You are on page 1of 7

ENI – IRAQ

ZUBAIR OIL FIELD DEVELOPMENT PROJECT

Method Statement for Fencing and Gates – PPG

Issued for
A EX-CO 00 03/11/2014 M. Al Saffar Dhiaa J. Alaa Kamal
Approval
AP Validity Rev.
Rev. Status number Prepared Checked Approved Contractor Company
No Date Description
By By by Approval Approval
Revision Index
Company logo and business name Project Name Company Identification

ZUBAIR OIL FIELD 00251900DAST66723


DEVELOPMENT
eni iraq b.v.
Job N. 210/2011/NR/ZU
Contractor logo and business name Contractor Identification

ZBR/90/W/--------CD/MS/011

Alstom Middle East, FZE, Dubai, UAE. Contract N. 210/2011/NR/ZU


Vendor logo and business name Vendor Identification

002519-PC-SAS-AP-008

Order N. 210/2011/NR/ZU
SHAMS AL SABAH GENERAL CONTRACTING CO. LTD.
Facility Name Location Scale Sheet of
ZUBAIR-PERMANENT POWER GENERATION ONSHORE N.A. Sheets
1/7
Document Title Supersedes N.

Method Statement for Fencing and Gates – PPG Superseded by N.


Plant Area Plant Unit
00
N.A.
Software: Microsoft Word 97-2003 File N° 00251900DAST66723_EXCO00_07.doc

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 2/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

REVISION HISTORY

Rev. Date Nr. of sheets Description


EXCO00 03/11/2014 07 Issued for Approval

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 3/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

INDEX

1. OBJECTIVE .................................................................................................................................... 4

2. DEFINITIONS ................................................................................................................................. 4

3. REFERENCE DOCUMENTS ......................................................................................................... 4

4. STATUS OF WORK ....................................................................................................................... 4

5. RESOURCES ................................................................................................................................. 4
5.1. PERSONNEL .......................................................................................................................... 4
5.2. EQUIPMENT .......................................................................................................................... 5
6. MATERIALS ................................................................................................................................... 5

7. PROGRAM OF WORK ................................................................................................................... 5


7.1. MOBILIZIATION ..................................................................................................................... 5
7.2. EXCAVATION......................................................................................................................... 5
7.3. PREPARATION OF INSTALLING THE FENCE .................................................................... 5
7.4. INSTALLING THE FENCE ..................................................................................................... 5
7.5. HIGH TENSILE CABLE FENCES .......................................................................................... 6
7.6. BARBED WIRE....................................................................................................................... 6
7.7. INSTALLING GATES.............................................................................................................. 6
7.8. DEMOBILIZIATION ................................................................................................................ 7
8. QUALITY CONTROL ..................................................................................................................... 7

9. HSE ................................................................................................................................................. 7

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 4/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

1. OBJECTIVE
This work method covers earth works for Zubair Permanent Power Plant Generation Plant
(ZPPGP), in Zubair Oil Field Development Project, Basrah, Iraq

2. DEFINITIONS

For purpose of this work method, the following definition shall apply:

PROJECT ZUBAIR OIL FIELD DEVELOPMENT

COMPANY ENI IRAQ

CONTRACTOR ALSTOM MIDDLE EAST

SUBCONTRACTOR SHAMS ALSABAH GENERAL CONTRACTING CO. (SAS)

3. REFERENCE DOCUMENTS

2.1. Approved project drawings


2.2. (00250600BASG10006 – GENERAL SPECIFICATION FOR SITE PREPERATION /
EARTHWORKS).
2.3. (00251900DAST60201 - SITE LEVELLING - TECHNICAL SPECIFICATION).
2.4. (00251900DAST66717 - METHOD STATEMENT FOR CIVIL WORKS).
2.5. (00251900DBSS75050 - CIVIL WORKS FIELD QUALITY PLAN – PPG).

4. STATUS OF WORK

The work shall start based on a completion of site leveling and backfilling.

5. RESOURCES

5.1. PERSONNEL

• Civil Engineers.
• Surveyor.
• Civil Foreman.
• Skilled Labours.
• Skilled Equipment Operators.

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 5/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

5.2. EQUIPMENT

• Surveying Instruments.
• Excavator.
• Hand compactor.
• Water tanker.
• HIAB crane.

6. MATERIALS
All material for chain-link fencing and gates shall conform to the requirements of the project
drawings and specifications.

7. PROGRAM OF WORK

7.1. MOBILIZIATION

Mobilization will be carried out within 2 days from the date of receiving the acceptance to
commencement the works from the company.

7.2. EXCAVATION

Excavations shall be done by hand excavation or backhoe, excavations shall be carried out
under supervision.
Excavation limits shall be done according to project drawings. Excavated trenches shall be
barricaded to prevent any person/any excavator and other construction vehicles on site
from falling into the trench or the excavation.

7.3. PREPARATION OF INSTALLING THE FENCE

Once the earthwork is completed, inspected and approved the preparation of the fence will
commence.
The Contractor shall locate the position of the work by establishing and marking the fence
line.

7.4. INSTALLING THE FENCE

7.4.1 INSTALLING POSTS


All posts shall be set plumb, true to line and grade. Terminal posts, defined as end,
corner, pull or gate posts, shall be set in concrete. The concrete footing shall be
uniform thickness around the post. Distance of post shall according to the
construction drawing.

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 6/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

7.4.2 BRACING
All corner, end, pull, and gate posts shall be braced as shown on the drawings. Pull
posts shall be used at sharp breaks in vertical grade or as directed by the
Consultant.

7.4.3 INSTALLING FABRIC


Fabric shall be securely attached to end, corner, gate and pull posts in accordance
with manufacturer’s recommendations. All fabrics shall be taut before attaching to
line posts or tension wire. High and size for the fabric should follow as per
construction drawing:

7.4.3.1 After rolling out the chain link and weaving the rolls together, ‘hook-up’
one end. Make sure the nuts are on the inside of the fence so they
cannot be removed from outside the enclosure.
7.4.3.2 Pulling the chain link tight by hand to the other end.
7.4.3.3 Stretch the fence using stretch tools. Do not over tighten.
7.4.3.4 Hand stretch the small section of chain link left between the come-a-
long and terminal post by hand. Slide the tension bar into the mesh and
make the last hook-up. Once all bolts are in place, remove the
stretching tools.

7.5. HIGH TENSILE CABLE FENCES

7.5.1. High-tensile cable placements on the end and corner post have been set.
7.5.2. Stretching and fastening the cable by using tension tools.

7.6. BARBED WIRE

The barbed wire shall install on the support arm which is be at a 45-degree angle, and shall
be fitted with clips, slots or other device for attaching three lines of barbed wire to the arm.
The barbed wire arm shall be sufficient strength to withstand a weight of the barbed wire
without causing any permanent deflection of the arm. Each strand of barbed wire shall be
pulled taut to remove all sag before the strand is attached to the extension arm.

7.7. INSTALLING GATES

The gates shall be erected and hung on gate fittings as shown in the drawings. Gates shall
be erected to swing in the direction indicated and shall be provided with gate stops, as
specified or as shown on the drawings.

7.7.1 Gate posts to be installed in the same manner as mentioned above, used for corner
and straining posts.
7.7.2 Gates to be attached to gate posts as per company specifications.

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent
Contractor Document Company Document Originator Document Identification AP Revision Index Sheet of
Identification Identification Rev. Sheets
No. Validity Rev.
Status No.

Alstom Middle East, FZE. 7/7


eni Iraq b.v.
A EX-CO 00
ZBR/90/W/--------CD/MS/011 002519-PC-SAS-AP-008
00251900DAST66723

7.8. DEMOBILIZIATION

As soon as the works are completed, the whole machineries and equipment's which are
not necessary for the successor activity will be demobilized from work site.

8. QUALITY CONTROL
Tests and inspections will be made in accordance to the documents & specification according to
project specifications item 3.

9. HSE
9.1 Work to be carried out in a safe manner and accordance with the HSE program and Safety
Policy. Site operatives shall be well inducted for the safe operation of the machineries,
equipment and tools to be used.
9.2 Personnel protective equipment will be used by all staff and labours. The minimum
personnel protective equipment is as follows:

• Safety Helmet.
• Safety footwear.
• Eye protection.
• Any other equipment required by the site operator or deemed necessary by the
task.
9.3 All regulation implemented by authority at site will be considered.
9.4 Proper barricades and traffic signs shall be placed around the work site location wherever
required.

Subject to Contract, this document is property of eni Iraq BV.


It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent

You might also like