PETRONAS GAS DEHYDRATION PLANT PHASE 2

TECHNICAL REQUISITION FOR


ENGINEERING SERVICES
REV.: A Attachment-3

ATTACHMENT-3

DEVIATION LIST

DEVIATIONS LIST
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3

Sr.No Document Clause Abstract of Description Reason/ Alternate


No. & Title No / Requiremen of Deviation Justification for Proposal
Section t against Deviation
/ Para which
deviation is
presented
1 GFDP- 5.1 Add Chemical
COM-51-PP- cleaning Standard
SP-99-0006 procedure Procedure
Specification shall be
for Piping approved by
Testing and Corrosion
Completion_ Specialist.
Rev.0
2 GFDP- 5.1 Add Chemical
COM-51-PP- inhibitors,
SP-99-0006 solubility Standard
Specification agents, Procedure
for Piping descaling
Testing and agents shall
Completion_ be approved
Rev.0 by Corrosion
specialist
PETRONAS GAS DEHYDRATION PLANT PHASE 2
TECHNICAL REQUISITION FOR
ENGINEERING SERVICES
REV.: A Attachment-3