Current Activities
DST / Wireline / Well Flow
Things to Do/Follow-Up
Rig move is ahead, road risk assessment done shared with office, and pre-rig move meeting is pending
which will be done once movers are on location.
Rig Audit by OMV Vienna is expected. Pre-hire rig audit checklist. (Updated Copy on the board).
Company man will finalize the checklist but HSE has to facilitate him.
Mast beams TDS and draw works motors will be changed on rig move.
Cat 3 inspection of mast is planned during the move.
Rescue Drill Procedure from Monkey Board received and conducted. We will do it on next well spud.
We have started some extra gifts of appreciation for the people who are writing regularly, for that Franz
arranged BP wrist apparatus and some of the dairies, last time we choose card from catering, time we
have good number of cards from security guards. In one of the draw we have 4 BP apparatus are left
which we plan one for every month.
Well end report I started but most of the data will be load after rig release. The day rig will be released we
will make reports of the Latif-14.
MPI of TDS is expired, new TDS arrived on location but Saxon has to provide the scan copy of each
certificate of the new TDS.
We will be having ISO 14001 Audit in March. Internal environmental Audit conducted on 26th December
2015 Report submitted to Adnan & copy is on desktop EMS folder.
Best Strive cards, management meeting and management walk around for January are done.
Best Strive card will be given with the recommendation of company man.
Web slings were cut and disposed off as per OMV standard, we will stick to same standard.
Inspections:
Geronimo & line tested by 3rd party, report submitted to Adnan bahi
Lifting gear register updated and fall arrestor certificates are provided by Saxon ( mail box)
ATR:
ATR need to update and close out open points on target date. Owner of the ATR is DSV but we have to
update and send to company man for his approval.
Before closing ATR points please discuss with company man.
We will keep send ATR every Sunday as we were doing before.
FR-QP03.01-4.9-01 1
HANDOVER NOTE: “WELCOME BACK”
Meetings:
Daily morning meetings are 8:45 AM with company man.
Daily Conference Call 9:00 AM
Weekly meeting done
Reports:
Daily QHSE Report:
We have to submit the report before calling off the day to co man, after adding information from SLDC
QHSE report which they will email to you about 05:45hrs and POB will be sending by Rig Doctor. Made
few changes as per drilling manager instruction we have to add stop cards details in report which we send
to everyone in the list.
(Please Send POB to Adnan on daily basis) No one is allowed to stay on site more than 35 days
maximum, only catering crew can stay up to 45 days, Security 60 days.
Man-hour calculator and vehicle record is in HSE reporting folder, kindly use it to have proper man hours
and vehicle record.
FR-QP03.01-4.9-01 2
HANDOVER NOTE: “WELCOME BACK”
(Detail in mail box) Make sure 3rd party certification is valid and with proper serial number to avoid any problem in
future in case of any incident.
Medical certificates folder has certificates of service companies.
Job ticket
Put my 14 days of Waqar Azeem (01st Feb to 14th Feb, 2016)
Computer Password
Omvrut1234
H2S Equipment Details
Welcome to paradise
Best Regards
Waqar Azeem
Mobile: 0321-3326278
Waqar.azeem@rutledgeservices.com
FR-QP03.01-4.9-01 3