HSE Environmental Activities Onsite & Scaffolding issue.
Before
After
4
T.U.V. Certificate & I.D. of scaffolding inspector
Responsible for Internal & External Scaffolding Work at hospital and parking building
5
Daily rectification of erected scaffolding on site
6
Tagging system of scaffolding on site
7
Tagging system of scaffolding on site
8
MONTHLY ACCOMPLISHMENTS JANUARY 2019
SN Activity ACCOMPLISHMENTS
Total Safe Total Man hours till end of December 2018 = 2,294,410
1
man hours (UPDATED DEC. 2018)
Monthly
General Toolbox Talk conducted this month December 2018
2. General
General Toolbox Talk conducted this month January 2019
Toolbox Talk
Man-counting
3. Daily Actual Manpower Counting On-Site By month of January 2019
9
MONTHLY ACCOMPLISHMENTS JANUARY 2019
SN Activity ACCOMPLISHMENTS
Fire extinguisher Fire extinguishers was inspected and checked at all locations.
7. Monthly inspection
refilling of pressurised fire extinguisher
8. Record Keeping Records for Monthly report, Toolbox talk record, Safety Violation
report , PPE issuance record , Washroom cleaning log ,
10
Monthly Safety Statistics Report
11
Monthly general toolbox talk & awarding of Certificate of appreciation
(January 2019)
12
Monthly general toolbox talk & awarding of Certificate of appreciation
(December 2018)
13
January - 2019 Daily Actual Man-counting On-site
Pest Control initiated inside & outside @ Site Offices of (Dar Engr./Client & PBC)
Pest Control initiated @ Hospital and Parking Building. (07,01,2019)
Pest Control initiated inside & outside @ Site Offices of (Dar Engr./Client & PBC)
Pest Control initiated @ Hospital and Parking Building. (07,01,2019)
Removal of garbage waste around site offices on daily basis.
Removal of waste/debris of all collection point @ Hospital Building
& Parking Building on daily basis.
18
HSE daily activities Onsite @ (Hospital & Parking building)
19
Before and after of housekeeping at hospital building. (H.B)
Before
After
After
20
Before and after of housekeeping at hospital building. (H.B)
Before After
21
Segregation of materials near fence perimeter in project premises .
22
Removal of waste materials in collection point #2 & kitchen area @ Hospital Building.
23
Clinic First Aid Facilities
New medicine & first aid materials
.
First Aid Facility in Clinic Room Monthly Stocks Medicines
24
FIRST AID MEDICINE CHECK LIST
25
AMBULANCE DAILY INSPECTION CHECK LIST
26
Fire Extinguisher Monthly Inspections
27
Fire Extinguisher Monthly Inspections
28
2019 1st Weekly Site Visit
29
Stoppage of unsafe danger works on-site
30
Inspection for heavy equipment works on-site
31
END