You are on page 1of 1

Dated: 25th Feb.

, 2019
NOTE SHEET
SUBJECT:TRANSFER OF MAINTENANCE OF COROLLA XLi (1 NO), MEHRAN (1 NO),
BOLAN (1 NO.) & 09 NOS. BIKES FROM PACKAGE GL-09 TO GL-16 OR
KARACHI PACKAGE OR MAIN OFFICE ESTABLISHMENT.
01. Following vehicles were procured/ maintained against GL-09 Package.

Sr. Particulars Vehicle Numbe Remarks

I Corolla XLi BKX 393 Manager Technical/ Q.A

II. Mehran BHJ 459 P.E

III. Bolan CW 9750 Administration/ Project


Duties
KKX-0520
KKX-0532
KKX-0535 Provided to newly
KKX-0539 Appointed Junior Staff
IV. 9 Nos. Bikes KKX-0542 (KIDCL)
KKX-0547
KKX-0549
KKX-0553
KKX-0556

02. As the Package GL-09 (Construction Of Command And Control Building)


completion date 30th November, 2018 has passed. Further, maintenance of above vehicles
are not possible from Package GL-09.
03. It is therefore, requested to transfer the maintenance of above vehicles from
GL-09 to Karachi Package OR main office establishment except Sr. I which may be shifted to
GL-16

04. Submitted for approval, please.

Planning Engineer
05. Manager Q.A

06. CHIEF ENGINEER

07. GM (F&A)/CFO

08. CEO