You are on page 1of 10

HNSS PHASE-II - PACKAGE NO.

22 & 22

Name of work : Excavation of HNSS Main canal fro


M/s Sree Jaya - K.Siva SEH 01 EPC / 2006 -
Agency : P-22 Agt No. & Value.
Rao (J.V) 51.53 Cr
Progress : 80.46% Work done Rs.41.46Cr.

M/s Sri Sai lakshmi


Agency : P-22 BW Agt No. & Value. 2SE, Dt.16.6.2017 & Rs
construction & company
Progress : 58.28% Work done Rs.10.45Cr.

LINE DIAGRAM SHOWING STATUS OF PACKA

Main Canal in Kms Land Acquistion (in Acres)


607.05
Main Canal 23.000 Requisitioned
workdone 22.225 Acquired 607.05

Balance 0.775 Balance to be


Acquired 0.00

Kummarapalli (v), Sambepalli (m) Kadapa (Dt)

Starting Point @ Km.523.000 DLRB.Km.523.710


K m 523.800
S.P.Km.524.380

U.T.Km.526.625

SLRB.Km.526.755

UT Km.532.650
DLRB.Km.533.349
Main can
Main canal
SP.Km.534.556
DLRB Km 535.395

S.P. Km 536.00

S.P. Km 536.745

SLRB Km 539.060

UT Km.539.450
Thandu km 540.575

Thandu Km 540.900
Completed U.T.Km.541.71

U.T.Km.541.970

SP Km.542.500
To be taken up
Progress
Km 543.000 to 545.000 Ewe progress
SLRB Km.545.650
Thandu Km 545.675

Ending Point @ Km.546.000 Kottha gandla palli (V)


SE-II - PACKAGE NO.22 & 22 BW

HNSS Main canal from Km 523.000 to Km 546.000


SEH 01 EPC / 2006 - 07 Rs.
Rs.51.53Cr.
51.53 Cr
E.O.T:-31.12.2011, 30.06.2013, 30.06.2014 & 31.03.2016
Now : 30.06.2019

2SE, Dt.16.6.2017 & Rs. 17.93 Cr Rs.17.93Cr.

E.O.T up to 30.11.2018.

HOWING STATUS OF PACKAGE WORK

Status of CM & CD Works

P- 22 P-22 BW Total
Total Nos 11 16 27
completed 11 11
22
Progress 0 5 5
To be taken
up 0 0 0

mbepalli (m) Kadapa (Dt)


Balance E.W & Concrete Quantites status
Concrete
Quntities E.W in Cum
(Cum)
Total Qty 51844 34645

Work Done 41678 19081

Balance 10166 15564


HNSS PHASE-II - PACK

Name of work : Excavation of HNSS Main canal from Km 546.00 to

M/s RMN-GVR (JV) , Agt No. &


Agency : P-23
Hydarabad Value.

Progress : 98.92% Work done

M/s Sri SCL Infratech Limited , Agt No. &


Agency : P-23 A
Hyderabad Value.
Progress : 73.74% Work done

LINE DIAGRAM SHOWING STAT

Main Canal in Kms Land Acquistion (in


Main Canal 8.175 Requisitioned
workdone 8.000 Acquired
Balance 0.175 Balance to be
Acquired

Kottha gandla palli (V) Kalakada (M)

Starting Point @ Km.546.000

UT @ Km 546.2

Thandu Km 547.130

Thandu Km 548.000
M2 Lift P M2 @ Km 551.1

Thandu Km 551.500

M3 Lift M3 @ Km 553.050

554.175 Km End point

Adivipalli
Reservoir 1.418
TMC OFF TAKE

O
FF
Completed TA
K
To be taken up E
Neeva Branch canal
Progress
HNSS PHASE-II - PACKAGE NO.23 & 23 A

ain canal from Km 546.00 to Km 554.175 and formation of Adivipalli Reservoir in Chit
District.

SEH 3 EPC, Dt.01/12/06. & Rs. 48.71 Cr Rs.48.71Cr.

E.O.T :-30.11.2011,31.03.2013, 31.03.2014 & 31.12.201


Rs.48.18 Crores
to 04.05.2016.

11SE/2016-16, Dt.22/01/16. & Rs. 29.21 Cr Rs.29.21Cr.

Rs.21.54Cr. E.O.T up to 31.12.2018.

E DIAGRAM SHOWING STATUS OF PACKAGE WORK

Land Acquistion (in Acres) Status of CM & CD Works


1482.36 P- 23 P-23 A
1482.36 Total Nos 7
completed 6 0
0.00
To be taken
up 0

Balance 1 0

palli (V) Kalakada (M)

UT @ Km 546.200

Thandu Km 547.130

Thandu Km 548.000 Balance Critical Structure


Work Status

Total 1
Progress
To be taken 1
Balance E.W & Concrete Quantites st
in Reservoir
Revetment in
Quntities
sqm
Total Qty 55645.000
Lift P M2 @ Km 551.175 Work Done
55345.000
Balance 300.000
Thandu Km 551.500

Lift M3 @ Km 553.050

Balance E.W & Concrete Quantites st


in main canal

Quntities E.W in Cum

554.175 Km End point Total Qty 441790.000


Work Done
441790.000
Balance 0

OFF TAKE
Vayalpadu Branch Canal

nch canal
3 & 23 A

nd formation of Adivipalli Reservoir in Chittoor

Rs.48.71Cr.

E.O.T :-30.11.2011,31.03.2013, 31.03.2014 & 31.12.2015, up


to 04.05.2016.

Rs.29.21Cr.

E.O.T up to 31.12.2018.

AGE WORK

Status of CM & CD Works


Total
7

0
1
Balance E.W & Concrete Quantites status
in Reservoir
Concrete
(Cum)
3340

3300
40

Balance E.W & Concrete Quantites status


in main canal
Concrete
(Cum)
650

0
650