You are on page 1of 4

Document Review Sheet

From: KEIL To: PETROJET


Contract: KEIL/SIBA/2015/C-051
Document Title: MCC for Debutanizer
Document No.: C-051-390-MCC-TR2-03-002 Revision:
Touchstone Document No.:
Please respond by: (Refer to Transmittal for Return Date)
The document as listed above has been reviewed and has been found to be:

Reviewed - no comment. Revise and re-submit. Revise and re-submit.


Work may proceed subject to incorporation of Work will NOT proceed.
comments.

*(Tick as appropriate)

Sl. No. Comments (Identify Section/Page/Paragraph) Response


Instrument
Calibration report for 02-PT-2433D (P&ID: 383-244) is missing. Noted and Attached in sec 11.2
1 Calibration report shall be added in this MCC dossier
Noted and Attached in sec 11.1
02-PT-2433D (P&ID: 383-244), R0-2533 (P&ID: 383-244), RO-2635B
2 (P&ID: 383-243), RO-2636B (P&ID: 383-243) are missing in this MCC
dossier. These instruments shall be included in the list of instrument.

3 Broken glass for 02-PI-2635C. Coverd in MPL Point NO.8150

Electrical
No Comments

Page 1 of 4
Classification: General
Sl. No. Comments (Identify Section/Page/Paragraph) Response
Mechanical/Piping
No Comments

Civil
1 Documents of T 2533 to be provided. Noted and Attached in sec 5

Name: Dilio/Suresh/Munther/Alaa Name: Ehab


Date: 22/05/2018. Date:29/5/2018.
Note: Please add/ insert rows for additional comments/ response(s).Do not add additional column.

Page 2 of 4
Classification: General
1

evise and re-submit. Review not Required - for


ork will NOT proceed. information only.

Conclusion

Closed.

Closed.

Closed.

Page 3 of 4
Classification: General
Conclusion

Closed.

Name: Dilio/Alaa
Date: 4/6/2018.