Professional Documents
Culture Documents
Presentation Title
Primary cementing
Presentation Title
Cementing Practices – Primary or single stage cementing
• CONDITION MUD
• RELEASE TOP PLUG
• RUN CASING
• CONTINUE DISPLACEMENT
• PUMP SPACERS
Presentation Title
Cementing Practices – Primary or single stage
cementing
Cement Head
equipment
includes Drilling Fluid
• Float collar
• Centralizers
Float Collar
head
Presentation Title
Figure 9 Typical cementing equipment. 5
Cementing Practices – Primary or single stage
cementing
Top
Plug
Top Plug
Released
Cement
Bottom Displacement
Plug Fluid
Spacer
Fluid
Drilling
Fluid Plug
Bottom Bumped
Float Plug
Collar Ruptured
Shoe
Joint
Float
Shoe
A B C
Presentation Title
6
Secondary or remedial cementing
• Squeeze jobs
• Top up job
Presentation Title
Types of cement
API Class Mix water gal / sx Slurry wt. ppg Depth ft BHST °F
Presentation Title
Yield
MIX
2 galls
Additives
Presentation Title
Slurry density
G 44 4.97
It is decided to cement 500 ft up inside the previous string of casing using API
class A cement.
133/8” OD casing
Using information provide:
95/8” OD
casing
3000 ft
• The amount of mud needed to pump to displace the cement i.e. bump the top plug.
In all cement calculations, it is necessary to know the yield per sack of the cement
being used to be able to confirm that sufficient material is on site for the job
(including contingency).
The yield/sack depends on the amount of additives in the cement and the required
final slurry density.
Schematics are invaluable in clarifying the volumes required including details
regarding annular capacities (open hole and cased hole), different grade casings,
section lengths etc.
Presentation Title
STATIC BOTTOM HOLE
TEMPERATURE vs
CIRCULATING TEMPERATURE
THICKENING TIME
hrs
Example of API
Casing Tests on
Class A or B slurry
3
4 6 8
ft x 1000
Presentation Title
14
Cement Job
• Centralization
• We have known for more than half a century that centralizing the
casing will aid in getting a good cement job
• For a non-Newtonian fluid, the velocity on the narrow side of the
annulus is slower than the velocity on the wide side of the annulus
• It is the “Popcorn Theory”
Presentation Title
16
Cement Job
Presentation Title
17
Cement Job
Rb − Rc − C − D
% S tan doff = x100
Rb − Rc
Presentation Title
18
Cement Job
• As a rule of thumb, one centralizer per two joints in vertical wells and
one centralizer per joint in directional wells
• High angle or horizontal wells may require two centralizers per joint
for adequate centralization
• Smaller hole clearances will require more centralizers
• Pipe movement
• It has been shown that pipe movement can increase the displacement
efficiency
• Pipe movement is rotation and/or reciprocation
• Pipe rotation helps the most
Presentation Title
19
Cement Job
• Drag forces associated with
rotation will pull the cement into
the narrow side of the annulus
• Rotation requires specialized
equipment No Rotation Rotation
• Some liner hangers can be Flowing Cement
rotated
Gelled Mud
Presentation Title
20
Cement Job
Presentation Title
21
Cement Job
• Hole condition
• A clean hole allows the ease of running casing and getting centralizers to bottom
• Washouts are hard to cement
• If washouts are a problem, change the mud to try and minimize the washouts
Presentation Title
22
Cement Job
• If you are getting adequate cement jobs, don’t spend more money on
the mud
• Displacement velocity
• Is turbulent, laminar or plug flow better?
Presentation Title
23
Cement Job
• Plug flow is the lowest annular
velocity (30 to 90 feet per
minute (10 to 30 m/min),
depending upon cement
properties)
Turbulent Flow
Laminar Flow
Plug Flow
Presentation Title
24
Cement Job
Presentation Title
25
Cement Job
Presentation Title
26
Cement Job
Presentation Title
27
Cement Job
• Spacer fluids
• Cement and mud are not compatible and should be kept separate
• A spacer fluid is used to separate the cement and mud in the annulus
• The spacer fluid should be compatible with both the cement and the mud
Presentation Title
28
Cement Job
Presentation Title
29
Cement Job
Presentation Title
30
Cement Job
• Directional wells
• More difficult to get adequate centralization
• Will need to run more centralizers than a vertical well
Presentation Title
31
Cement Job
Cuttings Bed
Presentation Title
32
Cement Job
Presentation Title
33
Cementing Problems
• Poor hole condition
Swapping out of drilling mud left below the pipe and cement
• Poor centralisation
• Abnormal pressure
• Subnormal pressure
• High temperature
• Shrinkage of cement.
Presentation Title
Cementing Problems
• Permeability after setting.
• Perforation of cement.
• Equipment, planning, and execution failures (people errors) and the quality of
cement and additives.
Presentation Title
Problem 1 (Poor displacement of mud)
Mechanism :
The volumetric fraction of the mud removed from the wellbore annulus by the
cement slurry is called displacement efficiency.
• High displacement efficiencies increase the probability that the set cement will
not contain channels of mud.
• Or that the cement will not have channeled through the mud.
• The type of flow regime in which the cement slurry and the mud being
displaced is dominant
Presentation Title
Problem 1 (Poor displacement of mud)
Solution:
The recognized flow regimes are:
(1) plug,
(2) laminar and,
(3) turbulent.
Presentation Title
Problem 1 ( Poor displacement of mud)
Plug flow cementation
• The plug flow technique is very efficient.
• It is limited to cementations of small volumes and where the mud in the hole is of low
density.
• The technique calls for Reynold's numbers of 100 or less,
• No cement slurry retarders or thinners or spacers.
Plug cementation variables
1- Nr ≤ l00
2- Low hydraulic horsepower
3- No spacer
4- Low Pressures
5- No retarders
6- Low Displacement rates
7- No thinner
8- Long cementation times
9- No friction reducer
10- Low circulating
Presentation Title
bottom pressure
Problem 1 (Poor displacement of mud)
• Rates places mud, spacer which should be used, and slurry which is usually thinned
(PV and YP are reduced) all into turbulent flow.
• Fully developed turbulent flow calls for Reynold's number of 3000 or more.
• In all cases the Reynold's number should be calculated with the power law equation.
• Primarily chosen because they require the shortest cementation times.
• Not chosen because of high circulating bottom hole pressures.
Presentation Title
Problem 1 (Poor displacement of mud)
• Has the smallest displacement efficiencies (75% and less) of the three flow regimes.
• Gives inadequate cementations.
• Should be avoided when possible.
• However, because of equipment limitations and poor planning, the technique is often
inadvertently used.
Presentation Title
Problem 2 ( Lost circulation )
Mechanism :
• Solution:
Reduce the density of the cement column and the circulating friction pressure
loss.
Presentation Title
Problem 3 (Bridges composed of cement filter cake)
Mechanism :
• Bridges from cement filter cake are formed on thick permeable beds and thereafter
until the cement sets.
• Once the cake grows to a point that it contacts the casing, it begins to support the
weight of the cement and mud above it.
• This in turn releases part of the pressure below the bridge which permits gas to
percolate through the cement.
Solution:
Presentation Title
Problem 4 (Swapping out of mud and cement below pipe)
Mechanism:
Casing or a plug back pipe is not run to the total depth of the well and the mud below
the pipe buoyantly rises into the annulus where the cement was circulated.
• While the mud is rising, the cement must be falling along side it; thus, mud and
cement are "swapping out.“
Solution:
• If pipe is close to the bottom of the hole (50 feet or so), a pill of a density equal or
slightly greater than that of cement may be circulated to the bottom of the hole prior to
the cementation of the pipe.
• If an up hole cement plug is to be set, the pipe is run one stand below the desired
location of the bottom of the plug and a very viscous bentonite pill is circulated.
• Thereafter, the pipe is raised one stand and the cement is circulated into place.
Presentation Title
Problem 5 (flash setting of cement)
Mechanism:
• Careful studies of flash setting of cement indicates that the mix water
was much harder (Mg, Ca, and Fe) than anticipated.
Solution
• Check the mix water and retard the cement as needed.
Presentation Title
Problem 6 (Cement can shrink and may fail to isolate zones)
Mechanism:
• Laboratory measurements have shown that cement can shrink as much as 5%.
Solution:
• Use non-shrinking cement.
• Non-shrinking cement has about 15% sodium chloride added to the base
cement.
Presentation Title
Problem 7 (Permeability of cement may cause an interzonal flow)
Mechanism:
Presentation Title
Problem 8 (Gas migration may fail to isolate zones)
Mechanism:
There are two mechanisms of gas migration:
• The first is that during the setting of the cement, pencil size (1/8") channels
form vertically allowing gas to flow either to the surface or to another zone.
• The second is that in inclined drill holes.
• The cement particles settle to the low side allowing a water (or nearly water)
channel to form on the high side of the hole.
Solution:
• The gas migration resulting from the first mechanism has not been totally
solved.
• Sometimes successful additives are latex flakes and alumina particles.
• The second mechanism requires careful planning of setting and circulating
times to eliminate long periods of quiescent unset cement in the hole.
Presentation Title
Problem 9 (A micro-annulus)
Mechanism
• Steel shrinks as temperatures are reduced.
• Pipe diameters decrease as pressures are reduced.
Solution
• One solution is to reduce the pressures within casing while the cement is
setting.
• This may be done by bumping the cement plugs with a light fluid and not
holding a surface pressure while the cement sets.
• Another is not to lower the pressure in the pipe at critical times.
Presentation Title
Problem 10 (Temperature retrograde of cement)
Mechanism
As temperatures approach 247° F, calcium silicate hydrate converts to crystalline
forms which are weak and permeable.
• If at least 35% fine silica is added then tobermolite is formed (at 247° F).
• Xonotlite crystals which are strong and moderately impermeable form at
temperatures of 302° F if at least 35% fine silica has been added.
Solution
• Use 35 to 50% by weight of silica flour to prevent the formation of weak and
permeable cement.
Presentation Title
Problem 11 (Perforation of cement mechanism)
Mechanism
Cement may shatter behind casing during perforation of the pipe
leaving the cement weak and permeable.
Solution
It has been found in the laboratory that cements with higher modulii of
elasticity give less shattering (neat cement).
Presentation Title
Problem 12
Solution
Presentation Title