Project Action Plan and Timetable

Wee Date Week Activity / What you are intending Resources / What you will need
k Beginning to do - including independent to do it - including access to TV
study studio & edit suites

Printed version of brief


1 25/02/19 FMP Brief introduced
Studying of the brief
Developing ideas

Printed version of project


2 04/03/19 Project proposal template is proposal
introduced
Completing 500 word proposal

Google forms
3 11/03/19 Conduct a survey and send to 30
peers

Pod rooms
4 18/03/19 Conduct a focus group with peers
and an expert interview with a
teacher

Google forms
5 25/03/19 Analyse survey findings

Edit suites
6 01/04/19 Complete secondary research

iMac
08/04/19 Spring break
& Complete relevant pre-production
15/04/19

DSLR Camera
7 22/04/19 Filming of short film Tripod
Recorder

Edit suites
8 29/04/19 Edit film
Edit suites
9 06/05/19 Evaluation and improvements

10 13/05/19 DEADLINE Friday 16th May