You are on page 1of 2

SCHEDULE PEKERJAAN TURBIN SERIOUS INSPEKSI UNIT #3

PERIODE : 20 Maret - 09 April 2019


Tanggal
Man Power
No. Unit Uraian Pekerjaan SHIFT TOTAL Day 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 Keterangan
CFK TK COHA WTP 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 Persiapan alat kerja dan APD 4
2 Cleaning Tubing condenser 8 8 8 8 8 8 8 8 8 8
3 Kuras dan cleaning bak water jet 0 4
4 Cleaning straine CWPP A dan B 2
5 Cleaning Tubing Pendingin Generator 2 4
CONDENSER 6 Cleaning Sisi dalam Condenser 4 4
A
SYSTEM Cleaning Strainer Inlet Condensat pump A/B & Bongkar
7 4
pasang strainer
8 Greasing - Trial open/close MOV & Manual Valve 2 2
9 Cleaning sekitaran 2 2 2
Trial motor pompa condensate pump A,B, CWPP A,B, Water
10 18
jet pump A,B dan Gland Exhaust Fan A,B
1 Persiapan alat kerja dan APD 4
2 Kuras/drain oli tank ke temporary Oil Tank 0
STEAM 3 Cleaning sisi dalam oil tank 0 4 4
SYSTEM, OIL 4 Cleaning oil filter 4
C SYSTEM & 5 Cleaning tube oil cooler A dan B 0 4
DRAIN 6 Masukkan kembali Oil Lube ke Oil tank 4
SYSTEM Inspeksi MOV & Manual Valve / Greasing ( elev 0; 4,5 & Auxiliary Steam )
7 2 2
dan trial open-closed MOV dan MV
8 Cleaning sekitaran 2 2 2
9 Trial Running HP, AC, DC, JOP & Extractor
1 Persiapan alat kerja dan APD 6
2 Cleaning Dearator atas bagian dalam dan cek nozzle 0 6
3 Cleaning Dearator bawah bagian dalam 6 6 6
HEATER DAN
4 Cleaning Strainer Inlet BFWP & Cooler A/B, tutup kembali 0
D DEAERATOR Inspeksi valve, greasing MOV & Manual Valve BFWP dan
SYSTEM 6 Deaerator, Trial open/closed 6
7 Cleaning sekitaran 6 6
8 Trial running BFWP A dan B
1 Persiapan alat kerja dan APD 0
2 Drain Dan Cleaning Hidrocyclone 2
3 Cleaning Filler-filler & Nozzle Spray Cooling tower 4 6 6 6 6 6
Pengecekan fan dan pengecekan/penggantian nozzle spray
4 0 6
cooling tower
COOLING
5 Cleaning Lumut di dinding,Tiang, filler dari sisi bawah 0 6 6
B TOWER
Cleaning Lumpur di bak cooling tower, dan tambal
SYSTEM 6 6 8 8 8 8 8 8 8
dinding,sekat,lantai yang bocor
7 Cleaning sekitaran 0
8 Pengisian Air Bak Cooling Tower 0 8 0
9 Greasing MOV & Manual Valve 0
10 Trial Running motor pompa & fan 0
TOTAL MANPOWER 12 2 0 4 PM 18 19 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 18 START UP

NOTE TEAM TURBINE GENERATOR & COOLING TOWER :


1 Team Merah sebanyak 4 (Empat) orang
2 Team Biru sebanyak 8 (Delapan) orang
3 Team Hijau sebanyak 6 (Enam) orang
SCHEDULE PEKERJAAN BOILER SERIOUS INSPEKSI UNIT #3
PERIODE : 20 Maret s.d 09 April 2019
Tanggal
Man Power
No. Unit Uraian Pekerjaan SHIFT Total Day 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 Keterangan
CFK TK COHA WTP 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Persiapan alat kerja dan APD
1 8
Cleaning/Flushing Coalmill A,B & C
2 0
kuras coal bunker ABC
3 0 8 8 8 8
Cleaning Chute Coal Feeder ABC
4 4
A MILL SYSTEM
Greasing - Trial Open/Cloe Valve MOV & Manual
5 8 8
6
Cleaning sekitaran 8 8
Trial Running Motor Coalmill ABC
7 17
Trial interlock sell work pump
8 0
Persiapan alat kerja dan APD
1 0
Drain dan geser bak bottom sludge
2 0
Pasang andang di dalam furnace sd sofa layer
3 9 9 9 9 9 9
Cleaning/inspeksi pipa Super Heater (platen,
4
Secondary,Primari) 9 9
5 Cleaning dinding ruang bakar 9 3 3
6 Cleaning upper Air Heater 6
GAS & FLUE
B 7 Cleaning Upper Economizer front & Back 0 6
GAS SYSTEM
8 Cleaning Midle air heater Front & Back 9
9 Cleaning Lower Economizer Front & Back 0
10 Cleaning triple lower air heater Front & Back 9
11 Cleaning Lower Temperatur Economizer 9 9
12 Cleaning Ducting Flue Gas 9
13 Bongkar andang di dalam furnace 9 9
14 Cleaning sekitaran 0
1 Persiapan alat kerja dan APD
Cleaning Housing & Impeller PAF A/B, SAF A/B, IDF A/B &
2 4 4
Sealing Air Fan
C AIR SYSTEM
3 Greasing - Trial Open / Close Valve MOV & Valve manual 0 0
4 Cleaning sekitaran 0 0
5 Trial Running Motor & Fan 0
1 Persiapan alat kerja dan APD 0
WATER ,
2 Flushing line cooler PAF, SAF,& IDF 4 4
VENTING,
3 Cleaning Steam Drum sisi dalam 3 3 3 3
D DRAIN &
4 Inspeksi kebocoran valve di drain main steam & Hanger
STEAM
5 Greasing - Trial Open / Close Valve MOV & Valve manual 0 0
SYSTEM
6 Cleaning sekitaran 0 0
1 Persiapan alat kerja dan APD 0
2 Buka manhole 4
3 Cleaning Electroda ESP Chamber ABCD 0 8 8 5
4 Pengecekan Hammer vertical dan horizontal 5
5 Cleaning Chute & Hopper ABCD 0 5
E ESP System 6 Cleaning Blow Ash Tank & Conveying Fly Ash 5
7 Cleaning Compressor luar / dalam 0
8 Cleaning Air Dryer luar / dalam 0
9 Greasing - Trial Open / Close Valve MOV & Valve manual 0 0
10 Cleaning sekitaran 0 0
11 Trial Running Motor - Blower 0
TOTAL MAN POWER DAN TARGET HARI KERJA 9 2 6 0 PM 17 19 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 START UP
35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35
NOTE TEAM BOILER & ESP : CALCULASI MANPOWER
1 Team Merah sebanyak 8 (Delapan) orang BAGIAN JUMLAH ORANG Embalut, 13 Maret 2019
2 Team Biru sebanyak 9 (Sembilan) orang BOILER 9
TURBIN 8
ESP/CT 4
COHA 6 TEAM UNIT 3
WTP 4
TK 4
TOTAL 35

You might also like