November 2011
Transmission Line and Substation Components Appendix B
1 TABLE OF CONTENTS
2 1.0 PROJECT FACILITIES ........................................................................................................ 1
3 1.1 Transmission Structures.............................................................................................. 1
4 1.1.1 Types of Transmission Line Support Structures .............................................. 1
5 1.1.2 Structure and Conductor Clearances .............................................................. 8
6 1.1.3 Structure Foundations ..................................................................................... 8
7 1.2 Conductors .................................................................................................................. 9
8 1.3 Other Hardware ......................................................................................................... 10
9 1.3.1 Insulators ....................................................................................................... 10
10 1.3.2 Grounding Systems ....................................................................................... 10
11 1.3.3 Minor Additional Hardware ............................................................................ 11
12 1.4 Communication Systems........................................................................................... 12
13 1.4.1 Optical Ground Wire ...................................................................................... 12
14 1.4.2 Communications Stations .............................................................................. 12
15 1.5 Access Roads ........................................................................................................... 13
16 1.6 Substations................................................................................................................ 21
17 1.6.1 Substation Components ................................................................................ 21
18 1.6.2 Distribution Supply Lines ............................................................................... 22
19 2.0 SYSTEM CONSTRUCTION .............................................................................................. 23
20 2.1 Land Requirements and Disturbance ........................................................................ 23
21 2.1.1 Right-of-Way Width ....................................................................................... 23
22 2.1.2 Right-of-Way Acquisition ............................................................................... 25
23 2.1.3 Land Disturbance .......................................................................................... 26
24 2.2 Transmission Line Construction ................................................................................ 32
25 2.2.1 Transmission Line System Roads ................................................................. 32
26 2.2.2 Soil Borings ................................................................................................... 34
27 2.2.3 Staging Areas ................................................................................................ 34
28 2.2.4 Site Preparation ............................................................................................. 35
29 2.2.5 Install Structure Foundations ......................................................................... 35
30 2.2.6 Erect Support Structures ............................................................................... 36
31 2.2.7 String Conductors, Shield Wire, and Fiber Optic Ground Wire ..................... 37
32 2.2.8 Cleanup and Site Reclamation ...................................................................... 39
33 2.3 Communication System ............................................................................................ 39
34 2.3.1 Communication Sites ..................................................................................... 39
35 2.3.2 Access Road ................................................................................................. 39
36 2.4 Substation Construction ............................................................................................ 39
37 2.4.1 Substation Roads .......................................................................................... 40
38 2.4.2 Soil Borings ................................................................................................... 40
39 2.4.3 Clearing and Grading .................................................................................... 40
40 2.4.4 Storage and Staging Yards ........................................................................... 40
41 2.4.5 Grounding ...................................................................................................... 40
42 2.4.6 Fencing .......................................................................................................... 40
43 2.4.7 Foundation Installation .................................................................................. 41
44 2.4.8 Oil Containment ............................................................................................. 41
45 2.4.9 Structure and Equipment Installation............................................................. 41
46 2.4.10 Conduit and Control Cable Installation .......................................................... 42
47 2.4.11 Construction Cleanup and Landscaping ........................................................ 42
48 2.5 Special Construction Techniques .............................................................................. 42
22 LIST OF TABLES
23 Table 1-1. Proposed Structure Characteristics .................................................................. 8
24 Table 1-2. Foundation Excavation Dimensions ................................................................. 9
25 Table 1-3. Proposed Communications Station Locations ................................................ 12
26 Table 1-4. Access Road Requirements for Transmission Line System ........................... 14
27 Table 2-1. Summary of Land Required for Construction and Operations ........................ 23
28 Table 2-2. Summary of Land Disturbed during Construction and Used during Permanent
29 Operations ...................................................................................................... 26
30 Table 2-3. Miles of New and Improved off-ROW Access Roads ..................................... 33
31 Table 2-4. Miles of New and Improved Access Roads1 ................................................... 34
32 Table 2-5. Construction Staging Areas and Helicopter Fly Yards .................................... 35
33 Table 2-6. Summary of Shallow Bedrock ......................................................................... 43
34 Table 2-7. Estimated Water Usage for Construction by County ...................................... 45
35 Table 2-8. Projected Workers and Population Change during Peak Construction .......... 46
36 Table 2-9. Transmission Line Construction Equipment Requirements ............................ 47
37 Table 2-10. Equipment Requirements for Grassland and Hemingway Substations .......... 48
38 Table 2-11. Average and Peak Construction Traffic (per spread) ..................................... 49
39 Table 2-12. Solid Waste Generation from Construction Activities ..................................... 50
40
November 2011 iv
Transmission Line and Substation Components Appendix B
1 LIST OF FIGURES
2 Figure 1-1. Proposed 500-kV Single Circuit Lattice Steel Structure ................................... 2
3 Figure 1-2. Proposed 500-kV Single Circuit Tubular Steel Pole H-frame Structure ............ 3
4 Figure 1-3. Proposed 138/69-kV Double Circuit Structure with Distribution Underbuild ..... 4
5 Figure 1-4. Proposed ROW Designs................................................................................... 5
6 Figure 1-5. Alternative 500-kV Single Shaft Steel Pole Structure ....................................... 6
7 Figure 1-6. Alternative ROW Design ................................................................................... 7
8 Figure 1-7. Typical Communication Site ........................................................................... 13
9 Figure 1-8. Typical Road Sections for Different Terrains .................................................. 15
10 Figure 1-9. Type 1 Drive Through Stream Crossing Methods .......................................... 16
11 Figure 1-10. Type 2 and Type 3 Crossing Methods ............................................................ 18
12 Figure 1-11. Type 4 – Channel Spanning Structures Including Fish Passage .................... 19
13 Figure 1-12. Typical 500-kV Substation .............................................................................. 22
14 Figure 2-1. Disturbance Area for Tower Structures .......................................................... 29
15 Figure 2-2. Typical Disturbance Area................................................................................ 30
16 Figure 2-3. Example Access Roads and Tower Locations ............................................... 31
17 Figure 2-4. Transmission Line Construction Sequence .................................................... 32
18 Figure 2-5. Conductor Installation ..................................................................................... 37
19 Figure 2-6. Project Construction Schedule ....................................................................... 52
20 Figure 3-1. Live-line Maintenance Space Requirements, Single-Circuit 500-kV Lattice
21 Tower .............................................................................................................. 59
22 Figure 3-2. Right-of-Way Vegetation Management ........................................................... 61
23
November 2011 v
Transmission Line and Substation Components Appendix B
1 This appendix contains detailed information provided by Idaho Power Company (IPC) regarding
2 the components of the transmission system including the transmission structures, the
3 communications system, and the substations. It provides details regarding construction of the
4 system (Section 2.0), goes on to provide information regarding the operations and maintenance
5 of the system (Section 3.0), and finally details the proposed abandonment and restoration
6 techniques (Section 4.0).
1
Of the 5.3 miles, 0.3 miles would be a 138-kV single-circuit which because of its limited extent, is not further discussed in this
document.
November 2011 1
Transmission Line and Substation Components Appendix B
1
2 Figure 1-1. Proposed 500-kV Single Circuit Lattice Steel Structure
November 2011 2
Transmission Line and Substation Components Appendix B
1
2 Figure 1-2. Proposed 500-kV Single Circuit Tubular Steel Pole H-frame Structure
November 2011 3
Transmission Line and Substation Components Appendix B
2
3 Figure 1-3. Proposed 138/69-kV Double Circuit Structure with Distribution
4 Underbuild
November 2011 4
Transmission Line and Substation Components Appendix B
1
2 Figure 1-4. Proposed ROW Designs
November 2011 5
Transmission Line and Substation Components Appendix B
1 Figure 1-5 presents the configuration of the alternative 500-kV monopole structure which could
2 be used in active agricultural areas where location is critical to farming operations. Figure 1-6
3 illustrates the alternative ROW design configuration.
4
5 Figure 1-5. Alternative 500-kV Single Shaft Steel Pole Structure
November 2011 6
Transmission Line and Substation Components Appendix B
1
2 Figure 1-6. Alternative ROW Design
November 2011 7
Transmission Line and Substation Components Appendix B
November 2011 8
Transmission Line and Substation Components Appendix B
3 1.2 Conductors
4 The proposed conductor for the 500-kV lattice structure lines is 1,272 KCM2 45/7 ACSR “Bittern”
5 45/73. Each phase of a 500-kV three-phase circuit4 will be composed of three subconductors in
6 a triple bundle configuration. The individual 1,272 KCM conductors will be bundled in a
7 triangular configuration with spacing of 25 inches between horizontal subconductors and 18
8 inches of diagonal separation between the top two conductors and the lower conductor (see
9 Figure 1-1). The triple-bundled configuration is proposed to provide adequate current carrying
10 capacity and to provide for a reduction in audible noise and radio interference as compared to a
11 single large-diameter conductor. Each 500-kV subconductor will have a 45/7 aluminum/steel
12 stranding, with an overall conductor diameter of 1.345 inches and a weight of 1.432 pounds per
13 foot and a non-specular finish5.
14 The proposed conductor for the 138/69-kV monopole structure lines is 397 KCM 26/7 ACSR
15 “Ibis” (138KV, one conductor per phase), 4/0 6/1 ACSR “Penguin” (69 KV, one conductor per
16 phase), No. 4 Copper Conductor (12.5-kV Distribution, one conductor per phase plus neutral
17 wire), and a 3/8” EHS 7-strand shield wire. Conductors will be aligned with typical vertical
18 spacing of 8 feet between shield wire and 69 or 138 KV phase wires, 6 feet between phase
19 wires, and a minimum of 12 feet between 138 or 69 KV phase wires and distribution wires.
20 Where multiple conductors are utilized in a bundle for each phase, the bundle spacing will be
21 maintained through the use of conductor spacers at intermediate points along the conductor
22 bundle between each structure. The spacers serve a dual purpose: in addition to maintaining
2
KCM (1,000 cmils) is a quantity of measure for the size of a conductor; kcmil wire size is the equivalent cross-sectional area in
thousands of circular mils. A circular mil (cmil) is the area of a circle with a diameter of one thousandth (0.001) of an inch.
3
Aluminum/steel refers to the conductor material composition. The preceding numbers indicate the number of strands of each
material type present in the conductor (i.e., 45/7 aluminum/steel stranding has 45 aluminum strands wound around 7 steel
strands).
4
For AC transmission lines, a circuit consists of three phases. A phase may consist of one conductor or multiple conductors (i.e.,
subconductors) bundled together.
5
Non-specular finish refers to a “dull” finish rather than a “shiny” finish.
November 2011 9
Transmission Line and Substation Components Appendix B
1 the correct bundle configuration and spacing, the spacers are also designed to damp out wind-
2 induced vibration in the conductors. The number of spacers required in each span between
3 towers will be determined during the final design of the transmission line.
November 2011 10
Transmission Line and Substation Components Appendix B
1 intended to provide localized protection to the structure and pipeline coating during a
2 fault event from a nearby electric transmission power system.
3 x Lumped Grounding – localized conductor or conductors connected to the affected
4 structure at strategic locations (e.g., at discontinuities). They are intended to protect
5 the structure from both steady-state and fault AC conditions.
6 x Gradient Control Wires – a continuous and long grounding conductor or conductors
7 installed horizontally and parallel to a structure (e.g., pipeline section) at strategic
8 lengths and connected at regular intervals. These are intended to provide protection
9 to the structure and pipeline coating during steady-state and fault AC conditions from
10 nearby electric transmission power systems.
11 x Gradient Control Mats – typically used for aboveground components of a pipeline
12 system, these are buried ground mats bonded to the structure, and are used to
13 reduce electrical step and touch voltages in areas where people may come in
14 contact with a structure subject to hazardous potentials. Permanent mats bonded to
15 the structure may be used at valves, metallic vents, cathodic protection test stations,
16 and other aboveground metallic and nonmetallic appurtenances where electrical
17 contact with the affected structure is possible. In these cases there is no “standard”
18 solution that will solve these issues every time. Instead, each case must be studied
19 to determine the magnitude of the induced currents and the most appropriate
20 mitigation given the ground resistivity, distance paralleled, steady-state and fault
21 currents, fault clearing times expected on the transmission line, and distance
22 between the line and the pipeline, to name a few of the parameters. If the electrical
23 studies indicate a need to install cathodic protection devices on a parallel pipeline
24 facility, a distribution supply line interconnection may be needed to provide power to
25 the cathodic protection equipment.6
26 During final design of the transmission line, appropriate electrical studies will be conducted to
27 identify the issues associated with paralleling other facilities and the types of equipment that will
28 need to be installed (if any) to mitigate the effects of the induced currents.
29 1.3.3 Minor Additional Hardware
30 In addition to the conductors, insulators, and overhead shield wires, other associated hardware
31 will be installed on the tower as part of the insulator assembly to support the conductors and
32 shield wires. This hardware will include clamps, shackles, links, plates, and various other pieces
33 composed of galvanized steel and aluminum.
34 A grounding system will be installed at the base of each transmission structure that will consist
35 of copper or galvanized ground rods embedded into the ground in immediate proximity to the
36 structure foundation and connected to the structure by a buried copper lead. When the
37 resistance to ground for a grounded transmission structure is greater than a specified
38 impedance value with the use of ground rods, counterpoise will be installed to lower the
39 resistance to below a specified impedance value. Counterpoise consists of a bare copper-clad
40 or galvanized-steel cable buried a minimum of 12 inches deep, extending from structures (from
41 one or more legs of structure) for approximately 200 feet within the ROW.
42 Other hardware that is not associated with the transmission of electricity may be installed as
43 part of the Project. This hardware may include aerial marker spheres or aircraft warning lighting
44 as required for the conductors or structures per Federal Aviation Administration (FAA)
6
NACE International. 2003. Grounding Systems. Houston, TX. Available online at
http://www.nace.org/content.cfm?parentid=1001¤tID=1001
November 2011 11
Transmission Line and Substation Components Appendix B
1 regulations.7 Structure proximity to airports and structure height are the determinants of whether
2 FAA regulations will apply based on an assessment of wire/tower strike risk. IPC does not
3 anticipate that structure lighting will be required because proposed structures will be less than
4 200 feet tall and will not be near airports that require structure lighting.
7
U.S. Department of Transportation, Federal Aviation Administration, Advisory Circular AC 70/7460-1K Obstruction
Marking and Lighting, August 1, 2000; and Advisory Circular AC 70/7460-2K Proposed Construction or Alteration of
Objects that May Affect the Navigable Airspace, March 1, 2000.
November 2011 12
Transmission Line and Substation Components Appendix B
1 routes (aerial and/or buried) from the transmission ROW to the equipment shelter will be
2 required. Figure 1-7 illustrates the plan arrangement of a typical communications sites.
3
4 Figure 1-7. Typical Communication Site
November 2011 13
Transmission Line and Substation Components Appendix B
November 2011 14
Transmission Line and Substation Components Appendix B
1
2 Figure 1-8. Typical Road Sections for Different Terrains
November 2011 15
Transmission Line and Substation Components Appendix B
1 Waterbody Crossings with Access Roads: Access roads will be constructed to minimize
2 disruption of natural drainage patterns including perennial, intermittent and ephemeral streams.
3 In order to estimate the impact on stream crossings, an assessment of stream crossing types
4 was made based on preliminary engineering plans. These are conservative estimates using
5 consistent quantitative descriptions for each crossing method. As the engineering plans are
6 advanced for new access roads, site specific crossings will be designed and crossing
7 disturbance will vary. On all federally managed lands, IPC will consult with the managing
8 agency regarding relevant standards and guidelines pertaining to road crossing methods at
9 waterbodies. Consultation will include site assessment, design, installation, maintenance, and
10 decommissioning. New crossings of canals, ditches and perennial streams will be avoided to
11 the extent practical by using existing crossings, but some new crossings are expected. The
12 performance of stream crossings will be monitored for the life of the access road, and
13 maintained or repaired as necessary to protect water quality. Four types of waterbody crossings
14 are considered as part of the Project (Figure 1-9 through Figure 1-11). They are:
15 Type 1 – Drive through with or without minor grading and/or minimal fill to match existing
16 stream profile: Crossing of a seasonally dry channel with minimal grading and/or fill to
17 repair surface ruts or re-contour minor surface erosion (Figure 1-9).
18
19 Figure 1-9. Type 1 Drive Through Stream Crossing Methods
20 Type 2 – Drive through/ Ford: Crossing of a channel that includes grading and
21 stabilization. Stream banks and approaches would be graded to allow vehicle passage
22 and stabilized with rock, geotextile fabric or other erosion control devices. The stream
23 bed would in some areas be reinforced with coarse rock material, where approved by
24 the land-management agency, to support vehicle loads, prevent erosion and minimize
25 sedimentation into the waterway. The rock would be installed in the stream bed such
26 that it would not raise the level of the streambed, thus allowing continued movement of
27 water, fish and debris. Fords may be constructed in small, shallow streams (less than 2’
November 2011 16
Transmission Line and Substation Components Appendix B
1 stream depth and 20’ active stream width) and rocky substrates. Fords may also be
2 appropriate on wider streams when they have a poorly defined channel that often
3 changes course from excessive bedload. A ford crossing results in an average
4 disturbance profile of 25 feet wide (along the water body) and 50 feet long (along the
5 roadway) for 1,000 square feet or 0.02 acre at each crossing. Disturbance amount is
6 estimated based on need to get equipment into the riparian area to build the 14-foot-
7 wide travel way and protect it from erosion by adding armoring. Flowing streams may
8 warrant temporary structures to maintain fish passage, hydrology and water quality to
9 span active the channel during construction activities (Figure 1-10).
10 Type 3 – Culvert: Crossing of a stream or seasonal drainage that includes installation
11 of a culvert and a stable road surface established over the culvert for vehicle passage.
12 Culverts would be designed and installed under the guidance of a qualified engineer
13 who, in collaboration with a hydrologist and aquatic biologist where required by the land
14 management agency, would recommend placement locations; culvert gradient, height,
15 and sizing; and proper construction methods. Culvert design would consider bedload
16 and debris size and volume. The disturbance footprint for culvert installation is estimated
17 to be 50 feet wide (along the waterbody) and 150 feet long (along the road) for 7,500
18 square feet or 0.17 acre at each crossing. Ground-disturbing activities would comply with
19 Agency-approved BMPs. Construction would occur during periods of low flow. The use
20 of equipment in streams would be minimized. All culverts would be designed and
21 installed to meet desired riparian conditions, as identified in applicable unit management
22 plans. Culvert slope would not exceed stream gradient. Typically, culverts would be
23 partially buried in the streambed to maintain streambed material in the culvert. Sandbags
24 or other non-erosive material would be placed around the culverts to prevent scour or
25 water flow around the culvert. Adjacent sediment control structures such as silt fences,
26 check dams, rock armoring, or riprap may be necessary to prevent erosion or
27 sedimentation. Stream banks and approaches may be stabilized with rock or other
28 erosion control devices (Figure 1-10).
29
November 2011 17
Transmission Line and Substation Components Appendix B
1
2
TYPE 3 CULVERT
3
4 Figure 1-10. Type 2 and Type 3 Crossing Methods
5 Type 4 – Channel spanning structures including fish passage: Crossing of a water
6 body identifies as containing a sensitive fish species that includes installation of a large
7 diameter culvert, arch culvert or short span bridge and a stable road surface established
8 over the structure for vehicle passage. Channel spanning structures would be designed
9 and installed under the guidance of a qualified engineer who, in collaboration with a
10 hydrologist and aquatic biologist would recommend placement locations; structure
11 gradient, height, and sizing; and proper construction methods. The disturbance footprint
12 for channel spanning structure installation is estimated to be 60 feet wide (along the
November 2011 18
Transmission Line and Substation Components Appendix B
1 water body) and 150 feet long (along the road) for 9,000 square feet or 0.2 acre at each
2 crossing. (Figure 1-11).
3
4
5 Figure 1-11. Type 4 – Channel Spanning Structures Including Fish Passage
November 2011 19
Transmission Line and Substation Components Appendix B
1 Wetlands Crossings with Access Roads: During construction and for routine and emergency
2 operations, access across wetlands to individual structure locations may be necessary.
3 Selection of final wetland crossing techniques will be based on final access road alignment and
4 wetland characteristics:
5 1. Constructing at grade roads with geotextiles and road materials which allow for water
6 through-flow. This type of road will be below water during certain times of the year which
7 will make locating the roads difficult, and the depth of the water over the drivable surface
8 may make travel over the submerged road surface impractical or not feasible.
9 2. Limiting structure access across wetlands to dry or frozen conditions along with the use
10 of low ground pressure tires or specialized tracked vehicles. This approach does not
11 allow sufficient flexibility for emergency restoration and for operation and maintenance
12 as the depth of water and/or soil conditions will not allow access to the structures during
13 certain times of the year. Construction of ice roads in wetlands involves using lightweight
14 equipment such as snowmobiles to tamp down existing snow cover and vegetation to
15 allow penetration of frost into the wetland soils. This operation is followed by packing
16 with heavier tracked equipment such as Bombardiers or wide tracked dozers. There is a
17 relatively small window of time during the year where cold enough weather is present to
18 allow for this technique thereby restricting the flexibility required for operation and
19 maintenance in other seasons besides winter.
20 3. Installing temporary matting materials to allow access for heavy vehicles and equipment.
21 The mats typically come in the form of heavy timbers bolted together or interlocking
22 pierced-steel planks. Mats spread the concentrated axle loads from equipment over a
23 much larger surface area thereby reducing the bearing pressure on fragile soils.
24 However, mats are less effective when standing water is present. Matting has a limited
25 service life before replacement is required and must be stored for maintenance and
26 emergency restoration activities.
November 2011 20
Transmission Line and Substation Components Appendix B
1 1.6 Substations
2 The Project includes expansion at one planned (Grassland) and one existing (Hemingway)
3 substation.
4 1.6.1 Substation Components
5 The following sections describe key components of substations.
6 1.6.1.1 Bay
7 A substation “bay” is the physical location within a substation fenced area where the high-
8 voltage circuit breakers and associated steel transmission line termination structures, high-
9 voltage switches, bus supports, controls, and other equipment are installed. For each
10 transmission line, 500-kV circuit breakers, high-voltage switches, bus supports, and
11 transmission line termination structures would typically be installed. The 500-kV transmission
12 line termination structures are approximately 125 to 135 feet tall.
13 The tallest structures in the substations will be the 500-kV dead-end structures, from 125 to 135
14 feet tall, and/or a microwave antenna tower, which will be in the range of 100 feet or more,
15 depending on the height needed to maintain line of sight to the nearest microwave relay site.
16 Figure 1-12 is a perspective sketch illustrating the appearance of a typical 500-kV substation
17 with multiple line connections.
18 1.6.1.2 Access Road
19 Permanent all-weather access roads are required at substation sites to provide access for
20 personnel, material deliveries, vehicles, trucks, heavy equipment, low-boy tractor trailer rigs
21 (used for moving large transformers), and ongoing maintenance activities at each site.
22 Substation access roads are normally well-compacted, graded gravel roads approximately
23 20 feet in width with a minimum 110-foot turning radius to accommodate the delivery of large
24 transformers to the site. No new access roads are necessary for access to the Grassland and
25 Hemingway substation locations.
November 2011 21
Transmission Line and Substation Components Appendix B
1
2 Figure 1-12. Typical 500-kV Substation
November 2011 22
Transmission Line and Substation Components Appendix B
1 substation will be determined during the final design process. The distance from Grassland
2 Substation to the nearest existing distribution supply is approximately 4,000 feet. The
3 Hemingway Substation exists and new distribution line extensions to provide station service
4 power will not be required. However, modifications to the existing distribution facilities may be
5 necessary to provide increased capacity to support the expansions at the existing Hemingway
6 Substation.
November 2011 23
Transmission Line and Substation Components Appendix B
1 Table 2-1. Summary of Land Required for Construction and Operations (continued)
Land Required for Land Required for Operations
Division by County Construction (acres) (acres)
Umatilla County
T-Line ROW 1,498.2 1,498.2
Off-ROW Staging Area 41.2 0
Off-ROW Fly Yards 44.5 0
Off ROW Wire Pulling/Splicing Sites 140.5 0
Off-ROW Access Roads 71.8 35.9
OPGW Communication Sites (1) 0.2 0.1
County Total Segment Subtotal 1,796.4 1,534.2
Union County
T-Line ROW 1,195.2 1,195.2
Off-ROW Staging Area 41.1 0
Off-ROW Fly Yards 103.8 0
Off ROW Wire Pulling/Splicing Sites 38.2 0
Off-ROW Access Roads 72.0 36.0
OPGW Communication Sites (1) 0.2 0.1
County Total Segment Subtotal 1,450.5 1,231.3
Baker County
T-Line ROW 2,157.7 2,157.7
Off-ROW Staging Area 43.8 0
Off-ROW Fly Yards 116.1 0
Off ROW Wire Pulling/Splicing Sites 112.3 0
Off-ROW Access Roads 161.5 80.8
OPGW Communication Sites (2) 0.5 0.3
County Total Segment Subtotal 2,591.9 2,238.8
Malheur County
T-Line ROW 2,184.3 2,184.3
Off-ROW Staging Area 63.9 0
Off-ROW Fly Yards 134.0 0
Off ROW Wire Pulling/Splicing Sites 120.2 0
Off-ROW Access Roads 163.0 81.5
OPGW Communication Sites (3) 0.7 0.4
County Total Segment Subtotal 2,666.1 2,266.2
Owyhee County
T-Line ROW 720.9 720.9
Off-ROW Staging Area 42.5 0
Off-ROW Fly Yards 59.8 0
Off ROW Wire Pulling/Splicing Sites 41.9 0
Off-ROW Access Roads 55.6 27.8
Hemingway Substation 4.0 2.0
County Total Segment Subtotal 924.7 750.7
2
November 2011 24
Transmission Line and Substation Components Appendix B
1 Table 2-1. Summary of Land Required for Construction and Operations (continued)
Land Required for Land Required for Operations
Division by County Construction (acres) (acres)
Total Project
Transmission line ROW 9,145.1 9,145.1
Off-ROW Staging Area 272.4 0
Off-ROW Fly Yards 473.5 0
Off ROW Wire Pulling/Splicing Sites 557.9 0
Off-ROW Access Roads 542.5 271.3
OPGW Communication Site(s) 1.8 1.0
Substations 34.0 8.0
Total Project 11,027.2 9,425.4
2 Assumptions/Notes:
3 1. The exact land requirements would depend on the final detailed design of the transmission line, which is influenced by the
4 terrain, land use, and economics. Alignment options may also slightly increase or decrease these values.
5 2. ROW width for 500-kV single circuit is 250 feet.
6 3. ROW width for 138/69-kV double-circuit is 100 feet.
7 4. The dimensions of the tower construction pads and area permanently occupied by towers after restoration are based on the
8 dimensions specified in Figure 1-1.
9 5. The staging areas would serve as field offices, reporting locations for workers, parking space for vehicles and equipment,
10 sites for material storage, fabrication assembly, equipment maintenance, and concrete batch plants. Staging/material storage
11 yards/batch plants would be approximately 20 acres for 500-kV lines. They would be located every 20 to 30 miles along the
12 line.
13 6. Fly yards would be 10 to 15 acres located every 5 to 10 miles. Values in table assume helicopter construction throughout all
14 single-circuit 500-kV lines. The construction contractor may choose to construct using ground-based techniques, therefore,
15 not utilizing fly yards.
16 7. Typical wiring pulling/splicing sites would be the ROW width x 600 to 900 feet located every 2 to 3 miles. Typically, the only
17 sites that would be off of the ROW would be at large-angle dead-ends. It is estimated that one in four sites would be off of the
18 ROW.
19 8. Miles of access road are based on an indicative layout of access roads along the current preferred route as of the date of this
20 document.
21
22 2.1.2 Right-of-Way Acquisition
23 All portions of the route must obtain new ROWs through a combination of ROW grants and
24 easements between IPC and various federal, state, and local governments; other companies
25 (e.g., utilities and railroads), and private landowners.
26 Close coordination with all property owners and land agencies during initial surveys and the
27 construction phase of the Project is essential for successful completion of the Project. In the
28 early stages of the Project, landowners will be contacted to obtain right-of-entry for surveys and
29 for geotechnical drilling at selected locations. Each landowner along the final centerline route
30 will be contacted to explain the Project and to secure right-of-entry and access to the ROW.
31 All negotiations with landowners will be conducted in good faith, and the Project’s effect on the
32 parcel or any other concerns the landowner may have will be addressed. ROWs for
33 transmission line facilities on private lands will be obtained as perpetual easements. Land for
34 substation or communication sites will be obtained in fee simple where located on private land.
35 Every effort will be made to purchase the land and/or obtain easements on private lands
36 through reasonable negotiations with the landowners.
37 Section 2.2.4 of the POD describes North American Electricity Reliability Corporation (NERC)
38 and Western Electricity Coordinating Council (WECC) reliability standards and capacity needs
39 for the Project. To achieve the capacity needed to serve present and future loads within IPC’s
40 service areas, the WECC requires a minimum separation from existing transmission lines that
41 serve substantially the same load as that served by the new Boardman to Hemingway
42 transmission project. In these cases, the Project transmission lines must be located at least
November 2011 25
Transmission Line and Substation Components Appendix B
1 1,500 feet as a general rule from the nearest existing 230 kV or higher-voltage transmission
2 lines or the length of the longest span where the two lines are adjacent to each other. Land
3 between ROWs that are separated to meet reliability criteria will not be encumbered with an
4 easement but could practically be limited in land uses due to the proximity of two or more large
5 transmission lines.
6 2.1.3 Land Disturbance
7 Land disturbance as described in Table 2-2 is the estimated amount of land that will be
8 disturbed during construction or required to be permanently converted to operational uses. The
9 areas are reported by county. These uses are less than the amount of land for which
10 operational controls are required over the life of the Project as described in Table 2-1.
11 Table 2-2. Summary of Land Disturbed during Construction and Used during
12 Permanent Operations
Land Affected During Land Affected During Operations
Segment/Project Component Construction (acres) (acres)
Morrow County
Single Circuit 500-kV Pad 304.0 12.2
On ROW Pulling/Tensioning Sites 159.3 0
ON ROW Construction Roads 59.4 29.6
Off ROW Pulling/Tensioning Sites 104.8 0
Off ROW Access Roads 18.6 9.3
Staging Yards 39.9 0
Fly Yards 15.3 0
Communications Station (1) 0.2 0.1
Grassland Substation 30.0 6.0
County Total Segment Subtotal 731.5 57.2
Umatilla County
Single Circuit 500-kV Pad 294.7 11.9
On ROW Pulling/Tensioning Sites 191.3 0
ON ROW Construction Roads 53.8 26.9
Off ROW Pulling/Tensioning Sites 140.5 0
Off ROW Access Roads 71.8 35.9
Staging Yards 41.2 0
Fly Yards 44.5 0
Communications Station (1) 0.2 0.1
County Total Segment Subtotal 838.0 74.8
13
November 2011 26
Transmission Line and Substation Components Appendix B
1 Table 2-2. Summary of Land Disturbed during Construction and Used during
2 Permanent Operations (continued)
Land Affected During Land Affected During Operation
Segment/Project Component Construction (acres) (acres)
Union County
Single Circuit 500 kV Pad 248.1 10.0
On ROW Pulling/Tensioning Sites 213.1 0
ON ROW Construction Roads 42.7 21.3
Off ROW Pulling/Tensioning Sites 38.2 0
Off ROW Access Roads 72.0 36.0
Staging Yards 41.1 0
Fly Yards 103.8 0
Communications Stations (1) 0.2 0.1
County Total Segment Subtotal 759.2 67.4
Baker County
Single Circuit 500 kV Pad 418.9 16.8
Double Circuit 138/69-kV Pad 16.5 4.1
On ROW Pulling/Tensioning Sites 342.1 0
ON ROW Construction Roads 78.2 39.1
Off ROW Pulling/Tensioning Sites 112.3 0
Off ROW Access Roads 161.5 80.8
Staging Yards 43.8 0
Fly Yards 116.1 0
Communications Station (2) 0.5 0.3
County Total Segment Subtotal 1,289.9 141.1
Malheur County
Single Circuit 500 KV Pad 456.7 18.4
On ROW Pulling/Tensioning Sites 263.1 0
ON ROW Construction Roads 80.1 40.0
Off ROW Pulling/Tensioning Sites 120.2 0
Off ROW Access Roads 163.0 81.5
Staging Yards 63.9 0
Fly Yards 134.0 0
Communications Station (3) 0.7 0.4
County Total Segment Subtotal 1,281.7 140.3
Owyhee County
Single Circuit 500 KV Pad 147.7 5.9
On ROW Pulling/Tensioning Sites 121.1 0
ON ROW Construction Roads 20.5 10.2
Off ROW Pulling/Tensioning Sites 41.9 0
Off ROW Access Roads 55.6 27.8
Staging Yards 42.5 0
Fly Yards 59.8 0
Communications Station 0 0
Hemingway Substation 4.0 2.0
County Total Segment Subtotal 493.1 45.9
3
November 2011 27
Transmission Line and Substation Components Appendix B
1 Table 2-2. Summary of Land Disturbed during Construction and Used during
2 Permanent Operations (continued)
Land Affected During Land Affected During Operations
Segment/Project Component Construction (acres) (acres)
Total Project
Single Circuit 500 KV Pad 1,870.2 75.2
Double Circuit 138/69-kV Pad 16.5 4.1
On ROW Pulling/Tensioning Sites 1,290.0 0
ON ROW Construction Roads 334.7 167.1
Off ROW Pulling/Tensioning Sites 557.9 0
Off ROW Access Roads 542.5 271.3
Staging Yards 272.4 0
Fly Yards 473.5 0
Communications Station 1.8 1.0
Substations 34.0 8.0
Total Project 5,393.5 526.7
1
3 The exact land requirements would depend on the final detailed design of the transmission line, which is influenced
4 by the terrain, land use, and economics. Alignment options may also slightly increase or decrease these values.
5
6 Assumptions/Notes:
7 1. ROW widths for 500-kV single circuit segments are 250 feet and 100 feet for 138/69-kV segments.
8 2. The staging areas would serve as field offices, reporting locations for workers, parking space for vehicles and equipment, sites
9 for material storage, fabrication assembly and stations for equipment maintenance, and concrete batch plants.
10 3. Staging/material storage yards/batch plants would be approximately 20 acres for 500 kV and located every 20 to 30 miles along
11 the line.
12 4. Fly yards would be 10 to 15 acres located every 5 miles. Values in table assume helicopter construction throughout all single-
13 circuit 500-kV segments. The construction contractor may choose to construct using ground-based techniques, therefore, not
14 utilizing fly yards for those sections.
15 5. For 500 kV, wiring pulling/splicing sites would be the ROW width x 600 to 900 feet located every 2 to 3 miles. Typically, the only
16 sites that would be off of the ROW would be at large angle dead-ends. It is estimated that one in four sites would be off of the
17 ROW.
18
19 Estimates for construction disturbances are based on best professional judgment and
20 experience with this type of project. Components estimated include transmission support
21 structures; their associated construction pads; pulling sites for tensioning conductors; access
22 roads to each structure, communications station, and substation; staging areas; fly yards where
23 helicopter construction would be used; communications stations; and substations. As part of the
24 conceptual design and in order to aid quantification of effects, preliminary indicative locations
25 were assigned for all components of the Proposed Route and alternatives. Figure 2-1 through
26 Figure 2-3 illustrate how disturbance was estimated for each of the components. Sections 2.2
27 through 2.4 of this appendix describe typical disturbance areas for each construction activity.
28
November 2011 28
Transmission Line and Substation Components Appendix B
1
2 Figure 2-1. Disturbance Area for Tower Structures
November 2011 29
Transmission Line and Substation Components Appendix B
November 2011 30
Transmission Line and Substation Components Appendix B
1
2 Figure 2-3. Example Access Roads and Tower Locations
November 2011 31
Transmission Line and Substation Components Appendix B
9
10 Figure 2-4. Transmission Line Construction Sequence
November 2011 32
Transmission Line and Substation Components Appendix B
1 wads will be removed with the aid of a bulldozer and surface restored with a grader. In steep
2 terrain new bladed access roads would be constructed using a bulldozer or grader, followed by
3 a roller to compact and smooth the ground. Front-end loaders will be used to move the soil
4 locally or off-site as necessary. Typically, access to the transmission line ROW and tower sites
5 requires a 14-foot-wide travel way for straight sections of road and a 16- to 20-foot-wide travel
6 way at corners to facilitate safe movement of equipment and vehicles. In steep, rugged terrain,
7 8-foot-wide all-terrain vehicle (ATV) trails may be established to facilitate permanent access for
8 off-road 4-wheel maintenance utility vehicles (UTVs).
9 Wherever possible existing roads will be used and new access roads would be constructed
10 within the proposed transmission line ROW. In other cases, new access roads would be
11 required between the proposed transmission line and existing roads outside of the ROW,
12 particularly in steep terrain where new bladed roads will often follow the contours to minimize
13 grades. Erosion control and sedimentation measures such as at-grade water bars, culverts,
14 sediment basins, or perimeter control would be installed as required to minimize erosion during
15 and subsequent to construction of the Project.
16 After Project construction, existing and new permanent access roads would be used by
17 maintenance crews and vehicles for inspection and maintenance activities. New roads created
18 to access tower sites would be revegetated but not restored to original contours in the event that
19 emergency access is needed to a tower location or for periodic inspection and maintenance
20 activities. Temporary construction roads not required for future maintenance access will be
21 restored after completion of Project construction. For example, access roads to staging areas
22 will not be required once the staging area is restored. Depending on Agency or landowner
23 preference, gates may be installed at fence crossings and other locations as requested to
24 restrict unauthorized vehicular access to the ROW. Roads retained for operations would be
25 seeded with an approved native grass mix and allowed to revegetate. For normal maintenance
26 activities, an 8-foot portion of the road would be used and vehicles would drive over the
27 vegetation. For non-routine maintenance requiring access by larger vehicles, the full width of the
28 access road may be used. Access roads would be repaired, as necessary, but not be routinely
29 graded. Vegetation (e.g., taller shrubs and trees) that may interfere with the safe operation of
30 equipment would be managed on a cyclical basis.
31 Table 2-3 lists the estimated miles of proposed off ROW access roads by county. The table will
32 be revised to show proposed locations of access roads once they are identified during the
33 design phase.
34 Table 2-3. Miles of New and Improved off-ROW Access Roads
New Access Roads Existing Access Roads
County (miles) to be Improved (miles) Total Miles
Morrow 7.3 2.2 9.5
Umatilla 21.4 15.6 37.0
Union 9.1 28.1 37.2
Baker 38.1 44.8 82.9
Malheur 33.1 50.9 84.1
Owyhee 5.2 23.5 28.7
Total 114.8 165.1 279.9
35
November 2011 33
Transmission Line and Substation Components Appendix B
1 Table 2-4 lists the estimated miles of proposed on and off road access roads. The table will be
2 revised to show any changes in the locations of access roads once they are identified during the
3 design phase.
4 Table 2-4. Miles of New and Improved Access Roads1
New
Access Existing Access Roads
Roads to be Improved Totals
County Miles Miles Miles
Morrow 37.3 2.8 40.1
Umatilla 44.2 20.5 64.7
Union 27.4 31.6 59.0
Baker 72.6 50.4 123.0
Malheur 69.0 56.3 125.3
Owyhee 12.2 27.0 39.2
Total2 262.7 188.6 451.3
1
Includes on- and off-ROW access roads (including roads shown in Table 2-2).
2
Acreages in table are rounded to the nearest acre; column therefore may not sum exactly.
November 2011 34
Transmission Line and Substation Components Appendix B
1 with easy existing access to minimize site grading and new road construction. The staging
2 areas will be located in previously disturbed sites or in areas of minimal vegetative cover where
3 possible.
4 Table 2-5. Construction Staging Areas and Helicopter Fly Yards
Staging Areas Fly Yards
County Number Acres Number Acres
Morrow 2 39.9 1 15.3
Umatilla 2 41.2 3 44.5
Union 2 41.1 7 103.8
Baker 2 43.8 8 116.1
Malheur 3 63.9 9 134.0
Owyhee 2 42.5 4 59.8
Total 13 272.4 32 473.5
5
6 2.2.4 Site Preparation
7 Individual structure sites will be cleared to install the transmission line support structures and
8 facilitate access for future transmission line and structure maintenance. Clearing individual
9 structure sites will be done using a bulldozer to blade the required area. At each single-circuit
10 500-kV structure location, an area approximately 250 feet by 250 feet will be needed for
11 construction laydown, tower assembly, and erection at each tower site. This area will provide a
12 safe working space for placing equipment, vehicles, and materials. The work area will be
13 cleared of vegetation only to the extent necessary. For 138/69-kV structures the site prep area
14 will be approximately 100 feet by 100 feet. After line construction, areas not needed for normal
15 transmission line maintenance, including fire and personnel safety clearance areas, will be
16 graded to blend as near as possible with the natural contours, then revegetated as required.
17 Additional equipment may be required if solid rock is encountered at a structure location. Rock-
18 hauling, hammering, or blasting may be required to remove the rock. Excess rock that is too
19 large in size or volume to be spread at the individual structure sites will be hauled away and
20 disposed of at approved landfills or at a location specified by the landowner. Table 2-2 provides
21 the dimensions of each of the foundation holes required for each structure. See Section 1.1.1 of
22 this appendix for a description of each structure type and Figure 1-1 through Figure 1-3 for
23 structure illustrations.
24 2.2.5 Install Structure Foundations
25 Table 1-1 lists the number of and type of support structures that will be installed.
26 2.2.5.1 Lattice Steel Tower Foundations
27 Each 500-kV support structure will require the installation of foundations, which are typically
28 drilled concrete piers. First, four holes will be excavated for each structure. The holes will be
29 drilled using truck- or track-mounted augers of various sizes depending on the diameter and
30 depth requirements of the hole to be drilled. Each foundation will extend approximately 1 to 2
31 feet above the ground level.
32 2.2.5.2 H-Frame Installation
33 Each 500-kV H-frame will require the installation of drilled pier foundations. Two or three
34 foundations will be required per H-frame structures. The holes for each foundation will be drilled
35 using truck- or track-mounted augers of various sizes depending on the diameter and depth
November 2011 35
Transmission Line and Substation Components Appendix B
1 requirements of the hole to be drilled. The diameter of each foundation will be approximately 7
2 to 8 feet at a depth of 30 to 40 feet. Each foundation will extend approximately 1 to 2 feet above
3 the ground level.
4 2.2.5.3 Monopole Installation
5 Tangent 138/69-kV monopole structures will require the poles to be directly embedded in the
6 ground. Holes will be drilled in the ground using a truck- or track-mounted auger. The diameter
7 of the hole excavated for embedment is typically between 5 and 6 feet (see Table 1-2). Depths
8 of the holes range from 15 to 25 feet deep. When the poles are placed in the holes, the hole will
9 be backfilled with native or select backfill. When backfill must be imported, material must be
10 obtained from commercial sources or from areas free of noxious weed species. See Section
11 1.1.1 of this appendix for a description a monopole structure and Figure 1-3 for an illustration.
12 Angle and dead-end 138/69-kV monopole structures will require the installation of drilled pier
13 foundations. The hole for each foundation will be drilled using a truck- or track-mounted auger of
14 various sizes depending on the diameter and depth requirements of the hole to be drilled. The
15 diameter of the foundation will be approximately 5 to 6 feet with at a depth of 20 to 25 feet deep.
16 Each drilled pier foundation will extend approximately one to two feet above the ground level.
17 Where solid rock is encountered, blasting (see Section 2.5.1 of this appendix), rock hauling, or
18 the use of a rock anchoring or micro-pile system may be required. Micro-piles are high capacity,
19 small diameter (5-inch to 12-inch) drilled and grouted in-place piles designed with steel
20 reinforcement to primarily resist structural loading. The rock anchoring or micro-pile system will
21 be used in areas where site access is limited or adjacent structures could be damaged as a
22 result of blasting or rock hauling activities.
23 In environmentally sensitive areas with very soft soils, a HydroVac, which uses water pressure
24 and a vacuum, may be used to excavate material into a storage tank. Alternatively, a temporary
25 casing may be used during drilling to hold the excavation open, after which the casing is
26 withdrawn as the concrete is placed in the hole. In areas where it is not possible to operate
27 large drilling equipment due to access or environmental constraints, hand digging may be
28 required.
29 Reinforced-steel anchor bolt cages will be installed after excavation and prior to structure
30 installation. These cages are designed to strengthen the structural integrity of the foundations
31 and will be assembled at the nearest Project laydown yard and delivered to the structure site via
32 flatbed truck or helicopter. These cages will be inserted in the holes prior to pouring concrete.
33 The excavated holes containing the reinforcing anchor bolt cages will be filled with concrete
34 (Table 1-2).
35 Typically, and because of the remote location of much of the transmission line route, concrete
36 will be provided from portable batch plants set up approximately every 25 miles along the line
37 route in one of the staging areas. Concrete will be delivered directly to structure sites in
38 concrete trucks with a capacity of up to 10 cubic yards. In the more developed areas along the
39 route and in proximity to the substations, the construction contractor may use local concrete
40 providers to deliver concrete to the site when economically feasible.
41 2.2.6 Erect Support Structures
42 The steel support structures will be assembled on site, except where helicopter delivery is
43 employed, as described in Section 2.5.2 of this appendix. Steel members for each structure will
44 be delivered to the site by flatbed truck. Assembly will be facilitated on site by a truck-mounted
45 crane. Subsequent to assembly, the structures will be lifted onto foundations using a large crane
46 designed for erecting towers. Where possible, the crane will move along the ROW from
November 2011 36
Transmission Line and Substation Components Appendix B
1 structure to structure site erecting the towers, if access along the ROW is not possible the crane
2 will leave the ROW and use the access road network to reach the next structure.
3 The H-frame and monopole structures will be framed on site. Two methods of assembly can be
4 used to accomplish this, the first of which is to assemble the poles, braces, cross arms,
5 hardware, and insulators on the ground. A crane is then used to set the fully framed structure by
6 placing the poles in the excavated holes. Alternatively, aerial framing can be used by setting the
7 poles in the ground first and assembling the braces, cross arms, hardware, and insulators in the
8 air. Where possible, the crane will move along the ROW from structure to structure site setting
9 the structures.
10 2.2.7 String Conductors, Shield Wire, and Fiber Optic Ground Wire
11 Conductor, shield wire, and OPGW will be placed on the transmission line support structures by
12 a process called stringing. The first step to wire stringing will be to install insulators (if not
13 already installed on the structures during ground assembly) and stringing sheaves. Stringing
14 sheaves are rollers that are temporarily attached to the lower portion of the insulators at each
15 transmission line support structure to allow conductors to be pulled along the line.
16 Figure 2-5 illustrates the sequence of steps in installing conductors.
17
18 Figure 2-5. Conductor Installation
19 Additionally, temporary clearance structures (also called guard structures) will be erected where
20 required prior to stringing any transmission lines. The temporary clearance structures are
21 typically vertical wood poles with cross arms and are erected at road crossings or crossings with
22 other energized electric and communication lines to prevent contact during stringing activities.
23 Bucket trucks may also be used to provide temporary clearance. Bucket trucks are trucks fitted
24 with a hinged arm ending in an enclosed platform called a bucket, which can be raised to let the
November 2011 37
Transmission Line and Substation Components Appendix B
1 worker in the bucket service portions of the transmission structure as well as the insulators and
2 conductors without climbing the structure.
3 Once the stringing sheaves and temporary clearance structures are in place, the initial stringing
4 operation will commence with the pulling of a lightweight “sock” line through the sheaves along
5 the same path the transmission line will follow. Typically the sock line is pulled in via helicopter.
6 The sock line is attached to the hard line, which follows the sock line as it is pulled through the
7 sheaves. The hard line will then be attached to the conductor, shield wire, or OPGW to pull
8 them through the sheaves into their final location. Pulling the lines may be accomplished by
9 attaching them to a specialized wire stringing vehicle. Following the initial pulling of the wire into
10 the sheaves, the wire will then be tensioned to achieve the correct sag between support
11 structures.
12 Pulling and tensioning sites for 500-kV construction will be required approximately every 1.5 to
13 2 miles along the ROW and at angle points greater than 30 degrees and will require
14 approximately 5 acres at each end of the wire section to accommodate required equipment. The
15 138/69-kV pulling and tensioning sites will be required approximately every 1 to 2 miles along
16 the ROW and will require approximately 1.2 acres each to accommodate required equipment.
17 Equipment at sites required for pulling and tensioning activities will include tractors and trailers
18 with spooled reels that hold the conductors and trucks with the tensioning equipment. To the
19 extent practicable, pulling and tensioning sites will be located within the ROW. However, angle
20 points typically necessitate pulling and tensioning sites outside of the ROW. Depending on
21 topography, minor grading may be required at some sites to create level pads for equipment.
22 Finally, the tension and sag of conductors and wires will be fine-tuned, stringing sheaves will be
23 removed, and the conductors will be permanently attached to the insulators at the support
24 structures.
25 At the tangent and small angle structures, the conductors will be attached to the insulators using
26 clamps to “suspend” the conductors from the bottom of the insulators. At the larger angle dead-
27 end structures, the conductors cannot be pulled through and so they are cut and attached to the
28 insulator assemblies at the structure which “dead ends” the conductors. There are two primary
29 methods to attach the conductor to the insulator assembly at the dead-end structure. The first
30 method, hydraulic compression fittings, uses a large press and pump that closes a metal clamp
31 or sleeve onto the conductor. This method requires heavy equipment and is time consuming.
32 The second method, implosive fittings, uses explosives to compress the metal together.
33 Implosive fittings do not require heavy equipment, but do create noise similar to a loud
34 explosion when the primer is struck. The implosive type sleeve is faster to install and results in a
35 secure connection between the conductor and the sleeve. Implosive sleeves are planned for the
36 Project.
37 The 500-kV single-circuit line uses a three conductor bundle for each phase. At each single-
38 circuit 500-kV dead-end structure, 18 implosive dead-end sleeves (six per phase, one for each
39 of the three subconductors on each of the three phases, and on each side of the structure) will
40 be required. Additionally, 18 compression or implosive sleeves will be required to fabricate and
41 install the jumpers that connect the conductors from one side of the dead-end structure to the
42 other, for a total of 36 sleeves for each single-circuit dead-end structure.
43 The 138/69-kV double-circuit lines use a single-conductor bundle for each phase. Each of these
44 dead-end structures will require 12 implosive or compression type sleeves to dead-end the
45 conductors and 12 sleeves to fabricate the jumpers, for a total of 24 sleeves at each dead-end
46 structure. For the overall Project, approximately 8,000 to 10,000 implosive fittings will be used.
November 2011 38
Transmission Line and Substation Components Appendix B
November 2011 39
Transmission Line and Substation Components Appendix B
November 2011 40
Transmission Line and Substation Components Appendix B
1 height of 8 feet. Locked gates will be installed at appropriate locations for authorized vehicle and
2 personnel access.
3 2.4.7 Foundation Installation
4 Foundations for supporting structures are of two types—spread footings or drilled piers. Spread
5 footings are placed by excavating the foundation area, placing forms and reinforced-steel and
6 anchor bolts, and pouring concrete into the forms. After the foundation has been poured, the
7 forms will be removed, and the surface of the foundation dressed. Pier foundations are placed in
8 a hole generally made by a truck-mounted auger. Reinforced-steel and anchor bolts are placed
9 into the hole using a truck-mounted crane. The portion of the foundation above ground will be
10 formed. The portion below ground uses the undisturbed earth of the augered hole as the form.
11 After the foundation has been poured, the forms will be removed, the excavation will be
12 backfilled, and the surface of the foundation dressed.
13 Equipment foundations for circuit breakers and transformers will be slab-on-grade type. These
14 foundations are placed by excavating the foundation area; placing forms, reinforced steel, and
15 anchor bolts (if required); and placing concrete into the forms. After the foundations have been
16 poured, the forms will be removed, and the surface of the foundation dressed. Where
17 necessary, provision will be made in the design of the foundations to mitigate potential problems
18 due to frost. Reinforced steel and anchor bolts will be transported to each site by truck, either as
19 a prefabricated cage or loose pieces, which will then be fabricated into cages on the site.
20 Concrete will be hauled to the site in concrete trucks. Excavated material will be spread at the
21 site or disposed of in accordance with local ordinances. Structures and equipment will be
22 attached to the foundations by means of threaded anchor bolts embedded in the concrete.
23 Some equipment such as transformers and reactors may not require anchor bolts.
24 2.4.8 Oil Containment
25 Some types of electrical equipment, such as transformers and some types of reactors and
26 circuit breakers are filled with an insulating mineral oil. Containment structures are required to
27 prevent equipment oil from getting into the ground or waterbodies in the event of a rupture or
28 leak. These structures take many forms depending on site requirements, environmental
29 conditions, and regulatory restrictions. The simplest type of oil containment is a pit, of a
30 calculated capacity, under the oil-filled equipment that has an oil-impervious liner. The pit is
31 filled with rock to grade level. In case of an oil leak or rupture, the oil captured in the
32 containment pit is pumped into tanks or barrels and transported to a disposal facility. If required,
33 more elaborate oil containment systems can be installed. This may take the form of an on- or
34 off-site storage tank and/or oil-water separator equipment depending on site requirements.
35 2.4.9 Structure and Equipment Installation
36 Supporting steel structures are erected on concrete foundations as noted above. These are set
37 with a truck-mounted crane and attached to the foundation anchor bolts by means of a steel
38 base plate. These structures will be used to support the energized conductors and certain types
39 of equipment. This equipment is lifted onto the structure by means of a truck-mounted crane
40 and bolted to the structures; electrical connections are then made. Some equipment, such as
41 transformers, reactors, and circuit breakers, are mounted directly to the foundations without
42 supporting structures. These are set in place by means of a truck-mounted crane. Some of this
43 equipment requires assembly and testing on the pad. Electrical connections to the equipment
44 are then made.
November 2011 41
Transmission Line and Substation Components Appendix B
November 2011 42
Transmission Line and Substation Components Appendix B
2 The construction contractor will be required to prepare an overall Blasting Plan for the Project,
3 subject to the approval of IPC. The Blasting Plan will detail the contractor’s proposals for
4 compliance with IPC’s blasting specifications and will detail the general concepts proposed to
5 achieve the desired excavations using individual shot plans. In addition, the plan will address
6 proposed methods for controlling fly rock, for blasting warnings, and for use of non-electrical
7 blasting systems. The contractor will be required to provide data to support the adequacy of the
8 proposed efforts regarding the safety of structures and slopes and to ensure that an adequate
9 foundation is obtained. When utilized, blasting will take place between sunrise and sunset.
10 The shot plans will detail, including sketches, the drilling and blasting procedures; the number,
11 location, diameter, and inclination of drill holes; the amount, type, and distribution of explosive
12 per hole and delay; and pounds of explosive per square foot for presplitting and smooth
13 blasting. The contractor will be required to maintain explosives logs.
14 Blasting near buildings, structures, and other facilities susceptible to vibration or air blast
15 damage will be carefully planned by the contractor and IPC and controlled to eliminate the
16 possibility of damage to such facilities and structures. The Blasting Plan will include provisions
17 for control to eliminate vibration, fly rock, and air blast damage.
18 Blasting will be very brief in duration (milliseconds), and the noise will dissipate with distance.
19 Blasting produces less noise and vibration than comparable non-blasting methods to remove
20 hard rock. Non-blasting methods include track drill rigs, rock breakers, jack hammers, rotary
21 percussion drills, core barrels, and rotary rock drills with rock bits. Which all require much longer
22 time duration to excavate approximately the same amount of rock as blasting.
23 Table 2-6 indicates that 100 percent of the route is within shallow bedrock. However, some
24 bedrock may be soft enough to accommodate soil drilling methods to construct foundations. The
25 bedrock characteristics will be more completely determined by on-site geotechnical testing.
26 Micropiles are high-capacity, small-diameter steel casing that are drilled into place, reinforced
27 with an internal structural bar, and pressure grouted. The grout creates a bond between the
28 interior casing wall and structural bar, as well as the external casing wall and the rock.
29 Micropiles are installed using water flush rotary drilling or rotary percussion drilling techniques.
30 This can be done remotely and requires a limited amount of disturbance and ground clearing.
31 Each pile measures between 6 and 12 inches in diameter and micropiles consistently achieve
32 capacities of 60 to 100 tons, with special installations of up to 200 tons. Drilled micropiles offer
33 excellent axial up and down capacity in hard rocks, with the added advantage of capability of
34 helicopter importing the micropile drill rig.
35 Rock anchors supporting a foundation “pile cap” is most advantageous when the rock is very
36 hard and very shallow. It consists of two parts; a foundation “pile cap” in addition to anchor bars
37 embedded in the grouted or epoxy anchor holes. The top part of the bar is embedded in the
38 concrete of the “pile cap”. The depth of embedment, diameter and number of anchor bars will
39 depend upon the uplift, moment and sliding force on the “pile cap”. The determination of
40 whether a rock formation is suitable for installation of rock anchors is a geotechnical
November 2011 43
Transmission Line and Substation Components Appendix B
1 determination based on rock quality. Since the bearing capacity of rock is usually much greater,
2 geotechnical assessments would center around designing for uplift. The rock surfaces may be
3 roughened grooved or shaped to increase the uplift capacity, depending on the final “pile cap”
4 configuration. This system may also be considered with the use of epoxy grout anchors to
5 facilitate a tidy construction area.
6 2.5.2 Helicopter Use
7 Access roads are required to each tower site for construction and for operation and
8 maintenance activities. Helicopters may be used to support these activities. Project construction
9 activities potentially facilitated by helicopters may include delivery of construction laborers,
10 equipment, and materials to structure sites; structure placement; hardware installation; and wire
11 stringing operations. Helicopters may also be used to support the administration and
12 management of the Project by IPC. Where construction access by truck is not practical due to
13 steep terrain, ATV trails may be utilized to support maintenance activities. The use of helicopter
14 construction methods for this Project will not change the length of the access road system
15 required for operating the Project because vehicle access is required to each tower site
16 regardless of the construction method employed.
17 The typical single-circuit 500-kV towers weigh approximately 25,000 pounds and in some cases
18 it may be desirable to employ heavy lift helicopters in the tower erection process. To allow the
19 construction contractor flexibility in construction methods, the construction specification will be
20 written to allow the contractor the option of using ground-based or helicopter construction
21 methods, or a combination thereof. Use of a helicopter for structure erection may be driven by
22 various factors, including access to the structure locations, construction schedule, and/or
23 construction economics.
24 When helicopter construction methods are employed, helicopter construction activities will be
25 based at a fly yard, which is a Project-material staging area (see Table 2-5). The fly yards will
26 be approximately 10 to 15 acres in area and will be sited at locations to permit a maximum fly
27 time of 4 to 8 minutes to reach structure locations, typically at about 10-mile intervals. Fly yards
28 will be used for material storage and erection of structure sections prior to transport to the final
29 structure locations for installation. Additionally, fueling trucks, maintenance trucks, and
30 operations crews will be based in the fly yards. Appropriate dust control measures will be
31 implemented at these fly yard locations as well as the locations where helicopters will be used
32 along the route.
33 Prior to installation, each tower structure will be assembled in multiple sections at the fly yard.
34 Tower sections or components will be assembled by weight based on the lifting capacity of the
35 helicopter in use. The lift capacity of helicopters is dependent on the elevation of the fly yard,
36 the tower site, and the intervening terrain. The heavy lift helicopters that could be used to erect
37 the single-circuit 500-kV tower sections will be able to lift a maximum of 15,000 to 20,000
38 pounds per flight, depending on elevation.
39 After assembly at the fly yard, the tower sections will be attached by cables from the helicopter
40 crane to the top four corners of the structure section and airlifted to the structure location. Upon
41 arrival at the structure location, the section will be placed directly on to the foundation or atop
42 the previous structure section. Guide brackets attached on top of each section will assist in
43 aligning the stacked sections. Once aligned correctly, line crews will climb the structures to bolt
44 the sections together permanently.
45 It should be noted that the fly yard locations provided are considered approximate and subject
46 to change, additions, or deletions upon acquisition of an installation contractor prior to the
47 beginning of construction. Upon completion of field review, a final determination will be made on
November 2011 44
Transmission Line and Substation Components Appendix B
1 the necessity of certain fly yards and the respective locations that provide the most efficient,
2 economic, safest, and least impact use of the fly yards that are needed.
3 2.5.3 Water Use
4 Construction of the transmission lines and substations will require water. Major water uses are
5 for transmission line structure and substation foundations, and dust control during ROW and
6 substation grading and site work. A minor use of water during construction will include the
7 establishment of substation landscaping where required. Table 2-7 lists the estimated amount of
8 water required for the Project by County.
9 Table 2-7. Estimated Water Usage for Construction by County
Foundation Dust Total, All
Construction Substation Communication Abatement Uses
County (gallons) (gallons) Sites (gallons) (gallons) (gallons)
Morrow 350,000 263,500 400 1,400,000 2,013,900
Umatilla 450,000 NA 400 1,500,000 2,000,000
Union 300,000 NA 700 1,200,000 1,500,000
Baker 600,000 NA 400 2,300,000 2,900,000
Malheur 550,000 NA 1,100 2,200,000 2,800,000
Owyhee 200,000 301,000 0 750,000 1,251,000
10 Transmission lines use water for two primary purposes: foundation construction and ROW dust
11 control. The required water will be procured from municipal sources, from commercial sources,
12 or under a temporary water use agreement with landowners holding existing water rights. No
13 new water rights will be required. In the construction of foundations, water is transported to the
14 batch plant site where it will be used to produce concrete. From the batch plant the wet concrete
15 will be transported to the structure site in concrete trucks for use in foundation installation (refer
16 to Section 2.2.4 for more details on foundation installation).
17 Construction of the transmission lines and related facilities will generate a temporary increase in
18 fugitive dust. If the level of fugitive dust is too high in specific Project areas, as determined in
19 cooperation with the landowner or agency, water will be applied to disturbed areas to minimize
20 dust.
21 Water usage for substation construction is primarily for dust control during site preparation work.
22 During this period, construction equipment will be cutting, moving, and compacting the subgrade
23 surface. As a result, water trucks patrolling the site to control dust will make as many as one
24 pass per hour over the station site. Once site preparation work is complete, concrete for the
25 placement of foundations becomes the largest user of water and dust control becomes minimal.
26 Once site grading is complete, the balance of the substation construction work will be performed
27 on bare subgrade soil or subgrade with a thin layer of rock. Fire risk will be minimal due to the
28 bare ground or rock surface and will be contained within the confines of station fenced area.
November 2011 45
Transmission Line and Substation Components Appendix B
13 IPC’s proposed schedule identifies general construction timeframes for the transmission line
14 and substations, generally 2 to 2.5 years. Project-wide, the workforce will reach a peak of
15 approximately 300 to 350 workers in the late summer months in 2014 and 2015. The
16 construction personnel peak on site in any portion of the route will be when the wire stringing
17 operations begin while several other operations are occurring at the same time, which includes
18 foundation installation, hauling materials, assembling structures, and erecting/setting structures.
19 Due to snowfall at the higher elevations, the workforce will be slightly lower in the winter
20 months.
21 With respect to each substation, installation of the ground grid, installation of the conduit and
22 cable trench system, assembly and erection of steel structures, construction of the control
23 building, and installation of major equipment will start when the foundations are 50 percent
24 complete and will overlap with each other, resulting in the highest concentration of the work
25 force on site.
26 The substation work is estimated to take between 40 and 60 personnel at each site. Site
27 grading requires a small number of people including a surveyor, heavy equipment operators,
28 foreman, and construction management personnel. Each station will require numerous concrete
29 crews in order to complete the below grade construction and concrete placement on schedule.
30 Concrete will be provided by a batch plant producing approximately 150 cubic yards per day
31 delivered in 8- to 10-cubic yard trucks. Other below-grade crews will be needed to install
32 conduit, cable trench, and ground mat material. The below-grade crews will be on site
33 overlapping the schedule of the concrete crew. Several three-man crews working with boom
34 trucks and bucket trucks will erect the steel and install the physical equipment in the yard.
35 Considering the size of the substation expansions, this will require approximately three fully
36 equipped crews per station. Electrical installation will be handled by 20 men arranged into two-
37 man teams alternating between indoor and outdoor activity. Construction will generally occur
8
EPC contract means that the final engineering, all or some of the procurement, and the construction are performed by one
contractor.
9
A spread is a geographic segment within which a complete construction sequence will be executed.
November 2011 46
Transmission Line and Substation Components Appendix B
1 between 7 a.m. and 7 p.m., Monday through Saturday. Additional hours may be necessary to
2 make up schedule deficiencies or to complete critical construction activities.
3 2.6.2 Construction Equipment and Traffic
4 Equipment required for construction of the Project transmission lines and substations will
5 include, but is not limited to, that listed in Table 2-9 and Table 2-10. The Hemingway Substation
6 is an existing substation planned for the minor Project additions within the existing fence line.
7 Table 2-10 includes construction equipment requirements for both substations. These tables
8 also include the anticipated daily duration of equipment use for each type. Table 2-11 provides
9 an estimate of the average and peak construction traffic during the construction period by
10 spread.
11 Construction access will occur at several locations along the transmission line route, resulting in
12 dispersed construction traffic. Truck deliveries will normally be on weekdays between 7:00 a.m.
13 and 7:00 p.m.
14 Table 2-9. Transmission Line Construction Equipment Requirements
Spread 11 Spread 2
Equipment Qty. hrs/ day days/ wk Qty. hrs/ day days/ wk
Pickup 10 8 6 10 8 6
Bulldozer 3 4 6 3 4 6
Motor Grader 2 4 6 2 4 6
Water Truck 2 6 6 2 6 6
Hole Digger 2 8 6 2 8 6
Truck (2-ton) 3 5 6 3 5 6
Concrete Truck 4 6 6 4 6 6
Carry All 12 6 6 12 6 6
Crane 7 7 6 7 7 6
Steel Haul Truck 2 7 6 2 7 6
Fork Lift 3 6 6 3 6 6
Wire Reel Trailer 6 7 6 6 7 6
Diesel Tractor 5 5 6 5 5 6
Boom Truck (5-ton) 3 6 6 3 6 6
Splicing Truck 2 3 6 2 3 6
3-Drum Puller 2 4 6 2 4 6
Single Drum Puller 2 3 6 2 3 6
Tensioner 2 4 6 2 4 6
Sagging Dozer 2 3 6 2 3 6
Static Wire Reel Trailer 2 5 6 2 5 6
Dump Truck 2 4 6 2 4 6
Loader 3 4 6 3 4 6
Helicopter2 1 6 6 1 6 6
1
15 Project divided into two segments of approximately equal length.
2
16 For structures which can only be set by helicopter, or if the contractor elects to erect structures by helicopter, one or
17 more heavy lift helicopters would be required.
18
November 2011 47
Transmission Line and Substation Components Appendix B
November 2011 48
Transmission Line and Substation Components Appendix B
2 The equipment required for transmission line construction is similar for both the 500-kV and
3 69/138-kV lines, although the equipment needed for smaller voltage lines construction is
4 generally smaller than for 500-kV construction. The following is a summary of anticipated
5 equipment to be used for each construction activity. Survey work only requires the use of pickup
6 trucks or ATVs. Road construction will utilize pickups, bulldozers, motor graders, and water
7 trucks. To dig holes and install the directly embedded structures or install 500-kV foundations it
8 is anticipated that pickup trucks, 2-ton trucks, hole diggers, bulldozers, concrete trucks, water
9 trucks, carry alls, cranes, hydro crane, wagon drill, dump trucks, and front-end loaders will be
10 used. Hauling lattice steel members, tubular poles, braces and hardware to the structure sites
11 will require the use of steel haul trucks; carry alls, cranes, and forklifts. For assembly and
12 erection of structures it is anticipated that pickup trucks, 2-ton trucks, carry alls, cranes, and a
13 heavy lift helicopter may be used. Wire installation requires the most equipment including
14 pickups, wire reel trailers, diesel tractors, cranes, 5-ton boom trucks, splicing trucks, three drum
15 pullers, single drum pullers, tensioners, sagging dozers, carry alls, static wire reel trailers, and a
16 light helicopter. Final cleanup, reclamation, and restoration will utilize pickups, 2-ton trucks,
17 bulldozers, motor graders, dump trucks, front-end loaders, and water trucks. The highest level
18 of traffic will be when the wire stringing operations begin while several other operations are
19 occurring at the same time which will likely include excavating holes, installing foundations,
20 hauling steel, assembling structures, and erecting structures.
21 For the substation work, the highest level of traffic will be during site grading and foundation
22 installation. It is estimated that 2,000 to 4,000 cubic yards of topsoil will not be suitable for re-
23 use at the Grassland Substation site and will have to be disposed of at an authorized off-site
November 2011 49
Transmission Line and Substation Components Appendix B
1 location. Dump trucks will be leaving and returning to the site on a constant basis each day for
2 the duration of the site grading. Each site will require between 4,000 and 7,000 cubic yards of
3 concrete. Delivering, placing, and finishing concrete is labor intensive. Once concrete placement
4 is complete, traffic on the surrounding roads will subside. Workers will arrive in the morning and
5 leave at the end of the day. The balance of daily traffic will be material deliveries from
6 storerooms, which will probably be one or two trips per day. Each substation will require the
7 delivery of permitted loads such as transformers and/or reactors. Each reactor or transformer
8 bank required will require four large multiple-wheel lowboy trucks. Delivery will be scheduled to
9 match the completion of their respective foundations.
10 2.6.3 Removal of Facilities and Waste Disposal
11 Substation and ROW construction will generate a variety of solid wastes including concrete,
12 hardware, and wood debris. The solid wastes generated during construction will be recycled or
13 hauled away for disposal. Excavation along the ROW and at substations will generate solid
14 wastes that could potentially be used as fill; however, some of the excavated material will be
15 removed for disposal. Excavated material that is clean and dry will be spread along the ROW.
16 The volumes shown in Table 2-12 reflect the waste that will be hauled away and not disposed of
17 in the ROW for each segment during construction of the Project.
18 Table 2-12. Solid Waste Generation from Construction Activities
Transmission Line Communication Sites Substation
Imported Imported
Native Solid Native Solid Native Imported
Material Waste Material Waste Material Solid Waste
Total1 Total2 Total1 Total2 Total1 Total2
County (cu. yard) (cu. yard) (cu. yard) (cu. yard) (cu. yard) (cu. yard)
Morrow 1,800 700 100 10 2,000 200
Umatilla 1,900 800 110 10 NA NA
Union 1,600 700 200 20 NA NA
Baker 2,900 1,200 100 10 NA NA
Malheur 2,800 1,200 330 30 NA NA
Owyhee 1,000 400 0 0 400 100
1
19 Native materials consist of stripped vegetation, excess soil, large rocks, or other natural materials that cannot be reused on-site.
20 This was assumed at approximately 10% of excavation. Native materials may be suitable for disposal at fill dirt sites, or County
21 Construction and Demolition landfills, as approved by local entities.
2
22 Imported solid waste is non-hazardous refuse delivered to the Project, such containers, boxes, bags, sacks, packing materials,
23 broken insulators, scrap conductor, empty wire spools, and other miscellaneous non-hazardous paper, plastic or similar materials.
24 These are materials that will be recycled, hauled directly, or placed in a dumpster or roll-off for disposal at a municipal solid waste
25 landfill, as approved by local entities.
26
27 The majority of waste associated with substation construction results from spoils created during
28 site grading. The values shown in Table 2-12 reflect the amount of vegetation and rock larger
29 than 6 inches in diameter that cannot be processed and converted into backfill for compaction.
30 Very little of the soil excavated during foundation installation is waste product. Above-grade
31 waste will be packing material such as crates, pallets, and paper wrapping to protect equipment
32 during shipping. It is assumed a 12-yard dumpster will be filled once a week with waste material
33 for the duration of each substation project.
34 2.6.4 Construction Schedule
35 IPC intends to continue to refine the design of the Project during the BLM approval process in
36 order to immediately commence construction if the Project is approved. Final engineering
November 2011 50
Transmission Line and Substation Components Appendix B
1 surveys will determine the exact locations of towers, access roads, and other features prior to
2 the start of construction and will be included in the Plan of Development. Due to the broad
3 scope of construction, the varied nature of construction activities, and the geographic diversity
4 of the Project area, IPC intends to hire multiple contractors to complete Project work within the
5 projected timeframe and in accordance with industry performance standards. The Proposed
6 Action will involve one EPC contracts with two construction spreads for the transmission line
7 and division of the Project into discrete construction phases. Each portion of the route will be
8 under construction at the same time. IPC developed a Project construction schedule based on
9 this strategy. Figure 2-6 provides a general schedule, showing preliminary construction
10 schedule time frames.
11 Although the construction rate of progress will be reduced in the winter, IPC has planned an
12 aggressive schedule and it is anticipated that construction will continue through the winter
13 months in the lower-elevation areas of the Project, except during winter storms. In the higher-
14 elevation areas of the Project, winter storms and snow will limit access to the ROW, for example
15 in the Blue Mountains. In these areas, it is expected that construction will be suspended on
16 some portions of the ROW during the peak winter months and construction resources will either
17 be demobilized or shifted to other portions of the Project.
18 Transmission line construction commences with contractor mobilization. The contractor will
19 mobilize equipment and personnel to the construction site at various stages in the Project
20 schedule depending on operational requirements. This will cumulatively require approximately
21 30 days throughout the schedule for each segment. Construction management, engineering
22 support, inspection, materials handling, and administration are required throughout the Project.
23 First, surveyors will start at one end of the route and stake the locations of access roads. Road
24 construction can start 1 to 2 weeks after the surveyors begin, which may require clearing in
25 higher elevations where tree removal is required prior to road construction. After a couple of
26 weeks of road construction another survey crew can begin staking the structure locations. A
27 week or two after the survey crew starts staking structure locations, excavation of holes for
28 foundations for 500-kV towers, or for directly embedded poles for smaller voltage structures,
29 can begin. For 500-kV construction, the installation of the concrete pier foundations will begin
30 within the next couple of weeks. The foundations need time to cure and develop to full structural
31 strength (measured by compressive strength) before lattice towers can be installed. Five to six
32 weeks after foundation installation has begun, lattice tower assembly and erection can begin.
33 For 138/69-kV construction, structure assembly and setting can begin immediately after the
34 excavation of holes has begun. The wire installation crews will start approximately 8 to 12
35 weeks after assembly and erection/setting begins. This will be followed by final cleanup,
36 reclamation, and restoration.
37
November 2011 51
Transmission Line and Substation Components Appendix B
1
2 Figure 2-6. Project Construction Schedule
November 2011 52
Transmission Line and Substation Components Appendix B
1 Substation construction includes five activities: 1) site grading (grading and access road
2 development), 2) below-grade construction (primarily the installation of foundations, 3) above-
3 grade construction (steel erection and building construction), 4) electrical (installation and
4 termination of control wiring), and 5) testing (functional testing of control and monitoring
5 schemes). Typically, these activities overlap and complement each other, allowing the
6 construction of a substation to proceed more quickly than line construction. It is estimated that
7 the site grading activity and access road work for Grassland and Hemingway substations will
8 take 4 to 8 weeks to complete, depending on the size of the site.
9 Below-grade construction can be completed in 3 months or less for the Hemingway Substation.
10 In this case, the basic infrastructure is already in place, having been installed with the initial
11 substation and designed for the future expansion requirements. If the Grassland Substation is
12 not constructed ahead of the Project and full buildout is required, the duration will be longer.
13 Above-grade construction duration is highly dependent on the level of construction force the
14 contractor chooses. For the substation expansions at Grassland or Hemingway Substations, it is
15 estimated that erection of steel, bus assembly, and major equipment assembly will take up to
16 9 months. Due to the size of each station, many crews can work on steel erection and
17 equipment assembly without interfering with each other. The greatest amount of schedule
18 recovery or acceleration in a station’s construction schedule can be achieved during this
19 timeframe. Electrical construction is a long and labor-intensive task. Although multiple crews
20 can work in a yard at any given time, the space in a control building is very limited and will
21 determine the length of this task. In the case of each of these stations, given the size and type
22 of equipment to be installed, there will be miles of cable to be pulled into conduit and duct banks
23 and thousands of connections to be made and double checked prior to the start of testing. New
24 substations will take longer than existing substations that already have the basic infrastructure
25 in place.
26 Prior to starting construction, IPC may be required to conduct on-site surveys in accordance
27 with applicable protocols or mitigation measures adopted by BLM and other agencies as Project
28 conditions. Accordingly, adjustments might occur to the Project schedule as necessary to avoid
29 sensitive resources. Pre-construction activities, including pre-construction environmental
30 surveys, materials procurement, design, contracting, ROW acquisition, and permitting efforts,
31 are not shown in the summary schedule.
32 The schedule is predicated upon IPC’s ability to complete the following tasks in a timely
33 manner:
34 x Secure all necessary permit approvals;
35 x Secure agency support;
36 x Complete biological and cultural survey work;
37 x Construct within environmental time constraints;
38 x Order and receive equipment;
39 x Secure construction contractor resources and associated construction equipment;
40 and
41 x Maintain continuous construction activity with no delay due to environmental,
42 administrative, or legal issues.
43
November 2011 53
Transmission Line and Substation Components Appendix B
November 2011 54
Transmission Line and Substation Components Appendix B
November 2011 55
Transmission Line and Substation Components Appendix B
November 2011 56
Transmission Line and Substation Components Appendix B
November 2011 57
Transmission Line and Substation Components Appendix B
1 include insulators, hardware or tower members. It is expected that these replacements will be
2 required infrequently.
3 IPC plans to conduct maintenance on the critical 500-kV transmission line system using live line
4 maintenance techniques. Maintenance on the transmission lines can be completed safely using
5 live line techniques thereby avoiding an outage to the critical transmission line infrastructure.
6 High reach bucket trucks along with other equipment are used to conduct these activities. For
7 the 500-kV lattice tower structures, this requires that adequate space be available at each
8 structure site so that the high reach bucket truck can be positioned to one side or the other of
9 the structure and reach up and over the lower phases to access the upper center phase for live-
10 line maintenance procedures. For the H-frame and monopole structures, this requires that
11 adequate space be available at each structure site so that a bucket truck can be positioned to
12 access the outside phases. Figure 3-1 depicts the space requirements for live-line maintenance
13 for the 500-kV lattice structures. The size and location of these required pads near the
14 structures may vary depending on the side slope and access road at each site. The work areas
15 and pads will be cleared to the extent needed to safely complete the work. These pads will
16 remain in place after construction, but will be revegetated after the initial construction is
17 completed.
18
November 2011 58
Transmission Line and Substation Components Appendix B
1
2 Figure 3-1. Live-line Maintenance Space Requirements, Single-Circuit 500-kV
3 Lattice Tower
November 2011 59
Transmission Line and Substation Components Appendix B
November 2011 60
Transmission Line and Substation Components Appendix B
1
2 Single-Circuit 500 kV
3
4
5 Figure 3-2. Right-of-Way Vegetation Management
November 2011 61
Transmission Line and Substation Components Appendix B
1 Vegetation will be removed using mechanical equipment such as chain saws, weed trimmers,
2 rakes, shovels, mowers, and brush hooks. Clearing efforts in heavy growth areas will use
3 equipment such as a Hydro-Ax or similar. The duration of activities and the size of crew and
4 equipment required will depend on the amount and size of the vegetation to be trimmed or
5 removed.
6 In selected areas, herbicides may be used to control noxious weeds and to meet vegetation
7 management objectives. All herbicide applications will be performed in accordance with federal,
8 state, and local regulations, and in compliance with managing land agency requirements.
9 3.1.6 Noxious Weed Control
10 The States of Idaho and Oregon list modes of action that are capable of disseminating noxious
11 weeds and the duties to control the spread of listed noxious weeds. Equipment and supplies
12 necessary for line construction and future operation and maintenance activities, and the
13 activities themselves, are possible agents for the spread of noxious weeds. Under the
14 requirements of a ROW grant or SUP, IPC is responsible for control of noxious weed species
15 that result or will result from the construction, operation, and maintenance of the improvements
16 authorized under the grant. Therefore, a noxious weed control strategy to reduce the
17 opportunity for weeds to invade new areas and to minimize the spread of weeds within the
18 Project area will be addressed in the Framework Reclamation Plan.
19 The responsible party will clean all equipment that may operate off-road or disturb the ground
20 before beginning construction or operation and maintenance activities within a pre-determined
21 project area. This process will clean tracks and other parts of the equipment that could trap soil
22 and debris and will reduce the potential for introduction or spread of undesirable exotic
23 vegetation. Preferably, the cleaning will occur at an IPC operation center, commercial car wash,
24 or similar facility. Vehicles traveling only on established paved roads are not required to be
25 cleaned.
26 3.1.7 Substation and Communication Site Maintenance
27 Substation and communication site monitoring and control functions are performed remotely
28 from IPC’s operation center in Boise, Idaho. Unauthorized entry into substations or
29 communication sites is prevented with the provision of fencing and locked gates. Warning signs
30 will be posted and entry to the operating facilities will be restricted to authorized personnel.
31 Project substations and communication sites will not be staffed; however, a remotely monitored
32 security system will be installed. Several forms of security are planned for each of the locations,
33 although the security arrangements at each of the substations or communication sites may differ
34 somewhat. Security measures may include fire detection in the control building via the remote
35 monitoring system; alarming for forced entry; and a perimeter security system coupled with
36 remote sensing infrared camera equipment in the fenced area of the station to provide visual
37 observation/confirmation to the system operator of disturbances at the fence line.
38 Maintenance activities include equipment testing, equipment monitoring and repair, and
39 emergency and routine procedures for service continuity and preventive maintenance. It is
40 anticipated that maintenance at each substation will require approximately six trips per year by a
41 2- to 4-person crew. Routine operations will require one or two workers in a light utility truck to
42 visit the substations monthly. Typically, once per year a major maintenance inspection will take
43 place requiring up to 15 personnel for 1 to 3 weeks. Communication sites will be visited every 2
44 to 3 months by one individual in a light truck to inspect the facilities. Annual maintenance will be
45 performed by a two man crew in a light truck over a 2- to 5-day period. If substation landscaping
46 is required by the permitting agency, drought-tolerant plant materials will be used to minimize
47 watering requirements after plant establishment.
November 2011 62
Transmission Line and Substation Components Appendix B
1 Safety lighting at the substations will be provided inside the substation fence for the purpose of
2 emergency repair work. Because night activities are not expected to occur more than once per
3 year, the safety lighting inside the substation fence will normally be turned off. One floodlight,
4 mounted near the entry gate to safely illuminate the substation entry gate, may be left on during
5 nighttime hours.
November 2011 63
Transmission Line and Substation Components Appendix B
1 handled round point shovel, size “0” or larger. In addition, each motor patrol, truck
2 and passenger-carrying vehicle shall be equipped with a double-bit axe or Pulaski,
3 3½ pounds or larger.
4 x Each internal combustion engine shall be equipped with a spark arrester meeting
5 either 1) USDA Forest Service Standard 5100-1a, or 2) appropriate Society of
6 Automotive Engineers recommended practice J335(b) and J350(a) as now or
7 hereafter amended unless it is:
8 – Equipped with a turbine-driven exhaust supercharger such as the turbocharger.
9 There shall be no exhaust bypass.
10 – A passenger-carrying vehicle or light truck, or medium truck up to 40,000 GVW,
11 used on roads and equipped with a factory-designed muffler complete with
12 baffles and an exhaust system in good working condition.
13 – A heavy-duty truck, such as a dump or log truck, or other vehicle used for
14 commercial hauling, used on roads only and equipped with a factory-designed
15 muffler and with a vertical stack exhaust system extending above the cab.
16 x Exhaust equipment, including spark arresters and mufflers, shall be properly installed
17 and constantly maintained in serviceable condition.
18 When working on public or National Forest lands, IPC’s employees and contractors will be
19 equipped with approved suppression tools and equipment. IPC or their construction contractor
20 will notify local fire authorities and the BLM or Forest Service (as appropriate) if a Project-related
21 fire occurs within or adjacent to a construction area. Smoking is not allowed outside of vehicles,
22 cleared storage yards/staging areas, and/or construction trailers.
23 If IPC becomes aware of an emergency situation that is caused by a fire on or threatening BLM-
24 managed or National Forest lands and that could damage the transmission lines or their
25 operation, they will notify the appropriate agency contact. Specific construction-related activities
26 and safety measures will be implemented during construction of the transmission line to prevent
27 fires and to ensure quick response and suppression if a fire occurs. Typical practices to prevent
28 fires during construction and maintenance/repair activities include brush clearing prior to work,
29 stationing a water truck at the job site to keep the ground and vegetation moist in extreme fire
30 conditions, enforcing red flag warnings, providing “fire behavior” training to all pertinent
31 personnel, keeping vehicles on or within designated roads or work areas, and providing fire
32 suppression equipment and emergency notification numbers at each construction site.
November 2011 64
Transmission Line and Substation Components Appendix B
1 4.0 DECOMMISSIONING
2 The proposed transmission line will have a projected operational life of at least 50 years or
3 longer. At the end of the useful life of the Project and if the facility were no longer required, the
4 transmission line will be removed from service. At such time, conductors, insulators, and
5 hardware will be dismantled and removed from the ROW. Structures will be removed and
6 foundations removed to below ground surface. Decommissioning and restoration on USFS
7 lands shall be consistent with the terms and conditions of the USFS authorization and shall not
8 include abandoning foundations or leaving in-place.
9 Following abandonment and removal of the transmission line structures and equipment from the
10 ROW, any areas disturbed areas during line dismantle will be restored and rehabilitated. If a
11 substation is no longer required, the substation structures and equipment will be dismantled and
12 removed from the site. The station structures will be disassembled and either re-used at another
13 station or sold for scrap. Major equipment such as breakers, transformers, and reactors will be
14 removed, refurbished, and stored for use at another facility. Foundations will be either
15 abandoned in-place or cut off below ground level and buried.
16 IPC describes roads necessary for the operation and maintenance of transmission lines as
17 access roads or service roads. The sole purpose of service roads is to provide maintenance
18 crews access to the transmission lines. These roads will not exist if the transmission lines did
19 not exist. In contrast, access roads serve a broader purpose, such as contributing to the federal,
20 county, or state road systems. Access roads provide direct or indirect access to the
21 transmission lines but that access is not their primary purpose. IPC is responsible for the
22 reclamation of service roads following abandonment and in accordance with the landowner’s
23 direction but is not responsible for reclamation of access roads unless mutually agreed upon by
24 IPC and the landowner. Service roads will be abandoned following removal of the structures
25 and lines and may be abandoned while the lines are in-service if they are determined to no
26 longer be necessary.
27 When a service road has been identified as no longer necessary, the road will be reclaimed and
28 seeded as soon as possible during the optimal seeding season. In some cases, reseeding may
29 not be necessary, given the existing amount of soil compaction and vegetation currently in
30 place.
31 The seed mix used for any restoration and revegetation project will be determined in
32 consultation with the landowner or land-managing agency. All seed will meet all of the
33 requirements of the Federal Seed Act and applicable Idaho and Oregon laws regarding seeds
34 and noxious weeds. Only seed certified as “noxious weed-free” will be used. If requested, IPC
35 or their contractor will provide the landowner with evidence of seed certification. Any seed
36 mixture will not contain aggressive, non-native species that might invade the site. Where
37 necessary, the surface of the ground will be prepared prior to seeding. Where practical, IPC will
38 follow these guidelines for preparing the seedbed:
39 x The road surface will be cleared of foreign materials, such as garbage, paper, and
40 other materials, but all rocks, limbs, or minor woody debris will be left in place. IPC or
41 their contractor will prepare the seedbed immediately prior to seeding.
42 x Under the right soil-moisture conditions, a standard disk or spring bar harrow will be
43 used to roughen the topsoil layer to create the desired surface texture before the
44 seed is applied. Dirt clods and chiseled voids resulting from the roughening process
45 increase the surface area for water collection and provide micro-sites for seed
November 2011 65
Transmission Line and Substation Components Appendix B
1 establishment. The soil should be disked or harrowed to no more than 2 inches deep
2 at a time when soil moisture allows the surface to remain rough, with clods
3 approximately 2 to 4 inches in diameter.
4 x Disking or harrowing will be performed parallel to surface contours. In this way,
5 downslope alignment of furrows can be avoided. In areas that already have the
6 desired soil characteristics; the seedbed does not need to be prepared.
7 After the seedbed has been prepared, IPC or their contractor will broadcast the seed on the
8 disturbed area, after which the seed will be lightly harrowed into the roadbed or raked into the
9 ground. Mulch and fertilizers may be added if necessary. An area will not be seeded when wind
10 velocities prohibit the seed mix from being applied evenly. If the seed does not germinate and
11 establish to an agreed-upon level of vegetation cover (e.g., consistent with adjacent site
12 conditions) after two growing seasons, IPC or their contractor will do a one-time reseeding
13 during a period acceptable to the landowner.
14 Other seeding methods, such as drilling, hydroseeding, or aerial application, may be used
15 depending on the area that requires reclamation and site conditions.
16
November 2011 66