ENGINEERS INDIA LIMITED

OPaL PETROCHEMICAL COMPLEX


DAHEJ
DG (DIESEL GENERATOR) SET INSPECTION CHECKLIST

EPCC NO…………………………………………………..….… CONTRACTOR’S NAME …………………


Inspected / checked (Site Elec. Engineer / Safety Officer): DATE………………………………………..

Name by …………………………………………………………

DG identification code: …………….…………………………

Serial Action to be taken / by


SUBJECTS Observation Remarks
No whom / by what time

Is the DG is freely accessible from all


O.K / NOT O.K
1. sides?

The overall construction / condition


Yes / No
2. of the DG set is acceptable?

Whether the noise around the DG set


Yes / No
3. is acceptable?

Whether the DG is fitted with


Yes / No
4. silencer?

Whether the DG operator is


Yes/ No
5. qualified?

Whether the DG operator has been


Yes / No
6. provided with ear-muffs?

Whether the DG is covered or


Yes / No
7. provided with a shed?

Whether the DG exhaust is diverted


Yes / No
8. outside the shed?

Whether the cables of DG set are


Yes / No
9. concealed / covered?

Whether surrounding areas of the


DG set are free from flammable Yes / No
10.
materials?

Whether insulation is provided on


Yes / No
11. the battery terminals?

Whether entry is restricted in to the


Yes / No
12. DG shed?

Whether the DG shed is free from


storage of personal materials (e.g. Yes / No
13.
tiffin box, umbrella, dress items etc.)

Whether the rotating parts of DG are


safely guarded (radiator fan blades, Yes / No
14.
couplings, shafts etc.)?

Whether there is any leakage of


Yes / No
15. lubricants, fuel, oils etc?
Whether the continuity & tightness
of earth conductor checked and Yes / No
16.
found all right?

What is the gauge of “earth”


Yes / No
17. conductor used at the DG set?

Whether “earth” resistance is


Yes / No
18. measured? What is that value?

Whether the “start” & “stop”


arrangement of DG set is promptly Yes / No
19.
operative?

Whether fire-extinguishers / fire-


buckets are available in operative Yes / No
20.
condition?

Whether illumination inside DG shed


Yes / No
21. is satisfactory?

Whether the lamps are protected


Yes / No
22. from inadvertent direct contact?

Whether the DG set stack height as


per statutory norms
Yes/ No
23.
(H=0.2 X Sqrt (KVA) + h

Checking frequency = Monthly