You are on page 1of 19

square cut on IPE

400 side with 150mm


overlength (typ.2 nos)
square cut on UB305
side with 150mm
overlength
square cut on W12
side with 150mm
overlength
Note:
1. No over-length required
to all Primary Frames
unless noted otherwise. Or
when an as-built drawings
or PDMS show
discrepancies against this
drawings.
2. Dimensional Check to
be done prior cutting of
existing member on joints
at "Blue Circle".

square cut end with


150mm overlength
square cut on HE700A
side with 150mm over-
length (typ.5 nos)

square cut on IPE


square cut on G8 square cut on IPE
500 side with
side with 150mm 500 side with
150mm over-length
over-length (typ.7 150mm over-length
nos)

TO PROVIDE
ADDITIONAL FRAME
TO CATER FOR THE
PRE-TREATMENT
BASE PLATE AT
THIS LOCATION

square cut on G8
side with 150mm
over-length
Note:
All new deck plates
weld to existing deck
plates shall have
150mm over-length/
width
TO PROVIDE
ADDITIONAL FRAME
TO CATER FOR THE
PRE-TREATMENT
BASE PLATE AT
THIS LOCATION

Note:
All new stiffener
plates weld to
existing deck frames
shall have no over-
length/width
Note:
All new deck plates
joint to existing deck
plates shall have
150mm over-length/
width