PROJECT BUILD CO.

‫مؤسسة اعمار المشاريع‬


(GENERAL CONTRACTORS) (‫)مقاولتا عامة‬

HSE : 171
Date : 11-02-2019

To
Engr.Syed Shahabuddin
Project Manager
PBC Co Ltd
Al-Salam Hospital

With Reference to DAR Engineering letter Ref # ASH-DAR-PBC-GEN-LTR-869 Listed below


are the actions taken to rectify those problems noticed by DAR Engineering at site.
1. ASH- DAR –PBC- HSE –LTR-855 – Safety & housekeeping (HSE-NCR-131) on 02/01/2019 is
in progress as debris and wastes are removed on daily basis, waste materials staked will be
allotted for waste material storage area.
2. DAR Safety Corrective Action Request –ASH-SCAR-0064 on 19/01/2019 had been
completed –See attached copy of photos.
3. DAR Safety Corrective Action Request –ASH-SCAR-0066 on 24/01/2019 had been
completed – see attached copy of photos.
4. DAR Safety Corrective Action Request –ASH-SCAR-0067 on 29/01/2019 had been
completed Except TUV for Man Lift operator, This TUV will be renewed in due course once
financial problem of PBC Company is solved.
5. DAR Safety Corrective Action Request –ASH-SCAR-0068 on 04/02/2019 had been
completed –See attached copy of photos.
6. ASH- DOR – HSE 002 – Daily HSE Observation Report – 19/01/2019 had been completed -
See attached copy of photos.
7. ASH- DOR – HSE 002 – Daily HSE Observation Report – 20/01/2019 had been completed -
See attached copy of photos.
8. HSE Weekly Walk Through findings -29/01/2019 is in progress
This is for your kind information

With Regards and thanks


Nackeeran Desingu
HSE Department
PBC Co Ltd

8945408 : ‫ – فاكس‬8644295 : ‫ – المملكة العربية السعودية – تلفون‬31952 ‫ الخبر‬79619 ‫ب‬.‫( – ص‬45342) ‫ – رقم الغرفة التجارية‬2051020158 ‫تا‬.‫س‬
C.R. 2051020158 – C.C. No. (45342) - P.O. Box 79619 Al Khobar 31952, Kingdom of Saudi Arabia Tel. No. 864-4295 Fax. No. 894-5408
PROJECT BUILD CO.‫مؤسسة اعمار المشاريع‬
(GENERAL CONTRACTORS) (‫)مقاولتا عامة‬

HSE : 174
Date : 11-02-2019

To
Engr.Syed Shahabuddin
Project Manager
PBC Co Ltd
Al-Salam Hospital

With Reference to ASHP and DAR HSE NCR # ASH – DAR-NCR-HSE –


NCR-131, Housekeeping work is in progress and is continued on daily basis.
Unwanted materials are removed from each floors and those wanted materials
are properly arranged and stocked in order to prevent slip and trip hazards.
Combustible materials like which are stacked are provided with fire
extinguishers to prevent fire hazards. We also provided daily housekeeping
program which is in progress.

This is for your kind information.

With Regards and Thanks

Nackeeran Desingu
HSE Department
PBC Company Ltd
Al-Salam Hospital project.

8945408 : ‫ – فاكس‬8644295 : ‫ – المملكة العربية السعودية – تلفون‬31952 ‫ الخبر‬79619 ‫ب‬.‫( – ص‬45342) ‫ – رقم الغرفة التجارية‬2051020158 ‫تا‬.‫س‬
C.R. 2051020158 – C.C. No. (45342) - P.O. Box 79619 Al Khobar 31952, Kingdom of Saudi Arabia Tel. No. 864-4295 Fax. No. 894-5408