You are on page 1of 1

Ministry of Public Works

Trans-Hindukush Road Connectivity Project - Implementation Stage High Level Program


Work Activity Dur 2017 2018 2019 2020 2021 2022 2023 2024
Mths N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Segment 1 (24 km)
Contract Awarded 21
Segment 6 (25 km)
Contract Awarded 28
Segment 2 (23 km)
100% Design Package Nov-17 Apr-18 1
Procurement & Award Apr-18 Oct-18 3
Contractor Mobilization Oct-18 Dec-18 2
contractor - Works Jan-19 Aug-20 21
Segment 5 (20 km)
Survey Nov-17 Feb-18 1

Salang Pass - Rehabilitation Completed


100% Design Package Dec-17 Mar-18 3
Procurement & Award Mar-18 Jan-19 3
Contractor Mobilization Feb-19 Apr-19 2
contractor - Works Apr-19 Aug-21 20
Segment 3 (14 km)
Survey Nov-17 Feb-18 -
100% Design Package Dec-17 Mar-18 4
Procurement & Award Mar-18 Jan-19 11

B2B-Highway Completed
Contractor Mobilization Feb-19 Apr-19 3
contractor - Works Apr-19 Jan-21 16
Segment 4A (25 km)
Survey Nov-17 May-18 -
100% Design Package Apr-18 Sep-18 6
Procurement & Award Oct-18 Jun-19 9
Contractor Mobilization Jun-19 Aug-19 3
contractor - Works Aug-19 May-21 21
Segment 4B (21 km)
Survey Nov-17 May-18 -
100% Design Package Apr-18 Sep-18 6
Procurement & Award Oct-18 Jun-19 9
Contractor Mobilization Jun-19 Aug-19 3
contractor - Works Aug-19 Apr-21 20
Salang Rehabilitation (86 km)
Study, Design and Procurement Package Nov-17 Aug-18 15
PMT/IC Engagement - Agree Final Package Aug-18 Aug-19 12
Procurement & Award Aug-19 Feb-20 6
South side - Lower Levels Mobilize & Implement Feb-20 Oct-21 -
Middle - Upper Levels/Tunnel Major Works Jan-22 Oct-23 12
North Side - Lower Levels Mobilize & Implement Feb-20 Oct-21 -
Turkham-Jalalabad-Kabul (TJK) Expressway Development
Prepare TOR for Feasibility &Preliminary Design 3
Procure & Award Consultancy 9
Undertake Consultancy 12
Prepare TOR for ESA 6
Procure and Award Consultancy 6
Undertake Consultancy 12
Development and Implementation of Sustainable Strategic O&M Approach for new B2B Highway and Rehabilitated Salang Pass (238 km)
Develop and Procure New O&M Approaches TBC
Implementation of New B2B O&M Modality 12
Implementation of New Salang O&M Modality 12
Development and Implementation of Capacity Building for MoPW Reforms
Assessment, Analysis & Reporting 6
Preparation of Capacity Building Plan 4
Implementation of CB Support 16
Capacity Building and Institutional Strengthening Support (PMT, CSU and MoPW)
Training, Mentoring, Developoing & TA Support -
Key: OMT - MoPW Project Management Team IC: UNOPS Implementation Consultants Team PMT Survey PMT/IC Tech Works External Design Procurement Mobilization implementation Stages Implementation Defects Perios MoPW Reform Programme

You might also like