Main Contractor: M/s. Larsen & Toubro & Shriram EPC JV, Tanzania (LTSEPC JV)
Task at Hand: This method statement outlines the procedure and methodology for earthworks
operations including excavation, placement and compaction of materials.
Supervision of Task:
• Banksman
• Site Supervisor
• General operatives
Equipment to be used
• 20 T – 70 T 360°-Excavator
• Tripper
• Pedestrian roller
Methodology
• Surveying of the site before excavation and set properly all lines and establish levels for various
works such as earthwork in excavation for leveling, basement, foundations, cable trenches,
pipelines. Etc.
• Established permanent bench mark at such point which will not be affected by subsequent
work. Such survey shall be carried out by taking accurate cross sections of the perpendicular to
the established reference/grid lines at 5 m intervals or nearer as determined by the Engineer –
in – charge based on ground profile.
• The area to be excavated/filled shall be cleared of fences, trees, plants, slumps, bush,
vegetations, rubbish slush, etc., and other objectionable matter. If any roots or stumps of trees
are found during excavation, they shall also be removed. The material so removed shall be burnt
or disposed off as directed by the Engineer.
• Excavation shall be carried out in accordance to line and levels shown on Design Drawings.
Excavation shall be carried out by excavator with material being hauled to fill area by dump
trucks.
• All formation levels shall be recorded by site engineer. All works will be executed within the
permanent fencing boundary.
Hard Rock
This shall include rock which cannot be easily excavated by pick-axes, hammer, crow bars and
wedges but has to be either heated where blasting is prohibited or has to be blasted. They shall be
staked separately for measurement as directed by the Engineer – in – charge.
JANDU PLUMBERS LTD.
P.O.BOX 409, ARUSHA, METHOD STATEMENT
TANZANIA.
• All personnel entering the site shall have received a site safety induction and have
attended a job toolbox talk.
• Before any excavations shall commence a permit to excavate shall be issued by the
site engineer and all persons involved in the task shall be fully briefed .
• All setting out works required including level profiles and batter rails shall be set out
by the site engineer prior to works commencing.
JANDU PLUMBERS LTD.
P.O.BOX 409, ARUSHA, METHOD STATEMENT
TANZANIA.
Compaction & Protection Formation
Emergency procedures
• First aid kits in site office and in engineers and foremans vehicle
Monitoring procedures
• A written report of inspection prepared by a competent person at least once every seven days, and
also after any event affecting strength or stability of the excavation, and after any accidental fall of
materials
• Reviews of the method statement and the risk assessment carried out regularly