Test Project LKS I
Test Project LKS I
Test Project
Lomba Kompetensi Siswa
E l e c t r i c a l I n s t a l l a t i o n & I n d u s t r i a l
C o n t r o l
Nama ..............................................
Bidang ..............................................
o 6 hours maximum
o Competitors use these instructions to design the installation using materials from their own.
o If a programmable device is included in the installation, the competitor must bring the
device with them.
o It is up to the competitor to choose which systems he prefers to use.
o The program it self is not part of the marking; only requested function will be marked as per
Instructions circulated.
o Competitors must design a circuit that will meet the project specifications using materials
and equipment from their homelands.
o Competitors must carry all equipment necessary to build the project.
o Competitors who choose to use a programmable device, it must bring your own
(programmable device) or a laptop with the appropriate software.
o All equipment for this module must be in condition "like new".
o Pre-programming, pre-cable, pre-bent, pre-assembly, pre-cut (a certain length), etc. not
allowed.
o 6 hours maximum.
o Material provided by the committee.
o Specific components in the list of materials must be brought and prepared themselves by
competitors.
Test specifications:
o Insulation resistance – The minimum resistance between any current carrying conductors
and any other conductors or earth may not be less than 1 MΩ, tested at a voltage of 500 V
DC with an insulation resistance tester.
o Earth continuity resistance – The maximum resistance between the main incoming earth
terminal and any point on the installation required to be earthed may not be more than 0.5 Ω.
o Polarity phase pin socket outlet located on the left or clockwise from the grounding pin.
Instructions for competitors
o Test project module B competitors must work in accordance with drawings and technical
requirements
o Competitors must perform checking the materials and components. They can request a
replacement 10 minutes before the start of the competition if there is anything wrong.
o All technical terms and descriptions used in the test project must be in accordance with
SNI/PUIL 2000 standards and terms, if applicable.
o All dimensions must be from specific reference lines (datum lines).
o Cable and conduit measurements are to the centre of the cable/conduit.
o Duct and equipment measurements are to the centre or edge of the duct/equipment.
o Bend for PVC conduit, standard radius cannot be less than six times the external diameter of
the conduit.
Bend radius for standard cable cannot be less than three times the cable diameter.
o Dimensional tolerance ± 2 mm for the dimensions of length 0 to 500 mm and ± 5 mm for the
dimensions of length over 500 mm in length.
o During the competition, competitors must read the drawing itself. Not allowed to talk to each
other.
o Prohibited connect the power source to the project without the approval of experts.
o When the work is completed, competitors must clean up the environment prior to
commissioning.
Gloves-leather
Gloves-rubber
Welding Mask
Safety Shoes
Dust Mask
Respirator
Protection
Protective
Hard Hat
Clothing
Hearing
VIP Y Y Y
Service
Y Y Y
Technicians
Jury Y Y Y
Competitors Y Y Y Y Y
Legend:
Y = Yes required
R = Recommended
Evaluation and scoring
A Safety Score 10
B Commissioning Score 20
C Function Score 25
D Measurements Score 5
E Installation Equipment Score 10
F Installation of Wire-ways Score 20
G Wiring Termination Score 10
Total Score 100
For 1 Competitor
(Yellow)
200
34 Bold Screw ¾ inch & 1 Inch
pieces
You have the task to undertake an electrical installation on a property in a remote area of your country.
This property has house and so a gate is required at the main entrance. The only problem with a gate is
that every time the owners want to enter or leave the property they need to get out of the car to open and
close the gate.
They have requested you to design an installation so that once a motion detector detects motion a
solenoid opens the solenoid operated gate (this may be represented by a light L1). As soon as the
solenoid loses power the gate automatically closes. The owners have also requested to include a
driveway light (L2) and a light in the garage (L3).
[In Bahasa]
Anda harus membuat projek instalasi listrik di suatu tempat di daerah Anda. Di sana adalah rumah yang
terdapat garasi dan pintu gerbang pada pintu masuknya. Masalahnya, apabila pemilik rumah ingin keluar
atau masuk ke rumahnya, Dia harus keluar dari mobil untuk membuka maupun menutup pintu.
Dia memintamu untuk mendesain instalasi yang apabila terdapat pergerakan maka selenoid akan aktif
dan pintu gerbang akan membuka (ini dapat direpresentasikan oleh L1). Seketika selenoid kehilangan
daya, pintu gerbang menutup. Pemilik rumah juga meminta untuk membuatkan penerangan jalan (L2)
dan lampu di dalam garasi (L3).
Operation
• Once motion has been detected the gate (L1), and lights L2 and L3 will come on simultaneously.
• After 10 sec the gate (L1) will close.
• Driveway light L2 will remain on for another 10sec. This will give the driver time to get to the house.
• The light (L3) is to be switched off manually
• The sub-switchboard is to be installed in the garage, the owner also require a socket outlet to be
installed in the garage for the use of portable plug-in appliances in the garage.
The Installation is to be carried out using as a minimum all the equipment listed below:
• 2 m of PVC conduit (including 2 – 90 degree manually formed bends)
• 1 m of flexible conduit.
• 1 m of Cable Duct (have 1 – 90 degree angle )
• 4 m of NYM Cable
• 1 Distribution Board / Panel box completed with safety protection devices
• 1 Switched socket outlet
Module B
Project specifications on the drawings (3 pages)
• Ganti Kabel Tray dengan kabel duct
• Ganti Pipa metal dengan kabel NYM
• Commercial Wiring – buat program dengan menggunakan Smart Relay
• Industrial Control – Buat Programnya dengan menggunakan PLC
• Untuk ketentuan terminasi dapat diabaikan