Professional Documents
Culture Documents
CONSTRUCTION
BY
VINEELA KAGITHA
(12071A01B4)
INTRODUCTION
Mechanization or mechanisation is the process of changing from working
largely or exclusively by hand or with animals to doing that work with
machinery.
• A project comprises various activities of diverse nature. Execution of each
activity should be planned meticulously to ensure sequential execution in
time.
• There is no alternative to adopting mechanized construction methods to
achieve more in less time.
• Once the decision of deployment of construction equipment is taken ,
required construction equipment need to be identified.
• Example : earthmoving construction equipment , handling and lifting
equipment's, aggregate and concrete production equipment.
GENERAL CONSIDERATIONS
A construction project may be of two types:
• Linear project (involving concept, design, procurement, and construction)-
traditional approach
• Fast-tracked project- design and build
• On a fast tracked job, design and construction being almost
simultaneously. Construction work is started even when the design
engineers are working on the foundations of the structures.
• This happens when the completion time is considered as sacrosanct
and competitive bidding is not essential
• Design and construction work are set on parallel tracks.
Disadvantage of fast-tracked project are:
a) Input for designing may not be available in time as a result of which
reconstruction may be necessary to comply with the input when received ,
and
b) Less control over costs
• Time of execution has to remain within the agreed construction time schedule.
DEPLOYMENT OF CONSTRUCTION
EQUIPMENT
The cost of construction is a major factor in all projects, therefore there
many factors influencing the construction cost such as labour, material,
construction equipment, profit etc. costs of construction equipment
ranges from 25% to 40% of total project cost.
Deployment of construction equipment is done for the reasons as
mentioned below:
• Larger output
• Cost-effective implementation
• For execution of work that is not feasible by manual efforts or when
deployment of construction equipment may help in doing the work
more cost efficiently.
• To reduce the amount of heavy manual work which would cause
fatigue, thereby allowing manual efforts to be more productive.