Notes For Electric Network for Honeymoon Hardscape Rev 02

1. The Drawing are not to scale with the Architect shop drawing and according to the
reality
2. Modify Branch circuit according to sketch
3. Re-Calculate Voltage Drop and Short Circuit analysis
4. Re-Calculate Power balance Sch.
5. All manholes should be recalculated according to Electric Codes to justify both the
minimum clearance between Cables and the Filling Ratio of Manholes including (1
meter Spare) .
6. Place 2 manholes under the Main panel size 40 cm*40 cm.
7. Duct banks Are Allowed (Code B) to be executed according to Notes. (PVC Heavy
Gauge conduits only )‫)) مواسير فقط‬
8. The Legend should be placed in Electrical network Rev 01.
9. Lux Calculation Should be Calculated and Submitted before the Drawing be
approved. For Both Bollards and Uplights Results including Luminance Curve and
Tunnel Geometry
10. Manholes and Conduits should be fastened to avoid moment of inertia effects.
11. Power balance should be recalculated.
12. Submit clean Copy after modify drawing according to sketch
13. All works should carried out according to Egyptian Code of electricity and the
requirement of South Cairo Electricity Distribution Company (SCEDC)
14. Full coordination with other disciplines