3.24.1 General
General Stipulations
The specifications and methods of construction for civil works are given hereinafter.
These must be consulted together with the general requirements for civil works. The
Contractor has to follow these specifications and shall conform thereto. The Contractor
shall submit their own specifications which they propose to use for methods not
Covered by these specifications together with a respective explanation why they are
being used and where they are deviating from the specification.
The Quoted costs given in the lump sum price shall cover any subsidiary or incidental
works that may be found necessary.
NO work will be regarded as complete, until the Contractor has removed from the site all
rubbish and unused materials and has properly dressed and finished all the grounds to the
final approved levels. To the full satisfaction of the Employer.
The Contractor shall be solely responsible in all respects for the suitability and stability of
the buildings and foundations.
The Contractor shall also be the solely responsible for verifying the suitability of his
designed foundations to the effective ground conditions. When the soil has been excavated accordin to the
approved design and the type of ground requires modifications in the design. These modifications shall be
carried out by the Contractor without extra charge and have to be approved by the Employer.
The construction work referred hereto shall be performed in such a manner that the high
standards of quality and function, are achieved. All materials shall be new and of the best quality, suitable
for working under the climatic conditions without any distortion or deterioration.
The Contractor shall set out the work and shall be solely responsible for the accuracy of the
setting out work. He is also responsible for the maintenance of existing and provision of all necessary new
survey marks.
Materials
All material used in the works shall be new and of best quality of their respective kinds.
They shall comply with the requirements of the latest edition of the relevant standards.
Workmanship
All workmanship shall be of the highest standard and shall be performed by competent
personnel skilled in their respective jobs.
Samples
Samples, when approved, shall be regarded as the acceptable standard, any material or
workmanship subsequently not complying with the samples shall be rejected and replaced by the
Contractor. Sample storage boxes shall be provided by the Contractor free of cost.
Tests
Prevention of damage
The Contractor shall take all necessary and reasonable precision during the execution of the
works to prevent damage to existing land channels, roads, buildings, Services on
and/or adjacent to the site.
Safety precautions
Cleanliness of site
The Contractor shall at all times maintain the site in a clean condition, and all rubbish, debris,
etc. shall be collected and shall be disposed as requested.
Contractor’s area
Sanitary facilities
The Contractor shall be responsible for providing suitable and adequate sanitary
facilities for his site staff, at a position agreed with the Employer/ Employer’s
Representative.
Health
The Contractor shall take for his staff all necessary health measures. as may be
required by the works and by the statutory provisions of the Local Health authorities.