PIPING SYSTEM

Activity ID Activity Name Original Start Finish May 2019 June 2019 July 2019 August 2019 September 2019 ber 2019
Duration
21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06

OS-BL-1 PIPING
PIPIN SYSTEM 90d 01-May-19 08:00 03-Sep-19 16:00 03-Sep-19 16:00, OS-BL-1 PIPING S

OS-BL-1.1 Milestone
Mi 86d 01-May-19 08:00 29-Aug-19 08:00 29-Aug-19 08:00, OS-BL-1.1 Milestone
A1000 Star 0d 01-May-19 08:00 Star
A1010 Finish 0d 29-Aug-19 08:00 Finish

OS-BL-1.2 PR
PRELIMINARIES 20d 01-May-19 08:00 28-May-19 16:00 28-May-19 16:00, OS-BL-1.2 PRELIMINARIES

A1020 Mobilization 4d 01-May-19 08:00 06-May-19 16:00 Mobilization


A1030 Direction Kit 4d 07-May-19 08:00 10-May-19 16:00 Direction Kit
A1040 Shop Drawing 4d 13-May-19 08:00 16-May-19 16:00 Shop Drawing
A1050 TKBT Training, Administration 4d 17-May-19 08:00 22-May-19 16:00 TKBT Training, Administration & Report
A1060 Health, Safety, Cleaning, Secu 4d 23-May-19 08:00 28-May-19 16:00 Health, Safety, Cleaning, Security & Health Insurance
A1070 Electrical Temporary (STPM S 4d 23-May-19 08:00 28-May-19 16:00 Electrical Temporary (STPM Standard)
A1080 Scafolding 4d 23-May-19 08:00 28-May-19 16:00 Scafolding

OS-BL-1.3 Tank
Ta Farm Refinery & Fr 8d 23-May-19 08:00 03-Jun-19 16:00 03-Jun-19 16:00, OS-BL-1.3 Tank Farm Refinery & Fractination

OS-BL-1.3.1 Oi
Oil Line (SS Pipe) 4d 23-May-19 08:00 28-May-19 16:00 28-May-19 16:00, OS-BL-1.3.1 Oil Line (SS Pipe)
A1090 Material Erection 3d 23-May-19 08:00 27-May-19 16:00 Material Erection
A1100 Welding Joint 3d 23-May-19 08:00 27-May-19 16:00 Welding Joint
A1110 Test Package 1d 28-May-19 08:00 28-May-19 16:00 Test Package
OS-BL-1.3.2 Valve
Va Erection 2d 29-May-19 08:00 30-May-19 16:00 30-May-19 16:00, OS-BL-1.3.2 Valve Erection
A1120 Gate Valve 2d 29-May-19 08:00 30-May-19 16:00 Gate Valve
A1130 Ball Valve 2d 29-May-19 08:00 30-May-19 16:00 Ball Valve
A1140 Check Valve 2d 29-May-19 08:00 30-May-19 16:00 Check Valve
A1150 Expantion Joint 2d 29-May-19 08:00 30-May-19 16:00 Expantion Joint
A1160 Y-Strainer 2d 29-May-19 08:00 30-May-19 16:00 Y-Strainer
OS-BL-1.3.3 Instrument
In Erection 6d 27-May-19 08:00 03-Jun-19 16:00 03-Jun-19 16:00, OS-BL-1.3.3 Instrument Erection
A1170 Control Valve 2d 31-May-19 08:00 03-Jun-19 16:00 Control Valve
A1180 Actuator Valve 2d 29-May-19 08:00 31-May-19 08:00 Actuator Valve
A1190 Flow meter 2d 27-May-19 08:00 29-May-19 08:00 Flow meter
OS-BL-1.3.4 Su
Support Pipe 2d 27-May-19 08:00 28-May-19 16:00 28-May-19 16:00, OS-BL-1.3.4 Support Pipe
A1200 Pipe Shoes 2d 27-May-19 08:00 28-May-19 16:00 Pipe Shoes
A1210 Support Pipe 2d 27-May-19 08:00 28-May-19 16:00 Support Pipe

OS-BL-1.4 Tank
Ta Farm Speciality Fat 6d 29-May-19 08:00 05-Jun-19 16:00 05-Jun-19 16:00, OS-BL-1.4 Tank Farm Speciality Fat

OS-BL-1.4.1 Oi
Oil Line (SS Pipe) 3d 29-May-19 08:00 31-May-19 16:00 31-May-19 16:00, OS-BL-1.4.1 Oil Line (SS Pipe)
A1220 Material Erection 2d 29-May-19 08:00 30-May-19 16:00 Material Erection
A1230 Welding Joint 2d 29-May-19 08:00 30-May-19 16:00 Welding Joint
A1240 Test Package 1d 31-May-19 08:00 31-May-19 16:00 Test Package
OS-BL-1.4.2 Valve
Va Erection 2d 31-May-19 08:00 03-Jun-19 16:00 03-Jun-19 16:00, OS-BL-1.4.2 Valve Erection
A1250 Gate Valve 2d 31-May-19 08:00 03-Jun-19 16:00 Gate Valve
A1260 Ball Valve 2d 31-May-19 08:00 03-Jun-19 16:00 Ball Valve
A1270 Check Valve 2d 31-May-19 08:00 03-Jun-19 16:00 Check Valve
A1280 Expansion Joint 2d 31-May-19 08:00 03-Jun-19 16:00 Expansion Joint
A1290 Y-Strainer 2d 31-May-19 08:00 03-Jun-19 16:00 Y-Strainer
OS-BL-1.4.3 Instrument
In Erection 6d 29-May-19 08:00 05-Jun-19 16:00 05-Jun-19 16:00, OS-BL-1.4.3 Instrument Erection
A1300 Control Valve 2d 04-Jun-19 08:00 05-Jun-19 16:00 Control Valve
A1310 Actuator Valve 2d 31-May-19 08:00 04-Jun-19 08:00 Actuator Valve

Actual Work Critical Remaining Work Summary Page 1 of 4 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


PIPING SYSTEM

Activity ID Activity Name Original Start Finish May 2019 June 2019 July 2019 August 2019 September 2019 ber 2019
Duration
21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
A1320 Flow meter 2d 29-May-19 08:00 31-May-19 08:00 Flow meter
OS-BL-1.4.4 Su
Support Pipe 4d 31-May-19 08:00 05-Jun-19 16:00 05-Jun-19 16:00, OS-BL-1.4.4 Support Pipe
A1330 Pipe Shoes 4d 31-May-19 08:00 05-Jun-19 16:00 Pipe Shoes
A1340 Support Pipe 4d 31-May-19 08:00 05-Jun-19 16:00 Support Pipe

OS-BL-1.5 Utility
Ut Lines 62d 06-Jun-19 08:00 30-Aug-19 16:00 30-Aug-19 16:00, OS-BL-1.5 Utility Lines

OS-BL-1.5.1 Co
Compressed Air Line (CS Gal 5d 06-Jun-19 08:00 12-Jun-19 16:00 12-Jun-19 16:00, OS-BL-1.5.1 Compressed Air Line (CS Galv. Pipe)
A1350 Material Erection 2d 06-Jun-19 08:00 07-Jun-19 16:00 Material Erection
A1360 Welding Joint 2d 06-Jun-19 08:00 07-Jun-19 16:00 Welding Joint
A1370 Painting (Secondary & Finish C 2d 10-Jun-19 08:00 11-Jun-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1380 Test Package 1d 12-Jun-19 08:00 12-Jun-19 16:00 Test Package
OS-BL-1.5.2 In
Instrument Air Line (CS Galv. 5d 13-Jun-19 08:00 19-Jun-19 16:00 19-Jun-19 16:00, OS-BL-1.5.2 Instrument Air Line (CS Galv. Pipe)
A1390 Material Erection 2d 13-Jun-19 08:00 14-Jun-19 16:00 Material Erection
A1400 Welding Joint 2d 13-Jun-19 08:00 14-Jun-19 16:00 Welding Joint
A1410 Painting (Secondary & Finish C 2d 17-Jun-19 08:00 18-Jun-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1420 Test Package 1d 19-Jun-19 08:00 19-Jun-19 16:00 Test Package
OS-BL-1.5.3 Process
Pr Air Line (CS Galv. Pip 9d 20-Jun-19 08:00 02-Jul-19 16:00 02-Jul-19 16:00, OS-BL-1.5.3 Process Air Line (CS Galv. Pipe)
A1430 Material Erection 4d 20-Jun-19 08:00 25-Jun-19 16:00 Material Erection
A1440 Welding Joint 4d 20-Jun-19 08:00 25-Jun-19 16:00 Welding Joint
A1450 Painting (Secondary & Finish C 4d 26-Jun-19 08:00 01-Jul-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1460 Test Package 1d 02-Jul-19 08:00 02-Jul-19 16:00 Test Package
OS-BL-1.5.4 Ni
Nitrogen Line (CS Galv. Pipe) 9d 26-Jun-19 08:00 08-Jul-19 16:00 08-Jul-19 16:00, OS-BL-1.5.4 Nitrogen Line (CS Galv. Pipe)
A1470 Material Erection 4d 26-Jun-19 08:00 02-Jul-19 08:00 Material Erection
A1480 Welding Joint 4d 26-Jun-19 08:00 02-Jul-19 08:00 Welding Joint
A1490 Painting (Secondary & Finish C 4d 02-Jul-19 08:00 05-Jul-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1500 Test Package 1d 08-Jul-19 08:00 08-Jul-19 16:00 Test Package
OS-BL-1.5.5 RO Water Line (CS Galv. Pipe) 9d 02-Jul-19 08:00 12-Jul-19 16:00 12-Jul-19 16:00, OS-BL-1.5.5 RO Water Line (CS Galv. Pipe)
A1510 Material Erection 4d 02-Jul-19 08:00 08-Jul-19 08:00 Material Erection
A1520 Welding Joint 4d 02-Jul-19 08:00 08-Jul-19 08:00 Welding Joint
A1530 Painting (Secondary & Finish C 4d 08-Jul-19 08:00 11-Jul-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1540 Test Package 1d 12-Jul-19 08:00 12-Jul-19 16:00 Test Package
OS-BL-1.5.6 Steam
St Line (CS Pipe) 4d 15-Jul-19 08:00 18-Jul-19 16:00 18-Jul-19 16:00, OS-BL-1.5.6 Steam Line (CS Pipe)
A1550 Material Erection 4d 15-Jul-19 08:00 18-Jul-19 16:00 Material Erection
A1560 Welding Joint 4d 15-Jul-19 08:00 18-Jul-19 16:00 Welding Joint
A1570 Painting (Secondary & Finish C 0d 15-Jul-19 08:00 15-Jul-19 08:00 Painting (Secondary & Finish Coat : 150?)
A1580 Test Package 1d 15-Jul-19 08:00 15-Jul-19 16:00 Test Package
OS-BL-1.5.7 W
WWTP Line (SS & CS Galv. Pip 9d 16-Jul-19 08:00 26-Jul-19 16:00 26-Jul-19 16:00, OS-BL-1.5.7 WWTP Line (SS & CS Galv. Pipe)
A1590 Material Erection 4d 16-Jul-19 08:00 19-Jul-19 16:00 Material Erection
A1600 Welding Joint 4d 16-Jul-19 08:00 19-Jul-19 16:00 Welding Joint
A1610 Painting (Secondary & Finish C 4d 22-Jul-19 08:00 25-Jul-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1620 Test Package 1d 26-Jul-19 08:00 26-Jul-19 16:00 Test Package
OS-BL-1.5.8 Ch
Chilled Water Line (CS Galv. P 3d 29-Jul-19 08:00 31-Jul-19 16:00 31-Jul-19 16:00, OS-BL-1.5.8 Chilled Water Line (CS Galv. Pipe)
A1630 Material Erection 2d 29-Jul-19 08:00 30-Jul-19 16:00 Material Erection
A1640 Welding Joint 2d 29-Jul-19 08:00 30-Jul-19 16:00 Welding Joint
A1650 Test Package 1d 31-Jul-19 08:00 31-Jul-19 16:00 Test Package
OS-BL-1.5.9 Co
Cooling Tower Line (CS Galv. 5d 01-Aug-19 08:00 07-Aug-19 16:00 07-Aug-19 16:00, OS-BL-1.5.9 Cooling Tower Line (CS Galv. Pipe)

Actual Work Critical Remaining Work Summary Page 2 of 4 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


PIPING SYSTEM

Activity ID Activity Name Original Start Finish May 2019 June 2019 July 2019 August 2019 September 2019 ber 2019
Duration
21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
A1660 Material Erection 2d 01-Aug-19 08:00 02-Aug-19 16:00 Material Erection
A1670 Welding Joint 2d 01-Aug-19 08:00 02-Aug-19 16:00 Welding Joint
A1680 Painting (Secondary & Finish C 2d 05-Aug-19 08:00 06-Aug-19 16:00 Painting (Secondary & Finish Coat : 150?)
A1690 Test Package 1d 07-Aug-19 08:00 07-Aug-19 16:00 Test Package
OS-BL-1.5.10 C
Condensate Line (CS Pipe) 3d 08-Aug-19 08:00 12-Aug-19 16:00 12-Aug-19 16:00, OS-BL-1.5.10 Condensate Line (CS Pipe)
A1700 Material Erection 2d 08-Aug-19 08:00 09-Aug-19 16:00 Material Erection
A1710 Welding Joint 2d 08-Aug-19 08:00 09-Aug-19 16:00 Welding Joint
A1720 Test Package 1d 12-Aug-19 08:00 12-Aug-19 16:00 Test Package
OS-BL-1.5.11 H
Hot Water Line (SS Pipe) 3d 13-Aug-19 08:00 15-Aug-19 16:00 15-Aug-19 16:00, OS-BL-1.5.11 Hot Water Line (SS Pipe)
A1730 Material Erection 2d 13-Aug-19 08:00 14-Aug-19 16:00 Material Erection
A1740 Welding Joint 2d 13-Aug-19 08:00 14-Aug-19 16:00 Welding Joint
A1750 Test Package 1d 15-Aug-19 08:00 15-Aug-19 16:00 Test Package
OS-BL-1.5.12 E
Effluent Line (SS Pipe) 3d 16-Aug-19 08:00 20-Aug-19 16:00 20-Aug-19 16:00, OS-BL-1.5.12 Effluent Line (SS Pip
A1760 Material Erection 2d 16-Aug-19 08:00 19-Aug-19 16:00 Material Erection
A1770 Welding Joint 2d 16-Aug-19 08:00 19-Aug-19 16:00 Welding Joint
A1780 Test Package 1d 20-Aug-19 08:00 20-Aug-19 16:00 Test Package
OS-BL-1.5.13 P
Phosporic Acid Line (SS Pip 3d 21-Aug-19 08:00 23-Aug-19 16:00 23-Aug-19 16:00, OS-BL-1.5.13 Phosporic Acid Lin
A1790 Material Erection 2d 21-Aug-19 08:00 22-Aug-19 16:00 Material Erection
A1800 Welding Joint 2d 21-Aug-19 08:00 22-Aug-19 16:00 Welding Joint
A1810 Test Package 1d 23-Aug-19 08:00 23-Aug-19 16:00 Test Package
OS-BL-1.5.14 F
Fuel Oil Line (CS Pipe) 3d 26-Aug-19 08:00 28-Aug-19 16:00 28-Aug-19 16:00, OS-BL-1.5.14 Fuel Oil Lin
A1820 Material Erection 2d 26-Aug-19 08:00 27-Aug-19 16:00 Material Erection
A1830 Welding Joint 2d 26-Aug-19 08:00 27-Aug-19 16:00 Welding Joint
A1840 Test Package 1d 28-Aug-19 08:00 28-Aug-19 16:00 Test Package
OS-BL-1.5.15 V
Valve Erection 2d 29-Aug-19 08:00 30-Aug-19 16:00 30-Aug-19 16:00, OS-BL-1.5.15 Valve Ere
A1900 Butterfly Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Butterfly Valve
A1910 Ball Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Ball Valve
A1920 Gate Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Gate Valve
A1930 Globe Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Globe Valve
A1940 Check Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Check Valve
A1950 Expantion Joint 2d 29-Aug-19 08:00 30-Aug-19 16:00 Expantion Joint
A1960 Basket Strainer 2d 29-Aug-19 08:00 30-Aug-19 16:00 Basket Strainer
A1970 Y- Strainer 2d 29-Aug-19 08:00 30-Aug-19 16:00 Y- Strainer
A1980 Steam Check Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Steam Check Valve
A1990 Steam Strainer 2d 29-Aug-19 08:00 30-Aug-19 16:00 Steam Strainer
A2000 Steam Trap 2d 29-Aug-19 08:00 30-Aug-19 16:00 Steam Trap
A2010 Foot Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Foot Valve
A2020 Floating Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Floating Valve
A2030 Pressure Regulating Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Pressure Regulating Valve
A2040 Pressure Safety Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Pressure Safety Valve
OS-BL-1.5.16 Instrument
I Erection 2d 29-Aug-19 08:00 30-Aug-19 16:00 30-Aug-19 16:00, OS-BL-1.5.16 Instrumen
A1850 Control Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Control Valve
A1860 Actuator Valve 2d 29-Aug-19 08:00 30-Aug-19 16:00 Actuator Valve
A1870 Flow meter 2d 29-Aug-19 08:00 30-Aug-19 16:00 Flow meter
OS-BL-1.5.17 P
Pipe Support 2d 29-Aug-19 08:00 30-Aug-19 16:00 30-Aug-19 16:00, OS-BL-1.5.17 Pipe Sup

Actual Work Critical Remaining Work Summary Page 3 of 4 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation


PIPING SYSTEM

Activity ID Activity Name Original Start Finish May 2019 June 2019 July 2019 August 2019 September 2019 ber 2019
Duration
21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
A1880 Pipe Shoes 2d 29-Aug-19 08:00 30-Aug-19 16:00 Pipe Shoes
A1890 Support Pipe 2d 29-Aug-19 08:00 30-Aug-19 16:00 Support Pipe

OS-BL-1.6 Close
Cl Out 4d 29-Aug-19 08:00 03-Sep-19 16:00 03-Sep-19 16:00, OS-BL-1.6 Close O
A2050 As built Drawing 4d 29-Aug-19 08:00 03-Sep-19 16:00 As built Drawing
A2060 Demob 0d 29-Aug-19 08:00 29-Aug-19 08:00 Demob

Rp13,500,000,000.00 Rp54,000,000,000.00

Rp10,800,000,000.00 Rp43,200,000,000.00

Rp8,100,000,000.00 Rp32,400,000,000.00

Rp5,400,000,000.00 Rp21,600,000,000.00

Rp2,700,000,000.00 Rp10,800,000,000.00
Budgeted Labor Cost
Budgeted Expense Cost
Actual Labor Cost
Actual Expense Cost
Remaining Labor Cost
Remaining Expense Cost
Rp0.00
21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
May 2019 June 2019 July 2019 August 2019 September 2019 ber 2019

Actual Work Critical Remaining Work Summary Page 4 of 4 TASK filter: All Activities

Remaining Work Milestone © Oracle Corporation