Professional Documents
Culture Documents
: EGP3-00-SP-061-605-001
Notes
i.) Revisions numbers shall be A, B, C, etc. up through the issue for Invitation to Bid.
iii.) Revisions after the issue for Invitation to Bid shall be 1, 2, 3, etc. Any revisions made after
Revision 0 shall be denoted by a vertical line in the left hand margin against the revised text.
iv.) A brief description of the key changes made in each revision shall be included on this page.
A Based on EGP1-03.19
1.1 Scope 4
1.2 Definitions 4
2.0 REFERENCES 4
3.0 GENERAL 5
4.1 Precleaning 7
4.3 Neutralisation 8
4.4 Passivation 8
5.1 Scope 8
6.0 SAFETY 10
1.1 Scope
This specification covers scale removal from inside carbon steel pipe by acid
pickling and field cleaning of stainless steel lube oil system piping in completed
piping systems for the onshore facilities associated with the Escravos Gas
Project.
1.2 Definitions
Definitions used in this specification are as follows:
2.0 REFERENCES
Chemical cleaning of piping shall be carried out in accordance with the requirements of
this Specification, the project piping drawings and with the latest editions of the
following codes and Project Specifications:
The following documents are hereby referenced and are considered part of this
specification:
API 614 Lubrication, shaft sealing and control oil systems for
special purpose applications.
2.4 Any conflict, inconsistency or ambiguity between the purchase order, material
requisitions, this Specification, drawings, national codes or project specifications
referenced herein, shall be referred to COMPANY for resolution.
3.0 GENERAL
3.1 CONTRACTOR shall submit descaling and cleaning procedures and schedule
to COMPANY for approval. CONTRACTOR shall also determine the
descaling/cleaning operation required for any given system unless otherwise
directed by COMPANY.
3.2 Descaling /Cleaning shall only be carried out on fabricated piping systems which
have been pressure tested and accepted by COMPANY.
3.3 CONTRACTOR shall maintain a log of each item, pipe and system which
has been descaled/cleaned.
● chemical cleaning
● passivation
● oil flushing
● neutralisation
● drying
3.6 CONTRACTOR will need to have a ready supply of cleaning media and
equipment, including but not limited to the following:
● Nitrogen gas
● Safety equipment
● Suitable drainage system(s) for the removal of water, oil and chemicals.
3.7 Prior to pipe cleaning, all control valves, pressure gauges, flow orifices,
transmitters and other valves and instruments that may be damaged by the
cleaning operation, shall be removed, isolated or by-passed.
3.8 During cleaning operations, appropriate precautions shall be taken to ensure that
debris is not flushed into excluded vessels and equipment or "dead ends".
3.9 Piping in cold service shall be thoroughly dried with clean, dry air or with nitrogen
after cleaning.
3.10 To avoid pipe stress during pipe cleaning operations, CONTRACTOR shall install
temporary spool pieces and supports where required.
3.11 Temporary filters or strainers required during pipe cleaning operations shall be
supplied and installed by CONTRACTOR. A complete record as to the location of
these filters and strainers shall be maintained by CONTRACTOR.
3.12 Permanent process strainers with properly sized mesh, may be used for line
clean-up.
3.13 The descaled and cleaned pipe shall be free of scale, rust, weld flux, oil, grease
and any other foreign material.
3.14 After cleaning, piping systems that will not promptly be put into service shall be
properly protected against further corrosion and adequately sealed against
ingress of foreign matter. Methods should be suited to the particular pipe material
(including valve packing and elastomers), operating service and length of time
before going into service. The methods include:
● Oil fill
3.15 CONTRACTOR is responsible for and shall have a contingency plan and
equipment available to clean up any chemical leaks. Disposal of chemical
effluent shall be in compliance with statutory requirements. Storm drains in the
vicinity of chemical cleaning operations shall be sandbagged prior to chemical
cleaning commencing. COMPANY shall be notified immediately in the event of
The descaled and cleaned pipe shall be equivalent to the surface described by the
Steel Structures Painting Council as SP-8.
4.1 Precleaning
Prior to chemical cleaning a precleaning solution shall be circulated through the
system to ensure that all oil and grease is removed from the pipe.
After removal of the precleaning solution the system shall be rinsed with clean
potable quality fresh water until the pH of the effluent rinse is within one pH unit
of the fresh rinse water.
Water for flushing stainless steel piping shall have a maximum chlorine content
of 50ppm.
4.2.4 If a dipping process is used, before dipping all piping component /spool
identification marks are to be recorded to the satisfaction of COMPANY.
Immediately on completion of pickling/abrasive blasting, neutralising and
passivation the recorded markings and any protection of etched
markings shall be reinstated in accordance with Project Specification
EGP3-3.03.
4.2.5 Use of ammoniated citric acid is a convenient procedure, that will allow
both pickling and passivating with the same solution.
4.2.6 Pickling solutions shall not be allowed to contact any parts of process
machinery.
4.2.8 After pickling the acid solution shall be drained under a nitrogen purge.
4.2.9 After removal of the acid solution the system shall be rinsed as
described in paragraph 4.1. The rinse shall be drained under a nitrogen
purge, except as noted in paragraph 4.2.4.
4.3 Neutralisation
4.3.1 After pickling a neutralising solution shall be circulated to remove all traces
of acid from the system. The neutralising solution shall be drained under
a nitrogen purge.
4.3.2 After removal of the neutralising solution the system shall be rinsed until
all traces of acid and neutralising solution have been removed. The rinse
shall be drained under a nitrogen purge.
4.4 Passivation
4.4.1 To minimise further corrosion of the descaled pipe, a phosphate coating
shall be applied to the pipe. Do not flush with water.
4.4.2 The system shall then be drained and thoroughly dried using dry air or
nitrogen and be tightly sealed. (Refer to paragraph 3.8).
5.1 Scope
This section specifies requirements for field cleaning of the complete stainless
steel lube oil systems associated with gas turbine engines and turbo-expanders.
Conformity to the criteria for lube oil system cleanliness given in API 614,
Chapter 2, paragraph 4.3.3.7.1 and 4.3.3.7.2 shall be demonstrated to
COMPANY.
All surfaces in contact with oil shall be cleaned to a white metal finish to comply
with Steel Structure Painting Council SP-8.
5.2.4 List of temporary pumps, piping and screens showing location and
identification.
Any sections which are not visible shall be checked by pulling a clean lint-free
cloth through the line and inspecting the cloth for debris.
Flow restrictions including orifices, check valve flappers, flow control valve
plugs, and oil filter cartridges shall be removed prior to flushing.
5.6.4 Fill the system with low-viscosity lube oil, which has the same
specification as the machines service oil for the flushing operation.
5.6.5 Oil flushing velocity in the piping oil to the equipment shall be at least
twice the normal velocity. If the existing oil pumps cannot provide
adequate circulation temporary circulation pumps shall be installed for the
flushing operation. The oil flush rate shall be monitored.
Proper velocity through the oil path being flushed can be achieved only by
selectively closing off parallel paths to force enough oil through the path
being flushed.
5.6.7 The lube oil systems shall be flushed in a systematic sequence to clean it
sequentially from inlet to outlet. This will prevent contaminating a section
of the system that has already been flushed.
5.6.8 Oil flushing shall continue for a minimum of 4 hours in each circulation
loop or until COMPANY acceptance.
5.6.9 Drains, instrument connections and vents shall be blown down once every
8 hours during the flushing procedure. Some sections will be flushed less
than a full shift. Such sections shall have their drains blown down.
5.6.10 Valves shall be exercised from as fully closed as possible to fully open,
slowly and repeatedly. This will create turbulence in the valve bonnet
cavities, which will help to flush them. COMPANY shall inspect.
6.0 SAFETY
● Safety showers
● Material safety data sheets shall be available for all chemicals being used.
● The working area shall be cordoned off with red tape with "Keep Out"
warning signs every 15 metres.
● Hoses shall have a minimum working pressure of 17.5 barg and shall be
chemically compatible with the cleaning solutions.
● The system shall be pressure tested to a minimum of 6 barg and all hose
and temporary fittings checked for leaks. Any leaks shall be repaired prior to
injecting any chemical solutions.