JIZAN REFINERY TERMINAL PROJECT -INSTRUMENT RFI - EPC 14

CONTRACTOR COMPANY
PLANT
SL NO. RFI NO. QMIS NO. Description SATIP SAIC LOCATION DRAWING NO. Inspection Date TIME (INSPECTION (INSPECTION HENC QC Inspector SAPID Inspector SAPMT Remark
CODE
LEVEL) LEVEL)

VISUAL INSPECTION OF INSTALLATION OF SPEED


SENSOR & TRAVELLING SWITCH WITH TAG# T04-SS- SATIP-J-200-01 Sulfur Shek Ahamed
1 HENC-INST- 5071, T04-SS-5081, T04-XS-5022A, T04-XS-5022B, T04- SAIC-J-6205 T36 VA-305738 5-Oct-19 H W Sant Hashmi
XS-5022C, T04-XS-5022D, at Sulfur Stacker SHIPLOADER (4.07) Stacker Shadhik
AS PER ATTACHED CHECKLIST AND DRAWINGS.

VISUAL INSPECTION OF INSTALLATION OF SPEED


SENSOR &Missalignment SWITCH WITH TAG# T04-SS-
5071, T04-SS-5081, T04-XS-5071A-XS-5071B,T04-XS- SATIP-J-200-01 Sulfur Shek Ahamed
2 HENC-INST- 5072A,T04-XS-5072B,T04-XS-5081A,T04-XS-5081B,T04- SAIC-J-6205 T36 VA-305738 5-Oct-19 H W Sant Hashmi
(4.07) Stacker Shadhik
XS-5082A,T04-XS-5082B,T04-XS-5101A,T04-XS-5101B,,
at Sulfur Stacker SHIPLOADER as per Highlighted
interconnecton diagram.