Professional Documents
Culture Documents
1/6
Key words
Smart Protection, busbar, selectivity, short-circuit.
ABSTRACT
This paper presents the "Fast Busbar Protection", adopted by AES Sul in their medium voltage substation buses,
which is the existence of a communication link between the feeder’s and main transformer overcurrent protection.
Its operation is based on the premise that the main protection will only operate if the busbar protection pickup and
any feeder protection pickup during the same time. If the overcurrent protection from at least one feeder pickup,
the Logic Selectivity will not operates because it means that is an external fault. It is an efficient, low cost and
selective system, with a 0.15 s time operation. This period corresponds to only 20% the traditional overcurrent
protection time. This percentage ratio applies directly to harm minimization, as the heat production is directly
proportional to the lack of time.
1/6
1. Introduction
The classical busbar protection
selectivity presents limitations about the
clearing time for a short circuit, because
fastest time would limit the application of
downstream protection. This happen because
the selectivity between the overcurrent device
is achieved by the relation: time operation
versus fault current amplitude. Thus, to have a
busbar protection selective in the substation it
is necessary to slow down the busbar
overcurrent protection by considering around
300 ms delay to the up and downstream Figure 1 - Circuit Breaker Explosion. Zoologico
devices [1]. Substation. AES Sul. 2003. System without
In this context, the purpose of this article fast busbar protection.
is to present the “Fast Busbar Protection” also
called “Logic Selectivity” that uses digital Zoologico substation didn’t have the
overcurrent relays. This protection is installed logic selectivity implemented. So the short
in all AES Sul substations to provide a faster circuit clearing time was enough to explode the
protection system, decreasing the damages circuit breaker and cause damage to the
caused by busbar short circuits. medium voltage busbar.
2/6
than in the first. That means the most severe
situation will take longer time to be extinct.
3/6
The cost for implementing the logic selectivity would be necessary additional
differential protection in the AES Sul is overcurrent and timer in the main protection.
calculated in US$ 90,000.00/substation. As The fast busbar protection operation
AES Sul has 60 own substations, total cost to zone is determined by the current transformers
move from traditional scheme to differential (CT’s) that are connected in the busbar and
protection would represent an investment of the CT’s installed in the feeder protection.
US$ 5,400,000.00. When the power transformer has
By using the resources provided for the bushing CT’s for protection purposes, these
existing digital overcurrent relays and current elements can be used in the fast busbar
transformers, AES Sul develop a project to protection instead of the external current
turn the traditional busbar protection faster, transformers. This will provide a longer
without compromising the selectivity with up protection zone since the transformer’s
and downstream protections with the lowest bushing until the feeder’s circuit breakers.
cost possible and with speed close the
differential protection.
The Logic Selectivity consists in a
communication between the feeders and the
main transformer overcurrent protection. It
premise of working is that this logic will just
work if the definite time relay installed in the
transformer protection operates and any of the
feeder’s protection pickup during the period of
150 ms. If at least one of the feeder’s
overcurrent protection pickup during this time, Figure 7 - Zone of operation – Fast Busbar
the logic selectivity will be blocked and will not Protection
operate because the fault is external from the
busbar. The fast time operation from the logic
The figure below shows the logic selectivity reduces the heating damages
diagram with the fast busbar protection. caused by the current flowing and corresponds
just to 20% of the operation time achieved by
the traditional busbar protections. It also
improves the personal safety and extends the
lifetime of substation protection equipments.
4/6
As it can be seen, this busbar protection As can be seen in the picture 9, the
doesn’t involve material costs in a substation circuit breaker was completely destroyed by
where the overcurrent protection devices the energy released. The heating was enough
enable the use of logic circuits. It involves just to burn the circuit breaker module and make it
the service installation cost that is around US$ throw its parts inside the substation.
3,000.00/substation.
The complexity of logic selectivity is just
about its implementation in the existing
overcurrent relays, what is not a difficult job.
The protection engineering area must establish
the pickup value – in AES Sul, usually the half
phase-to-phase fault current – and the team
must just implement it in the site.
The efficiency of this system is
demonstrated below, in the next topic, where
are presented two similar busbar faults. One
where it was already implemented the logic
selectivity and the second where it wasn’t
installed yet.
Figure 9 - 13.8 kV module damaged by the
busbar short circuit. Alegrete 1 Substation.
3. Real Situation With and Without
the Logic Selectivity in the AES Sul This substation has 16 MVA power
supplied for two transformers. The electrical
Hereafter will be showed two real diagram below shows in red the point where
situations involving busbar faults in the AES the short circuit happened.
Sul system. The first case happened in a
substation where it wasn’t implemented the
logic selectivity, while the second was
recorded in a system where this technique was
installed.
5/6
electrical stress and even damages in the
involved system. However, as can be checked
in the photographic records, the logic
selectivity brought a quick and efficient
protection. The animal was not burned and as
it was not recorded any damage in the system,
that could be immediately put in operation
again after the AES Sul’s team inspection.
Table 2
Outage Information – Uruguaiana 1 Substation
Outage Location: TR2-Uruguaiana 1-Substation
Date: March 29, 2004
Time: 07:36 pm
Figure 12 - Short circuit location in Uruguaiana
Cause: Earth fault caused by animal
Substation. The fault happened in the red point
Voltage: 23 kV
located in the 23 kV busbar.
Currente: 7 kA (calculated)
Protection Operation Time: 0,2 s
4. Conclusion
Associated equipment costs: US$ 0
This paper presented a busbar
In the figure 11 it is possible to see the protection technique called Logic Selectivity or
switches where the mouse did a short circuit Fast Busbar Protection. This protection has
and the animal lying next to it. been successfully implemented in the AES Sul
for more than 10 years. It were showed an
event where a system without this protection
ended up in a US$ 30000 loss and more than
six month breaker unavailability.
In a second case, in a substation where
it was already implemented the Logic
Selectivity, there was no damage in
equipments and the system could be
immediately reconnected after team
inspection.
This technique can easily be
implemented in any substation that has digital
overcurrent relays installed, with just service
implementation cost that represents just 3% of
the cost from the more sophisticated busbar
Figure 11 - 23 kV module after a busbar short protection techniques. AES Sul is a successful
circuit. Uruguaiana 1 Substation. example of using this scheme that is a current
standard in the company.
Next picture shows Uruguaiana 1
electrical diagram with red point detailing 5. References
where was located the fault. In green is
represented the incoming 69 kV transmission [1] ANSI/IEEE Std. 242-1986, “Protection and
line and brown the 23 kV busbar and outgoing Coordination of Industrial and Commercial
feeders. This substation has a 25 MVA power Power Systems”. Nova York. 1999.
transformer. [2] C. Privé, “Protection of Electrical Networks”.
This fast time protection is activated for ISTE LTD. Newport Beach, USA. 2006.
both ground and phase overcurrent elements, [3] UNIVERSIDADE SEL, “Proteção de
instantaneous and definite time curves. If Sistemas de Potência para Engenheiros”.
someone of these elements pick up during the Schweitzer Engineering Laboratories,
event, the logic selectivity will not work, Comercial Ltda. Campinas, Brazil, 2009.
because it means that the short circuit is out of [4] T. Hazel, J. Tastet, B. Lusson,
the busbar. In Uruguaiana 1 case it didn’t “Implementation Back-Up Protection Using
happened because it was an internal fault and Microprocessor Based Multifunction Relays”,
the logic selectivity was required. 2001 Petroleum and Chemical Industry
Technical Conference, 53-62.
6/6