SCHEDULE SERVICE ELECTRO MOTOR AIR COM

JUNI 2014
NO ITEM
30/5 31/5 1 2 3
1 Stop Plant
2 Service Electro Motor Joy Air Compressor :
- Prepare Tool, Take Data Aligment, Electrical Test, Dismantling
- Next Dismantling Check Bearing Clearance, Cleaning Part
- Cleaning Stator & Rotor
- Radoxide, Final Test Prepared Assembling
- Assembling, Alignment, Load Test, Take Bolt Cople
- Commissioning

3 Penggantian Filler Pack C. Tower


4 Penggantian Pasir Silica pd Sand Filter
5 Perbaikan Valve Adsorber Unit
6 Tambah Perlite Cold Box
7 Cleaning GAN Compressor
8 Install PLC MS Adsorber
9 Check Valve GAN & Waste (Tdk Bisa Auto)
10 Chek Tempreatur Control Heater Adsorber C2H2
11 Start Up Plant (Blow Off/Deriming/C. Down)
O MOTOR AIR COMP ASP 1
JUNI 2014
KTERANGAN PIC
4 5 6 7
Produksi ASP1 Sugiono/Irwanto
Team ABB Jakarta Soehendro BL

Produksi ASP1 Irwanto


QC Ronald
Maintenance Herry S
Maintenance + Produksi ASP1 Khusairi
Produksi ASP1 Hotler N
Team Pusat Hermawan
Team Pusat Hermawan
Team Pusat Hermawan
Produksi ASP1 Sugiono/Irwanto