Roads on Peat
Ron Munro, ROADEX IV Project Manager
ROADEX final seminar
Rovaniemi, 26 April 2012
ROADEX Network Implementing Accessibility
Construction methods
Maintenance of roads on peat
Examples of good practice Road improvement
Conclusions
Road widening
ROADEX Network Implementing Accessibility
Roads on Peat:
Peat across the Northern Periphery
Palsa mires
Fens
Raised bogs
Blanket Bogs
Contents:
- Peat
- Behaviour of peat
- Environmental considerations
- Geotechnical risk management
- Engineering considerations
- Investigations & surveys
- Construction of roads on peat
- Maintenance of roads on peat
- Monitoring
- Records
ROADEX Network Implementing Accessibility
Environmental considerations
• Usually a protected area/ecology/habitat
• Sensitive to changes in hydrology
• Disturbance
• Pollution
• Construction
• Drainage
BBC Scotland
ROADEX Network Implementing Accessibility
2.0 m
0.3m
18kN/m³
18kN/m³
10kN/m³
18kN/m³
10kN/m³
Effects of new drains on a floating road
P Carlsten SGI
ROADEX Network Implementing Accessibility
εp primary strain
εs secondary strain
“tertiary strain” εt
ROADEX Network Implementing Accessibility
-0.2
-0.4
Settlement for a 2m thick
-0.4 embankment after 30 years
Settlement
-0.8
Preload settlement using a 2m Settlement for 2m embankment
-1.0 embankment with a 1.5m surcharge, with 1.5m surcharge, then removed
down to required settlement
-1.2
-1.4
Loading peat:
Stage construction
Stage construction embankment
Fill
3rd stage
2nd stage
Strain
ROADEX Network Implementing Accessibility
Preload
Log time
preloaded
ROADEX Network Implementing Accessibility
Minimum:
• Desk study Steel rod probing for depth
– Water content
Roads on peat
THICKNESS OF PEAT, M*
Estimation of primary settlement
(Swedish Transport Administration method)
WATER CONTENT (%)
10 8 6 5 4 3 2
1400
1200 * THE DIAGRAM SHOWS THE SOLUTION FOR FREE DRAINAGE AT THE TOP AND BOTTOM
LAYERS OF THE PEAT. IF THE LAYER IS IMPERMEABLE THE PEAT THICKNESS SHOULD BE
1000
MULTIPLIED BY 2
800
600
400 10 8 6 5 4 3 2 First layer settlement >70%
10
30
50
99%
10 30 50
APPLIED LOAD (kPa) 70% 80% 85% 90% 95%
0 50 100 150 200 250
TIME (days)
ROADEX Network Implementing Accessibility
Roads on peat
THICKNESS OF PEAT, M*
Estimation of primary settlement
(Swedish Transport Administration method)
WATER CONTENT (%)
10 8 6 5 4 3 2
1400
1200 * THE DIAGRAM SHOWS THE SOLUTION FOR FREE DRAINAGE AT THE TOP AND BOTTOM
LAYERS OF THE PEAT. IF THE LAYER IS IMPERMEABLE THE PEAT THICKNESS SHOULD BE
1000
MULTIPLIED BY 2
800
600
400 10 8 6 5 4 3 2 Subsequent layers and preloading
10
30
50
99%
10 30 50
APPLIED LOAD (kPa) 70% 80% 85% 90% 95%
0 50 100 150 200 250
TIME (days)
ROADEX Network Implementing Accessibility
Risk Management
• Experienced designers
• Experienced contractors
• Good planning
• Awareness of the hazards and impacts
• Sound mitigation measures
• Careful construction techniques
• Contingency planning
• Monitoring of the work on site
Geotechnical risk management
ROADEX Network Implementing Accessibility
If risk cannot be
Very Likely >10 weeks added to planned Very
5 >€1M 5 17 to 25 Unacceptable reduced project should
>75% completion date high
not proceed
Work must not start
Likely >4 weeks added to planned €100K to
4 High 4 13 to 16 Unacceptable until risk has been
50-75% completion date €1M
reduced
Probable >4 weeks<1wk added to planned €10k to Mediu Reduce risk. (Mitigate
3 3 9 to 12 Significant
25-50% completion date €100k m or transfer.)
1 Unexpected Ground conditions encountered on Construction delayed. Design Monitor works in progress. Use
ground site differ from those indicated in review required with possible experienced staff on site. Ensure that
conditions the project ground investigation. 3 3 9 changes in design. Project cost site staff are aware of the results of the 3 1 3
and timescale increased ground investigation and the basis of
the design of the permanent Works
2 Flooding Prolonged rain, Rise in groundwater Permanent works damaged. Ensure that cut off drains are installed
levels within bog. Local Work stops. Increased costs for and serviceable. Monitor weather
3 4 12 2 2 4
watercourses break banks. repair of the Works. Project forecasts and take action in light of
delayed forecasted poor weather
3 Site Clearance of vegetation from within Damage to fibrous surface of Use low ground pressure construction
clearance the site limits ahead of the peatbog. Removal of surface plant. Ensure that site staff are aware
4 3 12 2 1 2
permanent Works rootmat. Design of Works that existing root mat has to be
affected retained as reinforcement
4 Placing of fill Rupture, puncture or tearing of the Damage to permanent Works. Protect geotextile with layer of fine
on geotextile permanent geotextile Fill material laid directly on to material. Ensure that site staff are
4 4 16 2 1 2
bog surface. Failure of aware of need to protect geotextile
subgrade during installation
ROADEX Network Implementing Accessibility
Contingency planning:
Barrage location
Zone 2
Zone 3
Public Road Barrage location
Zone 1
Zone 4
Public Road
ROADEX Network Implementing Accessibility
ROAD CONSTRUCTION
Methods of construction
H
Surcharge
Firm Layer
Geotextile
Embankment Fill
Peat
Firm Layer
ROAD CONSTRUCTION
Methods of Construction – Peat left in place
Peat left in
place
Stage Slope Reduction
Construction
Lightweight Fill
Offloading
ROADEX Network Implementing Accessibility
Budget v. Timing:
Roads on Peat
Widening an existing road
Roads on Peat
Widening an existing road
Roads on Peat
Widening an existing road
Geotextile placed on
exposed surface
ROADEX Network Implementing Accessibility
Roads on Peat
Widening an existing road
Widened area
preloaded in stages
Roads on Peat
Widening an existing road
Roads on Peat
Widening an existing road
• Collect data
• Understand the ground conditions
• Respect the established hydrology
• “Do no more harm”
• Think about geotechnical risk management
• Monitor the works during and afterwards
• Keep records & share knowledge
ROADEX Network Implementing Accessibility
Thank you