ESTIMATEC COST FOR PROCESSING OF THREE (3) BLDG. PERMITS

DRAWING PLAN (30 SHEETS) P 30,000.00

PRIVATE ENGINEER

CIVIL 10,000.00

ELECTRICAL 10,000.00

PLUMBER 6 ,000.00

MECHANICAL 6,000.00

ELECTRONIC 8,000.00

DOLE 10,000.00

STRUCTURAL ANALYSIS (civil engineer) (P20.00/sqm) ,


BILL OF MATERIALS and SPECIFICATIONS

BLDG. 1 ( 900 sqm) 18,000.00

BLDG. 2 (1800 sqm) 36,000.00

SKECTH PLAN (2 title) 1,400.00

ZONING FEE (bill of materials)

BLDG. 1 3,900.00 (w/ OR)

BLDG. 2 4,900.00 (w/ OR)

BLDG. 3 3,100.00 (w/ OR)

PROCESSING FEE 25,000.00

Total ------------ P172,300.00

PESOS : ONE HUNDRED SEVENTY-TWO THOUSAND THREE HUNDRED only

n.b. above estimate cost does not include gov’t fees of the ff:

Office of the City Engineer (OBO) --- application and penalty

ESTIMATE ---- gov’t fees plus 100% …… 10,000 – existing structure ……. 8,000.00 – occupancy penalty gov’t fees
plus 100%
ZONING ------------------------- penalty ( P500.00/day since start of construction…for nego)