Shree Kranti Sugar & Power Ltd.

Work Progress Report Up to 20 June 2018 Date :- 20/06/2018

Sr. Section Work Completed


No.
2 Boiler
Boiler no. 2 1) Staging for external cleaning completed.
2) All internal dismantling completed
3) Steam drum and mud drum cleaning Completed.
4) All header Cleaning
5) Feed Line dismantling completed.
6) All valves dismantled, overhauling remained.
7) External cleaning started at 10/06/2018.
8) Brushing will be started on 1/07/2018.
Boiler no. 1
1) Staging for external cleaning completed.
2) Internal dismantling Work Remained.
3) External cleaning started at 15/06/2018.
4) Brushing will be start on 01/07/2018.
.
Boiler no 1 & 2 1) Both Boilers ID & FD Fans Motor dismantled.
ID, FD & Feed pump 2) Both Boilers ID & FD Fans dismantled.
3) Feed pump no-2 valve dismantle.
4)

Section Engineer
Shree Kranti Sugar & Power Ltd.
Work Progress Report 20 June to 11 July 2018 Date :- 13/07/2018

Sr. Section Work Completed


No.
2 Boiler
Boiler no. 2
1) All valves dismantled Completed.
2) External cleaning completed.
3) Tube Brushing Completed.

Boiler no. 1
1) Internal dismantling Work completed.
2) All valves dismantled Completed.
3) External cleaning completed.
4) Tube Brushing Completed.
.
Boiler no 1 & 2 1) Both Boilers ID & FD Fans Shaft Dismantled.
ID, FD & Feed pump 2) Boiler No-1 ID fan welding work start.

Section Engineer
Shree Kranti Sugar & Power Ltd.
Work Progress Report 11 July to 19 September 2018 Date :- 19/08/2018

Sr. Section Work Completed


No.
2 Boiler
Boiler no. 2
1) IBR valves Grinding 100% work complete.
2) Vale testing work complete.
3) ID & FD Fan Ducting repairing Work complete.
4) IBR repairs work in progress.
5) Safety vale Overhauling work complete.
6) 50 % IBR valves Fitting work complete.

Boiler no. 1
1) IBR valves Grinding 100% work complete.
2) Vale testing work complete .
3) ID & FD Fan Ducting repairing Work complete
4) IBR repairs work in progress.
5) Safety vale Overhauling work complete.
6) 50 % IBR valves Fitting work complete.

.
Boiler no 1 & 2 1) Feed pump Overhauling work in progress.
ID, FD & Feed pump 2) FD Fan Fitting work complete.

Section Engineer
Shree Kranti Sugar & Power Ltd.
Work Progress Report 20 June to 11 July 2018 Date :- 04/08/2018

Sr. Section Work Completed


No.
2 Boiler
Boiler no. 2
7) Open Inspection Done.
8) IBR valves Grinding 50% work complete.
9) IBR repairs work Enquiry prepared.
10) Boiler Bricks work enquiry prepared.

Boiler no. 1

1) Open Inspection Done.


2) IBR valves Grinding 50% work complete.
3) IBR repairs work Enquiry prepared.
4) Boiler Bricks work enquiry prepared.

.
Boiler no 1 & 2 1) Feed pump Motor Dismantle And send to power House.
ID, FD & Feed pump 2) Boiler No-1 ID fan welding work Complete.

Section Engineer