B2B-Highway Completed
Contractor Mobilization Feb-19 Apr-19 3
contractor - Works Apr-19 Jan-21 16
Segment 4A (25 km)
Survey Nov-17 May-18 -
100% Design Package Apr-18 Sep-18 6
Procurement & Award Oct-18 Jun-19 9
Contractor Mobilization Jun-19 Aug-19 3
contractor - Works Aug-19 May-21 21
Segment 4B (21 km)
Survey Nov-17 May-18 -
100% Design Package Apr-18 Sep-18 6
Procurement & Award Oct-18 Jun-19 9
Contractor Mobilization Jun-19 Aug-19 3
contractor - Works Aug-19 Apr-21 20
Salang Rehabilitation (86 km)
Study, Design and Procurement Package Nov-17 Aug-18 15
PMT/IC Engagement - Agree Final Package Aug-18 Aug-19 12
Procurement & Award Aug-19 Feb-20 6
South side - Lower Levels Mobilize & Implement Feb-20 Oct-21 -
Middle - Upper Levels/Tunnel Major Works Jan-22 Oct-23 12
North Side - Lower Levels Mobilize & Implement Feb-20 Oct-21 -
Turkham-Jalalabad-Kabul (TJK) Expressway Development
Prepare TOR for Feasibility &Preliminary Design 3
Procure & Award Consultancy 9
Undertake Consultancy 12
Prepare TOR for ESA 6
Procure and Award Consultancy 6
Undertake Consultancy 12
Development and Implementation of Sustainable Strategic O&M Approach for new B2B Highway and Rehabilitated Salang Pass (238 km)
Develop and Procure New O&M Approaches TBC
Implementation of New B2B O&M Modality 12
Implementation of New Salang O&M Modality 12
Development and Implementation of Capacity Building for MoPW Reforms
Assessment, Analysis & Reporting 6
Preparation of Capacity Building Plan 4
Implementation of CB Support 16
Capacity Building and Institutional Strengthening Support (PMT, CSU and MoPW)
Training, Mentoring, Developoing & TA Support -
Key: OMT - MoPW Project Management Team IC: UNOPS Implementation Consultants Team PMT Survey PMT/IC Tech Works External Design Procurement Mobilization implementation Stages Implementation Defects Perios MoPW Reform Programme