Proyek :

Lokasi : Untuk Mengcopy Tipe


Klik Disini Baris Ke-
Jenis Bangunan Kolom :
Perhitungan : Kolom
Note : Prosentase Tul. Lentur (Kolom) = 1% s/d 6% (terhadap luas penampang beton)
Prosentas Ratio
Beton Besi Bkst.
No. Lantai/ No.Gbr Axis Tipe Kolom e Besi
m3 kg m2 m2/m2 kg/m3

SISTEM PENULANGAN
(1) OVERLAP TIAP SATU LANTAI
(2) OVERLAP TIAP DUA LANTAI
POSISI KOLOM
(1) LANTAI PALING BAWAH
(2) LANTAI TENGAH
(3) LANTAI PALING ATAS
-------------------------------- ------------- --------------------- ---------------------
SISTIM OVER LAP : : 1.00
Overlap besi dari lantai ke lantai : 40.00
Overlap besi kolom di dalam PC : 20.00 x dia
Overlap stek besi kolom dr PC (bag. atas) : 40.00 x dia
Overlap stek besi kolom dr PC (bag. bawah) : 40.00 x dia
Tebal Selimut : 25.00 mm
Faktor hook : 6.00 x dia
Faktor bend : 2.00 x dia
Selimut PC bwh. : 100.00 mm
Lantai 1
(Drawg. S1 - 5 )

2 Besi Kolom Menerus da C-8 K1-1 45.58 12116.30 336.86 1.99% 265.83

STOP
Sub Total 45.58 12,116.30 336.86
Ratio 265.83 7.39

Note : Prosentase Tul. Lentur (Kolom) = 1% s/d 6% (terhadap luas penampang beton)
47.00

Ratio Kolom Tebal Tebal Kolom Dia Jmlh.


Bkst. Tg. Jmlh. Pos. Pelat Pile Cap Lbr. Pjg. Utm Tul.Utm.
m2/m3 m nos 1/2/3 m m m m mm nos

/CRUMUS~~

7.39 6.60 22 1 0.00 0.40 0.43 0.73 19 22


0.00 0 1 0.00 0.00
0.00 0 1 0.00 0.00
Sengkang Sengkang Tambahan Pjg. Tulangan Utama Pjg. Tulangan Utama
Ovrlp.
Dia Jrk. T Jrk. L Dia Jrk. T Pjg. T Jrk. L Pjg. L Pos (1) Pos (2) Pos (3) Tul.Utm. 13 16 19 22
mm m m mm m m m m m m m m m kg kg kg kg

10 0.10 0.10 10 0.10 1.90 0.10 1.90 7.32 0.00 0.00 0.76 8.08 0.00 0.00 8701.41 0.00
ama Sengkang Sengkang Tambahan
25 32 16 13 12 10 8 6 16 13 12 10 8 6
kg kg kg kg kg kg kg kg kg kg kg kg kg kg

0.00 0.00 0.00 0.00 0.00 2126.41 0.00 0.00 0.00 0.00 0.00 1288.49 0.00 0.00
BANGUNAN COAL STORAGE
DINDING BETON
ARAH VERTIKAL
A. AS 11/A-G
UKURAN 250 x 2000 DAN 200 x 3000
P = 36.000 m
L1 = 0.250 m
T1 = 2.000 m
L2 = 0.200 m
T2 = 3.000 m

1. V Beton = 39.6 m3
2. Bekisting = 362.2 m2

3. Reforcement Bar 250 x 2000


a. Pembesian TEGAK

Besi D22- 150


W = 2.98386
Panjang = 35.950 m
n = 239.6666667 + 1 = 240.667 ~ 241

L2
11
Rmin Rmin Rmin = 2d
= 0.044 m
L1 = 2.181
L2 = 0.112 m
L3 = 2.181 m
Ltmin Lt min = 6d
L1
L3 0.132 m
Rmin

Ltmin
`
Rmin

Panjang Total Besi = 1184.274 n=1


1184.274 m
Berat Total besi arah X = 3533.71 n=1
3533.71 Kg
a. ARAH MEMANJANG
UKURAN 250 x 2000 DAN 200 x 3000
P = 36.000 m
L1 = 0.250 m
T1 = 2.000 m
L2 = 0.200 m
T2 = 3.000 m

Besi D16 - 200


W = 1.57824
Panjang = 1.975 m
n = 9.875 + 1 = 10.875 ~ 11

Rmin = 2d
= 0.032 m
L1 = 35.95
Lt min = 6d
0.096 m
Overlap = 40D
= 0.88

Panjang Total Besi = 38.846 n = 22


= 854.612 m
Berat Total besi arah X = 1348.78 Kg

4 Reforcement Bar 200 x 3000


a. Pembesian TEGAK

Besi D19- 300


W = 2.225565
Panjang = 35.950 m
n = 119.8333333 + 1 = 120.83 ~ 121

L2
11
Rmin Rmin Rmin = 2d
= 0.044 m
L1 = 3.181
L2 = 0.062 m
L3 = 3.181 m
Ltmin Lt min = 6d
L1
L1 Ltmin
L3 0.132 m
Rmin

Ltmin
`
Rmin

Panjang Total Besi = 830.544 n=1


830.544 m
Berat Total besi arah X = 1848.43 n=1
1848.43 Kg

a. ARAH MEMANJANG
UKURAN 200 x 3000
P = 36.000 m
L2 = 0.200 m
T2 = 3.000 m

Besi D16 - 200


W = 1.57824
Panjang = 2.975 m
n = 14.875 + 1 = 15.875 ~ 16

Rmin = 2d
= 0.032 m
L1 = 35.95
Lt min = 6d
0.096 m
Overlap = 40D
= 0.88

Panjang Total Besi = 38.846 n = 32


= 1243.072 m
Berat Total besi arah X = 1961.87 Kg

B. AS 11/A-G
UKURAN 250 x 2000 DAN 200 x 3000
P = 6.000 m
L1 = 0.250 m
T1 = 2.000 m
L2 = 0.200 m
T2 = 3.000 m
JUMLAH = 20 SEGMEN

1. V Beton = 6.6 m3 TOTAL = 132 m3


2. Bekisting = 62.2 m2 TOTAL = 1244 m2

3. Reforcement Bar 250 x 2000


a. Pembesian TEGAK

Besi D22- 150


W = 2.98386
Panjang = 5.520 m
n = 36.8 + 1 = 37.8 ~ 39

L2
11
Rmin Rmin Rmin = 2d
= 0.044 m
L1 = 2.181
L2 = 0.112 m
L3 = 2.181 m
Ltmin Lt min = 6d
L1
L3 0.132 m
Rmin

Ltmin
`
Rmin

Panjang Total Besi = 191.646


TOTAL = 3832.92 m
Berat Total besi arah X = 571.84
TOTAL = 11,436.90 Kg

a. ARAH MEMANJANG
UKURAN 250 x 2000 DAN 200 x 3000
P = 6.000 m
L1 = 0.250 m
T1 = 2.000 m
L2 = 0.200 m
T2 = 3.000 m
Besi D16 - 200
W = 1.57824
Panjang = 1.975 m
n = 9.875 + 1 = 10.875 ~ 11

Rmin = 2d
= 0.032 m
L1 = 35.95
Lt min = 6d
0.096 m
Overlap = 40D
= 0.88

Panjang Total Besi = 38.846 n = 22


= 17,092.24 m
Berat Total besi arah X = 26,975.66 Kg

4 Reforcement Bar 200 x 3000


a. Pembesian TEGAK

Besi D19- 300


W = 2.225565
Panjang = 5.520 m
n = 18.4 + 1 = 19.4 ~ 20

L2
11
Rmin Rmin Rmin = 2d
= 0.044 m
L1 = 3.181
L2 = 0.062 m
L3 = 3.181 m
Ltmin Lt min = 6d
L1
L3 0.132 m
Rmin

Ltmin
`
Rmin
Rmin

Panjang Total Besi = 137.28 n=1


TOTAL = 2745.6 m
Berat Total besi arah X = 305.53 n=1
TOTAL = 6110.51 Kg

a. ARAH MEMANJANG
UKURAN 200 x 3000
P = 6.000 m
L2 = 0.200 m
T2 = 3.000 m

Besi D16 - 200


W = 1.57824
Panjang = 2.975 m
n = 14.875 + 1 = 15.875 ~ 16

Rmin = 2d
= 0.032 m
L1 = 35.95
Lt min = 6d
0.096 m
Overlap = 40D
= 0.88

Panjang Total Besi = 38.846 n = 32


= 24,861.44 m
Berat Total besi arah X = 39,237.32 Kg
TOTAL VOLUME

NO URAIAN VOLUME SATUAN


1 BEKISTING 1,606.20 m2
2 BETON 171.60 m3
3 BESI
D22 - 150 14,970.60 Kg
D16-200 66,826.06 Kg
D19-300 7,958.94 Kg