Purchase Order
Order No : GDCL / Hyd-CED / PUR / 28977 / 15-16 / 1600001377 Date : 28-DEC-2015
Supplier Quotation No : Indent No(s) :
Supplier Quotation Date : Project : Shreno_Samsara_Bangalore
This has reference to your offer/s and further telephonic discussion we had with you, we are pleased to confirm our order for the supply of following
material/s as per the rates, terms and conditions mentioned in our order.
Amount in Words : INR Four Lakh Eighty Thousand Two Hundred Ninety Six Rupees And Thirty Eight Paise Only
Special Remarks :
Sr. Rate
Item Quantity Amount
No INR
1 PVC Pipe 20 OD 8160.000 12.60 102816.00
CST@2%(Against C Form) 2056.32
104872.32
2 PVC Pipe 75mm 600.000 70.81 42486.00
CST@2%(Against C Form) 849.72
43335.72
3 PVC Pipe 160mm 540.000 313.36 169214.40
CST@2%(Against C Form) 3384.29
172598.69
4 PVC Pipe 110mm 1080.000 144.78 156362.40
REGISTERED OFFICE : NEW EXCELSIOR BUILDING (3RD FLOOR), A.K. NAYAK MARG, FORT, MUMBAI-400001
OFFICES AT : AHMEDABAD . CHENNAI . COIMBATORE . HYDERABAD . KOLKATA . MUMBAI
Page 1 of 2
Contd..
GDCL / Hyd-CED / PUR / 28977 / 15-16 / 1600001377
PO Date: 28-DEC-2015
Gannon Dunkerley & Co., Ltd.
Payment Terms :
Delivery Instruction: Within one or two days send through Vehicle to our Samsara Project Site, Bangalore ( Mr. Suresh - 09686405657 ).
Delivery Charges: Extra on our A/c at actual. Payment Terms: 30 days Credit.
Test Certificate: Batch Test Certificate of the materials shall be send along with the materials / invoice.
Inspection Instruction: Our representative will check the materials after receiving the same, if any defect in quality or if not as per our requirement etc.,
you have to take back the same at your own cost and risk.
Any other dispute arising out of above is subject to Hyderabad Jurisdiction only.
We are issuing this order in duplicate; you are requested to sign on the duplicate copy as a token of your acceptance for our reference and record.
Thanking you,
Yours faithfully,
For Gannon Dunkerley & Co. Ltd.,
Authorized Signatory
CC: Samsara Project Site, Bangalore. Purchase Dept., A/c Section, HRO.