MASTER TIME SCHEDULE

BUDUK PROJECT

Sep-19 Oct-19 Nov-19 Dec-19


NO DESCRIPTION VOL UNIT UNIT PRICE TOTAL PERCENTAGE
I II III IV I II III IV I II III IV I II III IV
I DESIGN PROCESS

II SIGN OFF

III TENDERING PROCESS


I Brief overview
II Send the drawings, specification details, and BoQ to contractors
III Offer submission
IV Clarification meeting
V Agreement

IV CONSTRUCTION PROCESS
I Preliminaries
II Foundation works
III Structure works
1. Fabrication
2. Material on site
3. Material installment
IV Finishing works
A. Material process by suppliers
1. Fabrication
2. Material on site
B. Installment process by contractor
1. Wall
2. Floor
3. Roof
V MEP works
A. Material process by suppliers
1. Material preparation
2. Material on site
B. Installment process by contractor
VI Site Cleaning

V FURNISHING

VI LANDSCAPING

VII SOFT LAUNCH

VIII LAUNCH

IX PAYMENT PROCESS

X MARKETING