You are on page 1of 14

Prosedure Commissioning & Gas In

System Metering Gas Turbine

METERING GAS TURBIN G.40 DI TITIK TIE-IN DAN


G.65 DI PT PRASAD SEEDS INDONESIA
KAWASAN INDUSTRI REMBANG PASURUAN
JAWA TIMUR

0 01/10/19 COMMISIONING & GAS IN PROCEDURE


Prepared Checked Approved
Revision Date Description
By By by

COMMISSIONING AND GAS IN PROCEDURE


DAFTAR ISI TABLE OF CONTENT

BAB DESKRIPSI HAL SEC. DESCRIPTION PAGE

1.0 PENDAHULUAN 4 1.0 INTRODUCTION 4

2.0 PRE-COMMISSIONING 4 2.0 PRE-COMMISSIONING 4

2.1 UMUM 4 2.1 GENERAL 4


2.2 INSPEKSI 4 2.2 INSPECTION 7

3.0 COMMISSIONING 7 3.0 COMMISSIONING 7

3.1 UMUM 7
3.1 GENERAL 7
3.2 PUNCH LIST 7
3.2 PUNCH LIST 7
3.3 COMMISSIONING 7
3.3 COMMISSIONING 7
3.4 SISTEM PURGING 8
3.4 PURGING 8

4.0 GAS IN 11
4.0 GAS IN 11

LAMPIRAN
APPENDIX

Process Flow Diagram


Process Flow Diagram
Skematik
Schematic
P&ID
P&ID
General Arrangement
General Arrangement

PENDAHULUAN

COMMISSIONING AND GAS IN PROCEDURE


Tujuan pembuatan Prosedur Commissioning dan 1.0 INTRODUCTION
Gas In ini adalah untuk menentukan prosedur This document provides guideline for Comissioning
pelaksanaan Commissioning dan penyaluran Gas and Gas In procedure from Gas Pipeline PT
(Gas In) dari jaringan pipa salur PT Pertamina Gas Pertamina Gas (PTG) to system meter gas PT
(PTG) ke Sistem Meter Gas PT Unilever Unilever Oleochemical Indonesia (UOI) in area
Oleochemical Indonesia (UOI) yang berlokasi di Kawasan Ekonomi Khusus (KEK), North Sumatera .
Kawasan Ekonomi Khusus (KEK), Sumatera-Utara.

1.0 PRE-COMMISSIONING
1.1 UMUM 2.0 PRE-COMMISSIONING
Persiapan untuk pelaksanaan Pre-commissioning 2.1. GENERAL
terdiri dari beberapa tahap pelaksanaan yang harus Preparation for Pre-Commissioning execution
dilakukan: consist of several important steps which must be
1.1.1 Memeriksa seluruh pemasangan pipa salur, followed :
lengkap dengan kondisi wrapping, proteksi 2.1.1 Check all pipeline installation complete with
katodik dan penimbunan. Rambu-rambu pipa wrapping, cathodic protection and good backfill.
salur dan proteksi katodik test point, harus sesuai Pipeline marker and test point for cathodic
dengan spesifikasi dokumen teknik. protection position shall comply with specification
1.1.2 Memeriksa sistem koneksi dalam perpipaan of engineering document.
termasuk fitting, support pipa dan pondasi harus 2.1.2 Check all of piping connection system including
sesuai dengan spesifikasi dokumen teknik. fitting, pipe support and support foundation. Then
1.1.3 Memeriksa arah aliran yang ditunjukkan dengan all shall comply with specification of engineering
arah panah pada pipa bagian luar. document.
1.1.4 Memeriksa seluruh pekerjaan civil dan struktur, 2.1.3 Check gas direction flow, which shown by the
dan harus sesuai dengan dokumen teknik. arrow on the outside of pipe.
1.1.5 Memeriksa letak alat instrumen dan sistem 2.1.4 Check all civil and structural work, and all shall
koneksinya harus sesuai dengan spesifikasi comply with engineering document.
standard dokumen teknik. 2.1.5 Check all instrument equipment placement and
its connection, and shall comply with standard
1.1.6 Membuat daftar peralatan dan hasil aktivitas specification engineering document.
perbaikan, punch list. 2.1.6 Prepare Punch List
1.1.7 Memeriksa kembali hasil seluruh pengujian untuk
pipa salur, perpipaan, instrumen, civil/struktur 2.1.7 Check all of the test result for pipeline, piping,
dan katodik. Hasil uji sudah harus di setujui. instrument, civil/structure and cathodic, and all of
1.1.8 Memeriksa sertifikasi pipa salur yang telah the test result should be approved.
disetujui oleh MIGAS. 2.1.8 Check pipeline certificate from MIGAS.
1.1.9 Seluruh katalog peralatan yang terpasang telah
tersedia. 2.1.9 All equipment installed catalogue should be ready.

Tahapan-tahapan tersebut di atas harus dipenuhi All steps above must be done first before continue to the
terlebih dahulu, sebelum menginjak ke tahap next step, Commissioning.
berikutnya, Commissioning.

1.2 INSPEKSI 2.2 INPECTION/CHECK LIST


Inspeksi harus dilakukan Tim Inspeksi Pre- Check list must be perform by Pre-Commissioning
Commissioning untuk memastikan kelengkapan Team to ensure that equipment, pipeline, fitting,
peralatan, fitting, perpipaan, instrumen, piping, instrument, civil-structure and cathodic
civil/struktur, dan proteksi katodik. protection are installed in the right place.

2.2.1 Inspeksi Pipa Salur. 2.2.1 Pipeline Inspection/Check List.


1. Memastikan NDT telah dilaksanakan di seluruh 1. Ensure that NDT should be done on every

COMMISSIONING AND GAS IN PROCEDURE


jalur pipa salur dengan hasil baik dan disetujui. pipeline system with the good results and
approved.
2. Memastikan rambu-rambu pipa salur telah
2. Ensure pipeline sign and information board
terpasang dengan baik dan benar, papan
installed good and correctly.
informasi pipa salur juga terpasang.
3. Memastikan kedalaman pipa salur ditanam 3. Ensure pipeline buried in the correct depth, and
dengan benar sesuai dengan dokumen teknik. shall comply with engineering document.

4. Memastikan kondisi penimbunan jaringan pipa 4. Ensure the pipe backfill condition is good and
telah baik dan sesuai dengan dokumen teknik. shall comply with engineering document.
5. Memastikan sepanjang pipa salur telah di
5. Ensure that pipeline must be wrapped using
wrapping dan telah di uji dengan holiday test,
wrapping tape which already tested by holiday
dan hasilnya telah disetujui. test and must be approved.
6. Memastikan pemasangan Insulation Joint telah 6. Ensure that the insulation joint has been
siap dan benar, sesuai dengan dokumen installed correctly, ready, and shall comply with
teknik. engineering document
7. Memastikan bahwa dalam pipa salur telah 7. Ensure that inner pipeline has been cleaned,
dibersihkan, gauging telah dilakukan dan gauging has already implemented and approved
before hydrotest.
disetujui sebelum hidrotest dilaksanakan.
8. Ensure that hydrotest result approved by
8. Memastikan hasil hidrotest disetujui MIGAS. MIGAS.

2.2.2 Inspeksi Perpipaan. 2.2.2 Piping Inspection/Check List


1. Memastikan seluruh sistem perpipaan sesuai 1. Ensure piping system shall comply with
dengan engineering document. engineering document.
2. Periksa sambungan antara pipa dengan flange 2. Check connection between pipe and flange or
atau pipa dengan pipa atau pipa dengan elbow, pipe and pipe or pipe and elbow or flange and
atau flange dengan flange. Memastikan bahwa flange. Ensure welding procedure shall comply
prosedur pengelasan telah sesuai dengan with engineering document
dokumen teknik. 3. Ensure piping has been flushing.
3. Memastikan perpipaan telah di flushing. 4. Ensure valve can be opened and closed
4. Memastikan bahwa valve dapat membuka dan correctly and easily, and the placement shall
menutup dengan baik dan mudah dimana comply with engineering document.
peletakan valve telah sesuai dokumen teknik. 5. Ensure elevation and lay-out of piping system
5. Memastikan elevasi dan letak dari sistem shall comply with engineering document.
perpipaan harus sesuai dokumen teknik. 6. Ensure pipe support and other accessories have
6. Memastikan bahwa support pipa dan been installed and shall comply with
accessories yang lain, telah terpasang sesuai engineering document.
dokumen teknik.
7. Pastikan bahwa anchor bolt telah terpasang 7. Ensure anchor bolts have been installed well.
dengan baik.
8. Memastikan servis skid metering telah 8. Ensure service platform have been installed
terpasang dengan benar. correctly.
9. Memastikan bahwa sistem perpipaan telah di 9. Ensure hydrostatic test has been done on the
Hidrotest dan hasilnya telah disetujui oleh pipeline system and the results have been
MIGAS. approved by MIGAS

2.2.3 Inspeksi Instrumen 2.2.3 Instrument Inspection/Check List


1. Memastikan seluruh peralatan instrumen telah 1. Ensure all instruments have been calibrated and
dikalibrasi sesuai dengan dokumen teknik. shall comply with engineering document.
2. Memastikan seluruh peralatan instrumen telah 2. Ensure all instruments have been installed

COMMISSIONING AND GAS IN PROCEDURE


siap terpasang dengan baik. correctly.
3. Periksa kondisi panel instrumen apakah sudah 3. Check condition of panel instrument as
sesuai dengan spesifikasai yang dibutuhkan following with standard requirement based on
oleh standard yang ditentukan oleh dokumen engineering document and local regulation.
teknik dan regulasi terkait. 4. Check that the tube connection is in good
4. Periksa sambungan tubing sudah benar dan condition and shall comply with engineering
baik dan sesuai dengan dokumen teknik. document.
5. Memastikan seluruh peralatan instrumen telah 5. Ensure that fuctional test has been done on all
dilakukan function test dan berhasil baik sesuai instruments with good result based on
dokumen teknik. engineering document.
6. Memastikan Pressure Regulator telah 6. Ensure Pressure Regulator have been installed
terpasang dan telah di function tes. and function tested.
7. Memastikan katalog dari tiap peralatan 7. Ensure catalogue of all instruments are
instrumen telah lengkap. complete.

2.2.4 Civil dan Structure 2.2.4 Civil and Structure Inspection/Check List
1. Periksa seluruh kondisi pondasi equipment 1. Check condition of all equipment and piping
maupun perpipaan dan dengan hasil test baik. foundation and the results are good.
2. Memastikan seluruh elevasi pondasi harus 2. Ensure elevation of foundation shall comply
sesuai dengan dokumen teknik. with engineering document
3. Memastikan kondisi pondasi pagar yang baru 3. Ensure fence and fence foundation shall comply
dan pagar sesuai dokumen teknik yang with engineering document.
ditentukan.

2.0 COMMISSIONING 3.0 COMMISSIONING


Commissioning dapat dilaksanakan setelah pre- Commissioning can start after pre-commissioning
commissioning selesai dilaksanakan. steps completely finished.

2.1 UMUM 3.1 GENERAL


Team Leader Commissioning bertanggung jawab Commissioning Team Leader is in charge on
terhadap koordinasi dan arahan langkah-langkah coordination and conduction during Commissioning.
yang akan dilakukan selama Commissioning. Purging will be perform during commissioning.
Purging akan dilakukan saat commissioning. Before purging start, punch list review should be
Sebelum purging dimulai, sebaiknya dilakukan discussed.
pembahasan punch list.

2.2 PUNCH LIST 3.2 PUNCH LIST


Tim pre-commissioning akan mengeluarkan laporan Pre-Commissioning team will produce Check List.
Check List. Di dalam check list terdapat pernyatan Check List report contains statement approved / not
yang menyatakan diterima atau diterima dengan approved / approved with comment by Pre-
persyaratan atau tidak sama sekali terima oleh tim commissioning team.
pre-commissioning. Check list produces Punch List. The Punch List will
Berdasarkan Check List akan dihasilkan Punch List. present the recommendation of which equipment
Punch List ini akan mengeluarkan rekomendasi or activity that should be repaired/reinstall or even
peralatan atau hasil pekerjaan mana saja yang perlu replaced.
diperbaiki atau dipasang ulang atau diganti.

2.3 COMMISSIONING 3.3 COMMISSIONING


Tim commissioning akan melakukan pekerjaan Commissioning team will work based on Punch List.
berdasarkan Punch List. The inspection steps should be done is as follows:
Pemeriksaan yang akan dilakukan adalah sebagai

COMMISSIONING AND GAS IN PROCEDURE


berikut :
1. Memeriksa hasil pekerjaan yang telah 1. Check all of the improved job .
diperbaiki.
2. Memeriksa peralatan yang telah diperbaiki. 2. Check all of the repaired equipment.
3. Memeriksa kembali pekerjaan ulang yang telah
dilakukan. 3. Re-check all of the improved job.
4. Memeriksa kembali peralatan yang telah
diganti. 4. Check all equipment replacement.
5. Membahas/mendiskusikan ulang terhadap
peralatan/pekerjaan yang tidak dapat di 5. Re-check all of the equipment/job that can’t be
perbaiki/diganti. repaired/improved, then discuss it.
6. Melakukan function test dan running test
peralatan tanpa menunggu purging dan gas in 6. Perform function test and running test without
(Static Test). waiting on purging and gas in steps.

7. Melakukan purging ke seluruh system 7. Purging all of the system using nitrogen.
menggunakan gas nitrogen.
Commissioning Team will perform Mechanical
Hasil Tim Commissioning adalah Mechanical Completion, which is present of all activity approval and
Completion, yaitu pernyataan bahwa seluruh hasil equipment installation approval declaration (approved /
pemeriksaan terhadap pekerjaan/ peralatan dapat approved with comment).
diterima penuh atau diterima bersyarat.

3.0 GAS IN 4.0 GAS IN

PIPA SALUR PT PGN PIPELINE PT PGN


1. Pastikan future valve 8”-300#(Line pipa menuju Inlet 1. Ensure future valve 8”-300# (Line Pipe to
Meter gas ) DIBUKA perlahan-lahan sampai tekanan Inlet gas meter) is OPEN until operating
operasi yang diinginkan. pressure desired.

STATION METER STATION METER

1. Pastikan Valve VF1, VF2, VF3, VV1, VV2, V3A, V3B, 1. Ensure Valve VF1, VF2, VF3, VV1, VV2,
V4A, V4B, V5A, V5B, V6A, V6B, V7, V8, V9A, V9B, V3A, V3B, V4A, V4B, V5A, V5B, V6A, V6B,
V10A, V10B, V11A, V11B, V12A, V12B dalam kadaan V7, V8, V9A, V9B, V10A, V10B, V11A,
tertutup semua. V11B, V12A, V12B are all closed
2. Buka Perlahan lahan Valve V1 pada area Tie-in PT 2. Open slowly Valve V1 at PT Pertamina Gas
Pertamina Gas (PIER Station). Tie-in area (PIER Station).
3. Buka Valve V2 perlahan-lahan pada inlet MRS di Titik 3. Open Valve V2 Slowly at inlet MRS at Tie-
Tie-in. in area.
4. Buka Valve V3A kemudian valve V3B 4. Open Valve V3A then Valve V3B
5. Setting Slum Shut Regulator SR-1A dan SR-1B 5. Setting Slum Shut Regulator SR-1A dan SR-
6. Lakukan dan Pastikan Reliev Valve, Regulator Monitor 1B
dan Regulator Aktif pada stream A dan B telah 6. Make sure relief valve, regultor (active &
dilakukan penyetingan. monitor) already set
7. Buka Valve V4A 7. Open Valve V4A
8. Buka Valve V5A dan V5B 8. Open Valve V5A then V5B
9. Buka Venting Valve 9. Open Venting Valve
10. Tim HSE monitoring gas yang di-venting 10. HSE Team observes vented gas using gas
menggunakan gas detector detector

COMMISSIONING AND GAS IN PROCEDURE


11. Setelah kandungan nitrogen & oksigen tidak 11. After nitrogen & oksigen undetected,
terdeteksi, venting ditutup venting closed
12. Dilakukan pengamatan leak tes 15-30 menit 12. Leak test conducted for 15-30 min
13. Jika tidak terdeteksi leak, valve nomor 6 A/B bisa 13. If leak undetected, valve Number 8 A/B
dibuka. can be opened
14. Buka Valve V7 14. Open Valve V7
15. Buka Venting Valve VV2 15. Open Venting Valve VV2
16. Tim HSE monitoring gas yang di-venting 16. HSE Team observes vented gas using gas
menggunakan gas detector detector
17. Setelah kandungan nitrogen & oksigen tidak 17. After nitrogen & oksigen undetected,
terdeteksi, venting ditutup venting closed
18. Buka Valve V8 18. Open Valve V8
19. Buka Valve V9A dan V9B 19. Open Valve V9A then V9B
20. Setting Slum Shut Regulator SR-1A dan SR-1B 20. Setting Slum Shut Regulator SR-1A dan SR-
21. Lakukan dan Pastikan Reliev Valve, Regulator Monitor 1B
dan Regulator Aktif pada stream A dan B telah 21. Make sure relief valve, regultor (active &
dilakukan penyetingan. monitor) already set
22. Buka Valve V10A dan V10B 22. Open Valve V10A then V10B
23. Buka Valve V11A dan V11B 23. Open Valve V11A then V11B
24. Buka Venting Valve 24. Open Venting Valve
25. Tim HSE monitoring gas yang diventing menggunakan 25. HSE Team observes vented gas using gas
gas detector detector
26. Setelah kandungan nitrogen & oksigen tidak 26. After nitrogen & oksigen undetected,
terdeteksi, venting ditutup venting closed
27. Dilakukan pengamatan leak tes 15-30 menit 27. Leak test conducted for 15-30 min
28. Jika tidak terdeteksi leak, valve nomor 12 A/B bisa 28. If leak undetected, valve Number 12 A/B
dibuka. can be opened

Dengan dibukanya valve nomor 12 , maka proses Gas In After the valve number 12 opened, Gas In
telah selesai dan Station siap operasi. process is finish and the station is ready for
operation .

Catatan :
Pengaturan arah aliran gas disesuaikan dengan kebutuhan Note :
operasional PT. PERTAGAS NIAGA Adjustment of gas flow direction is depend on
PT PERTAGAS NIAGA operational need

COMMISSIONING AND GAS IN PROCEDURE


DRAWING
ATTACHMENT

COMMISSIONING AND GAS IN PROCEDURE


LIST OF DRAWING

1. Process Flow Diagram


2. Skematik
3. P&ID

Process Flow Diagram

COMMISSIONING AND GAS IN PROCEDURE


COMMISSIONING AND GAS IN PROCEDURE
Skematik

V1 VV1

VF2
V2 V7
VF1

V8

VF3
VV2

COMMISSIONING AND GAS IN PROCEDURE


P&ID MRS TITIK TIE-IN

V6A V6B

V5B
V5A

V4A V4B

V3A V3B

COMMISSIONING AND GAS IN PROCEDURE


P&ID MRS PRASAD

V12A V12B

V11A V11B

V10B
V10A

V9A V9B

COMMISSIONING AND GAS IN PROCEDURE


COMMISSIONING AND GAS IN PROCEDURE

You might also like