Operational Load Per Phase Last Overhauling Date 1/1/2016 (Mention the record avaialable with PMO) DG Serial No. xxxxxxxx (Provide Picture)
DG Status Prime Stand by Last OH Running Hours 10000 Engine Serial No. xxxxxxxx (Provide Picture/Must Match with Inspur database/Update )
Engine Manual
Engine Block Damage Yes No ✘ Yes ✘ No
Rotation/Cranking
DG information (Make, Rating, Serial No.) must be correctly registered in Inspur DG
database All Fuel
Nozzles/Injectors/ ✘ Yes No
Cranking Working
Sr Test Test Method Standard Value Complete overhaul Checked value Remarks
To be checked from Oil pressure gage. In case of faulty
1 Oil Pressure Visual inspection 3.5 bar Less than or equal to 2.5 bar
gauge, maintenance team must have a spare gauge to test.
Picture of Oil gauge while genset running.
2 Compression Pressure Compression tester Greater than or equal 27 bar Less than or equal to 22 bar Need to ensure that Genset head gasket is not leaked.
Video for compression test
3 Exhaust Color Visual inspection No color Blue/ Black color Excessive Blue/Black Smoke Video for exhaust smoke
Greater than or Equal 10000 Hr (1st OH). Historical Data from NOC DG Running and Running Hour
4 DG Running Historical Data 10000 hr Historical Record(Based on Fueling/Maintenance Records)
Greater than or Equal to 2000 Hr (Subsequent OH) meter
Audio Inspection/Sound No Abnormal Sound Abnormal sound must be from Genset block for connecting
5 Noise/Abnormal Sound Abnormal Sound (>85dB)
Tester (<=60dB) rod or crank.
10 - 15 mm/s (As per
6 Vibration Test Vibration Meter Check the vibration on the engine block
Manufacturer Manual) Provide the video of the test
7 Oil Indication at exhaust pipe Visual inspection No indication Oil indication at the manifold (air-exhaust) Engine blow need to be checked from exhaust pipe. Picture of oil blow on a white paper
ensuring no oil leakage from cylinder head, from and main oil PM Data of Total oil consumed (Including top up) for last 6
8 Oil Consumption Historical Data Rated as per DG KVA More than ( 30 % to 50 %) of the rated Value@250 Hours month along with total DG Running record for the same
seals, rocker assembly seals etc.
period.
Dummy load(Resistive)/on Genset will be tested on site load and ratio will be determined Video for site load (To be tested with Clamp meter at DG
9 Load Test 110 % of the rated Less than or equal to 70 % of the rated load output on all three phases after load balancing) and
site load accordingly.
genset operation.
10 Fuel Consumption Test Common Method in the field As per Manufacturer Manual Manufacturer Manual
Provide the value of fuel consumed per hour
11 Oil Drain Test Visual inspection No Metal Particles found Visible metal particles Oil to be drained and physically checked
Final Requirement
Major Overhauling ✘ Top Overhauling Weak DG
NOTE:
** This Form is based on small DGs less than 30KVA but manufacturing manual will provide support to the standard values
** For DG Overhauling, previous overhauling record need to be checked and OH will be awarded if DG RH are more than 10,000 running hours at least for first overhauling. For subsequent overhauling's, minimum of 2000 running hours must be completed.
**Incase of DG Heat up, Complete water circulation need to be checked including head gasket, Thermostat valve, Water body, radiator etc. Overhauling will not be awarded in this case
**Final decision will be based on available budgeted quota, DG condition, availability impact and Site priority, which shall be set by region after conducting overhauling test