DAILY SURVEILLANCE REPORT

Project Berth-N5 Conveyor System Report No. DSR-2019-0009


Client KPCL, Nellore. Date Of Inspection 14-03-2019
Item Inspected Gallery (Trestle 10 ϵ 10 A) Accessibility Good
Area / Location MCG-1 (Berth N5 FAB-YARD) Specification QAP/ITP-SFP-19-007 Rev.00
Drawing No: Contractor URS Engineering Contractors
Scope Of Inspection Structural Steel fabrication, Erection & Painting

Site Observations:

Comments / Work Progress:


1. 65x65x6 and 50x50x6 angle cleats welding on ISMC-150 gusset plates to ISMB-300 Beam
welding under progress. (Pic-1).
Unsatisfactory Findings:
1. Non-calibrated welding Equipment's are using for On-site production welds. This is
violation against Clause:26.1 of QAP-KPCL-MEC-009 Rev.01 (See Pic-2).

Any Non Conformance Report Issued: Yes (NCR/2019/001).

Attachments: Nil.