Professional Documents
Culture Documents
Gas in Procedure Prasad
Gas in Procedure Prasad
3.1 UMUM 7
3.1 GENERAL 7
3.2 PUNCH LIST 7
3.2 PUNCH LIST 7
3.3 COMMISSIONING 7
3.3 COMMISSIONING 7
3.4 SISTEM PURGING 8
3.4 PURGING 8
4.0 GAS IN 11
4.0 GAS IN 11
LAMPIRAN
APPENDIX
PENDAHULUAN
1.0 PRE-COMMISSIONING
1.1 UMUM 2.0 PRE-COMMISSIONING
Persiapan untuk pelaksanaan Pre-commissioning 2.1. GENERAL
terdiri dari beberapa tahap pelaksanaan yang harus Preparation for Pre-Commissioning execution
dilakukan: consist of several important steps which must be
1.1.1 Memeriksa seluruh pemasangan pipa salur, followed :
lengkap dengan kondisi wrapping, proteksi 2.1.1 Check all pipeline installation complete with
katodik dan penimbunan. Rambu-rambu pipa wrapping, cathodic protection and good backfill.
salur dan proteksi katodik test point, harus sesuai Pipeline marker and test point for cathodic
dengan spesifikasi dokumen teknik. protection position shall comply with specification
1.1.2 Memeriksa sistem koneksi dalam perpipaan of engineering document.
termasuk fitting, support pipa dan pondasi harus 2.1.2 Check all of piping connection system including
sesuai dengan spesifikasi dokumen teknik. fitting, pipe support and support foundation. Then
1.1.3 Memeriksa arah aliran yang ditunjukkan dengan all shall comply with specification of engineering
arah panah pada pipa bagian luar. document.
1.1.4 Memeriksa seluruh pekerjaan civil dan struktur, 2.1.3 Check gas direction flow, which shown by the
dan harus sesuai dengan dokumen teknik. arrow on the outside of pipe.
1.1.5 Memeriksa letak alat instrumen dan sistem 2.1.4 Check all civil and structural work, and all shall
koneksinya harus sesuai dengan spesifikasi comply with engineering document.
standard dokumen teknik. 2.1.5 Check all instrument equipment placement and
its connection, and shall comply with standard
1.1.6 Membuat daftar peralatan dan hasil aktivitas specification engineering document.
perbaikan, punch list. 2.1.6 Prepare Punch List
1.1.7 Memeriksa kembali hasil seluruh pengujian untuk
pipa salur, perpipaan, instrumen, civil/struktur 2.1.7 Check all of the test result for pipeline, piping,
dan katodik. Hasil uji sudah harus di setujui. instrument, civil/structure and cathodic, and all of
1.1.8 Memeriksa sertifikasi pipa salur yang telah the test result should be approved.
disetujui oleh MIGAS. 2.1.8 Check pipeline certificate from MIGAS.
1.1.9 Seluruh katalog peralatan yang terpasang telah
tersedia. 2.1.9 All equipment installed catalogue should be ready.
Tahapan-tahapan tersebut di atas harus dipenuhi All steps above must be done first before continue to the
terlebih dahulu, sebelum menginjak ke tahap next step, Commissioning.
berikutnya, Commissioning.
4. Memastikan kondisi penimbunan jaringan pipa 4. Ensure the pipe backfill condition is good and
telah baik dan sesuai dengan dokumen teknik. shall comply with engineering document.
5. Memastikan sepanjang pipa salur telah di
5. Ensure that pipeline must be wrapped using
wrapping dan telah di uji dengan holiday test,
wrapping tape which already tested by holiday
dan hasilnya telah disetujui. test and must be approved.
6. Memastikan pemasangan Insulation Joint telah 6. Ensure that the insulation joint has been
siap dan benar, sesuai dengan dokumen installed correctly, ready, and shall comply with
teknik. engineering document
7. Memastikan bahwa dalam pipa salur telah 7. Ensure that inner pipeline has been cleaned,
dibersihkan, gauging telah dilakukan dan gauging has already implemented and approved
before hydrotest.
disetujui sebelum hidrotest dilaksanakan.
8. Ensure that hydrotest result approved by
8. Memastikan hasil hidrotest disetujui MIGAS. MIGAS.
2.2.4 Civil dan Structure 2.2.4 Civil and Structure Inspection/Check List
1. Periksa seluruh kondisi pondasi equipment 1. Check condition of all equipment and piping
maupun perpipaan dan dengan hasil test baik. foundation and the results are good.
2. Memastikan seluruh elevasi pondasi harus 2. Ensure elevation of foundation shall comply
sesuai dengan dokumen teknik. with engineering document
3. Memastikan kondisi pondasi pagar yang baru 3. Ensure fence and fence foundation shall comply
dan pagar sesuai dokumen teknik yang with engineering document.
ditentukan.
7. Melakukan purging ke seluruh system 7. Purging all of the system using nitrogen.
menggunakan gas nitrogen.
Commissioning Team will perform Mechanical
Hasil Tim Commissioning adalah Mechanical Completion, which is present of all activity approval and
Completion, yaitu pernyataan bahwa seluruh hasil equipment installation approval declaration (approved /
pemeriksaan terhadap pekerjaan/ peralatan dapat approved with comment).
diterima penuh atau diterima bersyarat.
1. Pastikan Valve VF1, VF2, VF3, VV1, VV2, V3A, V3B, 1. Ensure Valve VF1, VF2, VF3, VV1, VV2,
V4A, V4B, V5A, V5B, V6A, V6B, V7, V8, V9A, V9B, V3A, V3B, V4A, V4B, V5A, V5B, V6A, V6B,
V10A, V10B, V11A, V11B, V12A, V12B dalam kadaan V7, V8, V9A, V9B, V10A, V10B, V11A,
tertutup semua. V11B, V12A, V12B are all closed
2. Buka Perlahan lahan Valve V1 pada area Tie-in PT 2. Open slowly Valve V1 at PT Pertamina Gas
Pertamina Gas (PIER Station). Tie-in area (PIER Station).
3. Buka Valve V2 perlahan-lahan pada inlet MRS di Titik 3. Open Valve V2 Slowly at inlet MRS at Tie-
Tie-in. in area.
4. Buka Valve V3A kemudian valve V3B 4. Open Valve V3A then Valve V3B
5. Setting Slum Shut Regulator SR-1A dan SR-1B 5. Setting Slum Shut Regulator SR-1A dan SR-
6. Lakukan dan Pastikan Reliev Valve, Regulator Monitor 1B
dan Regulator Aktif pada stream A dan B telah 6. Make sure relief valve, regultor (active &
dilakukan penyetingan. monitor) already set
7. Buka Valve V4A 7. Open Valve V4A
8. Buka Valve V5A dan V5B 8. Open Valve V5A then V5B
9. Buka Venting Valve 9. Open Venting Valve
10. Tim HSE monitoring gas yang di-venting 10. HSE Team observes vented gas using gas
menggunakan gas detector detector
Dengan dibukanya valve nomor 12 , maka proses Gas In After the valve number 12 opened, Gas In
telah selesai dan Station siap operasi. process is finish and the station is ready for
operation .
Catatan :
Pengaturan arah aliran gas disesuaikan dengan kebutuhan Note :
operasional PT. PERTAGAS NIAGA Adjustment of gas flow direction is depend on
PT PERTAGAS NIAGA operational need
V1 VV1
VF2
V2 V7
VF1
V8
VF3
VV2
V6A V6B
V5B
V5A
V4A V4B
V3A V3B
V12A V12B
V11A V11B
V10B
V10A
V9A V9B