats -included lot
Testing Materials lot
Electrical and Water Consumption lot
As-built Plans lot
Equipment lot
Others not specified
Subtotal
II. COMPLETE SITE PREPARATION
Mobilization/ Demobilization lot
Filling and Grading
Dewatering lot
Site Preparation lot
Cleaning and Hauling lot
Re-survey and building layout lot
Others not specified
Demolition works and hauling of
Existing structure-excluded as per
instruction
subtotal:
III. EXCAVATION AND BACKFILLING WORKS
A. Excavation works & trimmings (backhoe) cu.m.
Excavation for Basement cu.m.
Hauling-excess soil
Backfilling works inc. compaction cu.m.
Gravel & Sand Beddings cu.m.
Earthfill cu.m.
Soil Poisoning cu.m.
Damproofing cu.m.
Shotcrete Only lot
Bentonite lm
subtotal: cu.m
ITEMIZED BID BREAKDOWN
JSO BUILDING
ARCHITECTURAL
A Masonry Work
1. 4" CHB
B2 sq.m.
B1 sq.m.
LG sq.m.
UG sq.m.
2ND sq.m.
3RD sq.m.
subtotal:
2. 6" CHB
B2 sq.m.
B1 sq.m.
LG sq.m.
UG sq.m.
2ND sq.m.
3RD sq.m.
subtotal:
total:
B Plastering Works
1. Exterior & Interior (CHB)
a. Basement 2 sq.m.
b. Basement 1 sq.m.
c. Lower Ground sq.m.
d. Upper Ground sq.m.
e. 2nd Floor sq.m.
f. 3rd Floor sq.m.
subtotal: sq.m.
2. RC Wall (Interior)
a. Basement 2 sq.m.
b. Basement 1 sq.m.
c. Lower Ground sq.m.
d. Upper Ground sq.m.
subtotal: sq.m.
3. Plastering Works (Linear) l.m.
4. Concrete Moulding and Drip Moulds l.m.
5. Concrete Grooves l.m.
6. Lintel Beams sq.m.
subtotal:
C Floor Finishing
a. Concrete Topping
1. Basement 2
a. Elevator Lobby sq.m.
b. Utility/Storage sq.m.
c. Electrical Room sq.m.
d. Staircase 1 sq.m.
e. Staircase 2 sq.m.
f. sq.m.
2. Basement 1
a. Elevator Lobby sq.m.
b. MRF sq.m.
c. Staircase 1 Landing sq.m.
c. Aux Security Office sq.m.
c. Aux Admin Office sq.m.
c. Staircase 2 Landing sq.m.
3. Lower Ground
a. Elevator Lobby sq.m.
b. PWD Toilet sq.m.
c. Staircase Landing sq.m.
d. MRF sq.m.
4. Upper Ground
a. Elevator Lobby/Hallway sq.m.
b. Reception area sq.m.
c. Electrical Room sq.m.
d. Admin Office sq.m.
e. Stairacase 1 Landing sq.m.
f. Exterior (Rear) sq.m.
5. Second Floor
a. Elevator Lobby sq.m.
b. Staircase 1 Landing sq.m.
c. Electrical Room sq.m.
6. Third Floor
a. Office Space sq.m.
b. Staircase 1 Landing sq.m.
c. Electrical Room sq.m.
b. Tiling Works
1. Lower Ground Toilet sq.m.
2. Upper Ground Toilet sq.m.
3. Male Toilet sq.m.
4. Female Toilet sq.m.
5. Private Toilet sq.m.
subtotal: sq.m.
c. Ramp Non-Skid Tiles
7. B2 to B1 sq.m.
8. B1 to LG sq.m.
subtotal: sq.m.
c. Lower Ground Bush-Hammered Finish
1. Lower Ground Spillover Area sq.m.
2. Upper Ground Ramp sq.m.
subtotal: sq.m.
D Dry Wall/ Ceiling Works
Gypsum Board: fixed to & including metal
furring support system
sq.m.
subtotal: sq.m.
Fibre Cement Board: fixed to & including
metal furring support system
1. Upper Ground Eaves sq.m.
2. 2nd Floor Eaves sq.m.
1. 3rd Floor Eaves sq.m.
subtotal: sq.m.
E Waterproofing
1. Elevator Pit sq.m.
2. Roof Deck sq.m.
3. Canopy sq.m.
4. Firewall sq.m.
5. Basement 1 Wall sq.m.
6. Basement 2 Wall sq.m.
7. Fire Tank sq.m.
8. Cistern Tank sq.m.
9. Male Toilet (Lower Ground) sq.m.
10. Female Toilet (Lower Ground) sq.m.
11. Private Toilet (3rd Floor) sq.m.
12. Male Toilet (3rd Floor) sq.m.
13. Female Toilet (3rd Floor) sq.m.
Topping Works w/ wire mesh
F Painting Works
1. CHB Interior Walls + RC Walls + Columns sq.m.
2. Ceiling: Exposed Beams, Slabs
(skimcoat w/filler, MR Gypsum Boards)
G Stairs Finishes
Stairs 1 (behind Elevator)
Powder Coated Steel Railing m
50mm Powder Coated Tubular Steel m
Steel Stringer m
Tiling sq.m.
Stairs 2
Non-skid Nosing Tile pcs.
Black Iron Sheets
H Glazing/Louvres/ Miscellaneous Metals
Owner-Supplied
I Doors/Frames -Hardware
Powder Coated Steel Doors
700x2100mm overall pcs.
800x2100mm overall pcs.
900x2100mm overall pcs.
1000x2100mm overall pcs.
1000x2100mm overall pcs.
1000x2100mm overall pcs.
2000x1900mm overall pcs.
subtotal
MATERIAL LABOR COST TOTAL
UNIT COST UNIT COST AMOUNT
length, m line Total Length
LP01 - 01 18.22 2.00 36.44
1.00 18.22
THHN
THHN
THHN
Wire 283.67
5.35
wires type conduit
3.5 mm2 THW 18.22 20mmØ uPVC
3.5 mm2 THW
wires conduit
3.5 mm2 746.87 20mmØ uPVC 269.17 89.72
Item Description
A. General Requirements
Mobilization / Demobilization
Temporary Facilities
Bonds and Insurances
Supervision
As-built plan
Hoarding Fence (Construction phasing)
sub-total
B. Repairs / Refurbishments
C. Architectural Finishes
Floor Finishes
150 x 1200mm Wood Planks Glossy - Living / Dining / Main Entrance
300 x 300mm Homogeneous Porcelain Tiles - Kitchen Area
300 x 300mm Homogeneous Tiles - Toilet & bath
Existing Herringbone Wood Parquet - Bedroom
30 x 30 cm Carpet tile (Accent)
Concrete topping
Wall Finishes
Drywall
Glass Wall
Graphicote board
Operable Wall Partition
Laminate wall siding
Ceiling Finishes
6.0MM thk MR Fiber Cement Board on Metal Furring
6.0MM thk Fiber Cement Board on Metal Furring
Suspended 6.0MM thk Fiber Cement Board on Metal Furring
Doors w/ Jamb & hardwares (Re-installation and Re-painting Only)
Carpentry / Casegoods
Modular base cabinet - Pantry
Overhead cabinet - Pantry
Cashier counter
Biometrics counter
Conference room - cabinet/shelf
Guard Podium
Painting / Re-painting Works
Interior Walls
Drop Ceiling
Underslab & Utilities
Specialties
Logo Signage with EGD
sub-total
D. Carpentry Works
D. Mechanical Works
Page 14 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
Installation (Ducting)
5.0 TR ACU
5.0 TR ACU
2.0 HP Split-type Inverter - HRAD
2.0 HP Split-type Inverter - Conference
2.0 HP Split-type Inverter - C&R
2.0 HP Split-type Inverter - President
1.5 HP Split-type Inverter
1.5 HP Split-type Inverter
1.5 HP Split-type Inverter
Ducting
sub-total
E. Electrical Works
### General Lighting and Power
Lighting Fixtures & Devices
Troffer Light 1 (Re-Use with Tube bulb, Installation Only)
Troffer Light 2 (Re-Use with Tube bulb, Installation Only)
Pin Light 1
Pin Light 2
Pin Light 3
Cove Light
PB / CB
Wires, Rough-ins & other devices
3.2mm Wire
32mm dia x 3.0m uPVC
Pipe Fittings
Miscellaneous items
Emergency Light
Switches
Convenience Outlet
Utility Boxes
Telephone System
Telephone Outlet (re-use existing)
Main Telephone Terminal Cabinet (re-use existing)
Wires/cables, Rough-ins & other devices (Re-orientation)
0.65mm/4C Tel. Drop wire
25mm dia. uPVC pipe
20mm dia. uPVC pipe
Pipe Fittings
Utility Box
Square Box with cover
Pull Box
Miscellaneous items
Page 15 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
F. Plumbing Works
Water and Drainage System - to be tapped to the nearest source
Civil works
Note : Water and drainage line to be tapped to the nearest existing
source in the building
sub-total
Page 16 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
sub-total
Page 17 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
Page 18 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
VIII. PLUMBING
A. Fixtures and Accessories
Water Closet
Wall Hung Lavatory
Lavatory Faucet
Shower Set
Kitchen Sink - Double Bowl
Kitchen Faucet
Hose Bibb
Floor drain
Deck drain
Grease Trap
B. Sewer and Drainage System
Septic Tank 0.9m x 3.2m x 1.8m
Catch Basin
150mmØ x 3.0m uPVC pipe
100mmØ x 3.0m uPVC pipe
50mmØ x 3.0m uPVC pipe
Pipe Fittings
Miscellaneous and consumables
C. Water System
Water Meter
Gate Valve
Check Valve
25mmØ x 3.0m uPVC pipe (PNS 65)
20mmØ x 3.0m uPVC pipe (PNS 65)
Pipe Fittings
Miscellaneous and consumables
sub-total
IX. ELECTRICAL
A. Wires and Rough-ins
2.0mm2 THHN Copper Wires
3.5mm2 THHN Copper Wires
5.5mm2 THHN Copper Wires
8.0mm2 THW Copper Wires
22.0mm2 THW Copper Wires
38.0mm2 THW Copper Wires
20mmØ x 3m uPVC Pipe
32mmØ x 3m uPVC Pipe
40mmØ x 3m uPVC Pipe
Pipe Fittings
Miscellaneous and consumables
B. Lighting Fixtures
Lighting Outlet
Chandelier
Pinlight
Downlight
Wall Bracket Lamp
Up/DownWall Lamp
Covelight
C. Wiring Devices and Boxes
1-Gang switch
2-Gang switch
3-Gang switch
1-Gang 3W switch
Duplex Convenience Outlet
Refrigerator Outlet
Cooking Range Outler
Weatherproof Convenience Outlet
4" x 4" Octagonal box
2" x 4" Utlity box
Ga. 16 GI Pullwire
Miscellaneous and consumables
D. Panelboard and Circuit Breakers
LP-01, 125AT/150AT, 60Hz, 2P
Br : 1 - 4 - 30AT, 6 - 20AT
LP-02, 75AT/100AT, 60Hz, 2P
Br : 1 - 100AT, 4 - 30AT, 11 - 20AT
E. Testing and Commissioning
sub-total
Page 19 of 27
Project : PROPOSED FULL INTERIOR RENOVATION OF A RESIDENTIAL CONDOMINIUM UNIT
Location : Dansalan Gardens Condominium, Mandaluyong City
Owner : Atty. Thes Veneracion
Item Description
Page 20 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
- - - - -
- - - - -
sq m 32.04 - 300.00 - 375.00 - 12,015.00 12,015.00
- - - - -
1.00 10,000.00 - 12,500.00 - 12,500.00 12,500.00
24,515.00
244,896.25
- - - - -
sq m - - 300.00 - 375.00 - - -
- - - - -
1.00 10,000.00 - 12,500.00 - 12,500.00 12,500.00
184,750.00
Page 21 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
Page 22 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
Page 23 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
Page 24 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
set 1.00 - - - - - - -
set 1.00 - - - - - - -
set 3.00 - - - - - - -
set 3.00 - - - - - - -
set 1.00 - - - - - - -
set 1.00 - - - - - - -
set 4.00 - - - - - - -
set 1.00 - - - - - - -
set 1.00 - - - - - - -
set 1.00 - - - - - - -
167,360.00 24,270.00 191,630.00
1,516.67 1,516.67
Page 25 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
nos 1.00 - - - - - - -
nos 10.00 1,500.00 500.00 1,500.00 500.00 15,000.00 5,000.00 20,000.00
nos 2.00 1,530.00 610.00 1,530.00 610.00 3,060.00 1,220.00 4,280.00
nos 2.00 714.00 285.00 714.00 285.00 1,428.00 570.00 1,998.00
nos 2.00 250.00 100.00 250.00 100.00 500.00 200.00 700.00
lot 1.00 980.00 420.00 - - 980.00 420.00 1,400.00
lot 1.00 1,257.00 - - - 1,257.00 - 1,257.00
1,169,486.98
362,946.83
Page 26 of 27
PLEASE HIDE THIS COLUMN
change this VALUE to your liking
160,000.00
8,000.00
168,000.00
239,320.00
62,280.00
60,320.00
15,080.00
377,000.00
2,460,542.25
Page 27 of 27