SUB-STATION -86 (CT)

S.no. GROUND FLOOR Item Description Uom No No Length Width Thickness Qty Total Qty

1 HEAVY DUTY FLOORING


LOADING/UNLOADING PLATFORM East Side Sq.m 1 1 27.300 3.500 95.550
LOADING/UNLOADING PLATFORM West Side Sq.m 1 1 12.300 3.500 43.050
A C PLANT ROOM Sq.m 1 1 12.300 12.000 147.600
2 CEMENT CONCRETE FLOORING 286.200
CABLE CELLAR Sq.m 1 1 66.550 15.300 1018.215
GIS AREA Sq.m 1 1 12.000 11.700 140.400
MAINTENANCE ROOM North Side Sq.m 1 1 6.000 5.700 34.200
STORE ROOM North Side Sq.m 1 1 6.000 5.700 34.200
3 VITRIFIED TILE 1227.015
LOBBY North Side Sq.m 1 1 3.000 3.000 9.000
Sq.m 1 1 6.000 1.500 9.000
Skirting 125mm Ht Sq.m 1 1 18.000

FRIST FLOOR Item Description Uom No No Length Width Thickness Qty Total Qty
1 HEAVY DUTY FLOORING
`AHU ROOM Sq.m 1 1 12.000 12.000 144.000
LOADING/UNLOADING PLATFORM East Side Sq.m 1 1 17.300 3.700 64.010
LOADING/UNLOADING PLATFORM West Side Sq.m 1 1 5.300 3.700 19.610
SWITCHGEAR HALL Sq.m 1 1 66.550 15.300 1018.215
GIS PANELS AREA Sq.m 1 1 12.000 11.700 140.400
Deduction Area Sq.m -1 1 5.500 6.000 -33.000
2 VITRIFIED TILE 1353.235
AIR LOCK LOBBY @ East Sq.m 1 1 10.000 3.700 37.000
OPERATOR ROOM Sq.m 1 1 5.500 6.000 33.000
AIR LOCK LOBBY @ west Sq.m 1 1 10.000 3.700 37.000
3 EPOXY PAINT 107.000
BATTERY ROOM on Floor Sq.m 1 1 12.000 5.800 69.600
On Walls Sq.m 1 1 12.000 5.800 69.600
Sq.m 1 2 12.000 2.500 60.000
Sq.m 1 2 5.800 2.500 29.000
228.200
4 FALSE CELING
SWITCHGEAR HALL Sq.m 1 1 66.550 15.300 1018.215
1018.215
SECOND FLOOR Item Description Uom No No Length Width Thickness Qty Total Qty
1 HEAVY DUTY FLOORING
LOADING/UNLOADING PLATFORM East Side Sq.m 1 1 12.000 3.500 42.000
AHU ROOM Sq.m 1 1 12.000 12.000 144.000
186.000

2 VITRIFIED TILE
AIR LOCK LOBBY East Side Sq.m 1 1 7.800 3.500 27.300
Stair landing Sq.m 1 1 7.800 3.500 27.300
ELECTRICAL ROOM Sq.m 1 1 10.200 5.700 58.140
LOBBY inside -1 Sq.m 1 1 30.000 4.800 144.000
AIR LOCK LOBBY West Side Sq.m 1 1 7.800 3.500 27.300
Stair landing Sq.m 1 1 7.800 3.500 27.300
TECH ROOM Sq.m 1 1 12.000 12.000 144.000
455.340
3 FALSE FLOORING
UPS ROOM Sq.m 1 1 10.700 12.000 128.400
ENGINEERING ROOM Sq.m 1 1 15.500 5.600 86.800
RACK ROOM Sq.m 1 1 24.000 15.500 372.000
LOBBY middle -2 Sq.m 1 1 15.500 6.000 93.000
680.200
3 EPOXY PAINT
BATTERY ROOM on Floor Sq.m 1 1 10.700 12.000 128.400
BATTERY ROOM on Walls Sq.m 1 2 10.700 2.500 53.500
BATTERY ROOM on Walls Sq.m 1 2 12.000 2.500 60.000
241.900
4 FALSE CELING
RACK ROOM Sq.m 1 1 24.000 15.500 372.000
372.000
Remarks

Remarks
Remarks
SS-86 AND SCALE ROOM BROUGHTOUT ITEMS DETAILS

S.NO SOR ITEM BROUGHTOUT ITEMS UOM DRG.QTY SCH. RATE AMOUNT APPROVED PO/WO ISSUED TO SPECCIFICATIONS
MAKE/VENDER
CEMENT CONCRETE FLOOR :Providing and laying average 25mm cement
concrete flooring in panels consisting of base course of 1:2:4 grade
cement concrete (6mm down size stone aggregate) laid over sub-base of
1 A002.01.00 CEMENT cement concrete and finishing with a layer of floating coat of neat cement Sq.m 1230.615 ₹ 290.00 ₹ 302,275.96 EIL : 6-75-0002
CONCRETE FLOOR slurry @ 2.75kg. of cement per Sq. M. of area including cleaning the
subbase surface, applying neat cement slurry @ 2.75 kg of cement per Sq.
M. of area over the sub- base to receive the base course, compacting,
tamping,
HEAVY trowelling,
DUTY FLOORINGfinishing, curing,and
: Providing providing, shuttering
laying average 50mm to the edges
thick heavy
etc. all
duty complete
flooring in panels consisting of base course of 35mm thick cement
HEAVY DUTY concrete (1 cement : 1.5 coarse sand : 3.5 stone aggregates of 10mm to
2 A002.03.00 6mm size by volume) laid over sub-base and 15mm thick finishing layer Sq.m 1359.065 ₹ 630.00 ₹ 725,210.67 EIL : 6-75-0002
FLOORING
consisting of cement and integral hardening compound mixed in ratio of 4
cement :1 hardenar (by weight) :2 stone agrgregates of 6mm and down
size laid integral with base course and finished smooth including cleaning
the subbase
EPOXY PAINTsurface,
FLOOR applying
: Providingneat
andcement slurry
applying @2.75 Kg
pigmented of cement per
(approved
Sq.M ofchemical
shade) area overand
sub-base
abrasionto resistant,
receive the base course,
solvent levelling,
based self tamping,
levelling floor
trowelling,
coating finishing,
based curing,
on epoxy resinproviding
with amineshuttering to the edges
curing agents, etc. @
in 2 coats all 125
3 A002.15.00 EPOXY PAINT gms/sq.m.
omplete. (min.)per coat by brush or spraying over a levelling screed (min. Sq.m 455.730 ₹ 1,490.00 ₹ 575,144.93 EIL : 6-75-0002
FLOOR 3mm thick) of a 3 part solvent free combination of epoxy resin, amine
hardeners and graded chemically inert aggregate filler, laid over a coat of
2-part epoxy resin primer applied over existing flooring etc. all as per
manufacturer's
Granite Slab on specifications.
Counter Slab : Extra for round nosing/ moulded edges (as
4 A002.17.05 GRANITE COUNTER per approved design) to Granite stone slabs. Sq.m 3.000 ₹ 330.00 ₹ 838.53
SLAB
GRANITE STONE ATI SLIP FLOOR :Providing and laying anti slip
(rough)Granite stone slabs, of thickness minimum 25mm, in flooring,
5 A002.21.01 GRANITE STONE landing, tread, ramps over minimum 20mm thick cement mortor1:4 Sq.m 4.000 ₹ 4,630.00 ₹ 15,686.44
ANTI SLIP (1cement :4 course sand by volume) over and including a bed of cement
mortar including preparing the base surface, applying neat cement slurry
@ 2.75 kg. of cement per sq. mtr. of area to receive the mortar bed,
jointing each slab with neat cement paste/ grout with white cement mixed
with pigment
NON-SLIP (conforming
VITRIFIED to IS:2114,
TILES FLOOR Table-1)
: Ceramic, to match
matt thenon-slip
finished colour of the
type
granite stone slabs,
tiles of approved finishing
make etc. all complete.
and shade(s) in approved design/ pattern including
6 A002.11.05 NON-SLIP cleaning the finished surface with oxalic acid, wax polishing etc. for size Sq.m 24.000 ₹ 1,590.00 ₹ 32,321.52 EIL : 6-75-0002
VITRIFIED TILES 300mm x 300mm x 8mm (+5%) thick tiles for flooring.

VITRIFIED TILES FLOOR : Decorative, premium quality digitally glazed/


mirror finished Vitrified tiles in approved quality, colour(s), make, design/
pattern., laid with 3mm gaps all round each tile, provided with approved
7 A002.11.12 VITRIFIED TILES 3mm PVC spacer (cross-shaped, T-shaped and L-shaped- as required), Sq.m 485.207 ₹ 1,960.00 ₹ 805,501.84 EIL : 6-75-0002
including removing the spacers after setting, providing dust resistant
selflevelling flowable epoxy grout in the joints¿ gap (3mm) in approved
shade, cleaning, finishing the finished surface with oxalic acid etc. (of
minimum
WATER thicknessON
PROOFING 12mmSLABand of sizes 600mm
:Providing x 1200mm
and laying or A.P.P
4mm thick 800mm x
(atactic
800mm x 12mmmodified
polypropelene) thick or other approved
reinforced large sizes).
bituminous waterproofing membrane
over terrace and parapet including cleaning and preperation of the surface
8 A006.12.01 WATER PROOFING consisting of making good all the cracks and damages, filling potholes/ Sq.m 2656.200 ₹ 850.00 ₹ 1,912,331.19 EIL : 6-75-0006
depressions, removing weak foam concrete/ plaster and refilling with
same wherever required thus preparing smooth surface of the terrace;
providing and applying one coat of cold applied bitumen based primer @
0.2 to 0.4 litre per sq. mtr.; laying the membrane by torch welding over
primer, providing 100mm overlaps and ppropriately pressing the
membrane to remove any entrapped air, including fixing on parapet after
providing 10mm x 20mm continuous groove in parapet for terminating the
membrane and filling the groove with polyurethane sealant and
continuing this treatment at rain water outlet points; providing finishing
protective layer of 35 mm thk. P.C.C. (1:2:4) in panels of maximum size
1200mm x 1200mm chequered finish with 24 SWG chicken wiremesh
interposed in between finished smooth with joints between panels sealed
with suitable polyurethane sealant; providing fillets of 75 mm radius with
P.C.C. (1:2:4) at junctions of horizontal and vertical surfaces finished
smooth; providing 450mm x 450mm khuras (rain water collecting pits) in
1:2:4 cement concrete at all outlets, levelled down by min. 25mm,
finishing, curing etc. all complete as per approved manufacturer's
standard specifications and recommendations
S.NO SOR ITEM BROUGHTOUT ITEMS UOM DRG.QTY SCH. RATE AMOUNT APPROVED PO/WO ISSUED TO SPECCIFICATIONS
MAKE/VENDER
FALSE FLOOR :False flooring panels with minimum 10mm thick polished
mirror or mat finished vitrified tiles in approved design/ shade/ texture.
(Providing and installing/ fixing in position 600mm-1000mm high truly
9 A010.15.03 FALSE FLOOR levelled and aligned cavity/ false flooring system having load bearing Sq.m 773.200 ₹ 5,940.00 ₹ 3,890,108.38 EIL : 6-75-0010
capacity of uniformly distributed load of minimum 2025 kg/ sq.m. and
point load of 675 Kg., the system consisting of: (i) Sub-structure/ pedestal
assembly (designed for speedy assembly/ removal for relocation/
maintenance)
FALSE CEILINGof zinc electro
:Providing andplatedfixing steel comprising
false ceiling at allof: a. 90mm
height includingx 90mm
x 4mm embossed
providing and fixing pedestal
of frame headwork attachment
made of special mechanically
sections, riveted
powerto a
90mm long,
pressed fromminimum M.S. sheets 19mm and dia threaded
galvanized bright
with zincM.S.coating rod of stud120 with check
10 A010.17.00 FALSE CEILING gms/sqm
nuts for level (both adjustment
side inclusive) (for upto as per 25mm)
IS : 277 and and arresting
consisting vertical
of angle cleats Sq.m 2197.000 ₹ 660.00 ₹ 1,228,166.94 EIL : 6-75-0010
movement,
of size 25 mm anti-vibrational
wide x 1.6 mm PVC thickcapwith(for flanges
panel and of 27 stringer
mm and location),
37mm,b.at
CRCA mm
1200 (Electrical
centreresistant to centre, welded)
one flange Pedestal
fixedof to32mm
the ceiling dia (OD),
with 2mm dash thick
pipe mechanically
fastener 12.5 mm dia reducedx 50mm to four
longribs withat6mm top to diaaccommodate
bolts, other flange head of
assembly,
cleat fixedmechanically
UNDERDECK to INSULLATION
the angle hangers locked toofmaintain
25x10x0.50
:Polyisocyanurate true plumb
mm
foam of
(PIR) welded
required
shall be to pedestal
length
rigid with
base &
nuts
slabs plate.
sizec.1000
ofbolts ofPedestal
required
x 500mm Basesizeandplate 150mm
andthickness
other endxofof150mm xhanger
4mm thick
angle conforming
30mm fixedto (with
with
IS:
11 A010.12.00 UNDERDECK stiffening
intermediate
12436 havingfolds) G.I. fixed/
density channels anchored
not 45x15x0.9
less thanto main
32mm concrete floor
runningthermal
kg./Cu.M., at the @spacing
600mm
conductivity ofc/c
1200both
(K- Sq.m 1225.200 ₹ 1,200.00 ₹ 1,245,293.28 EIL : 6-75-0010
INSULLATION value)
wayscentre
mm (for
notinstalling
to centre,
more than flooring
to which
0.023 tiles)
w/mk the bymeasured
meanssection
ceiling ofatadhesive
100.5 deg. mm or
C. fastener
thick
The slabs asshall
bottom
recommended
wedge
be of 80on
covered mm bywith
one Manufacturer.
sidetapered
with glass (ii)
flanges Stringers
fibre oftissue/
26 mm ofAluminium
minimum
each having sectional
foil lips
having size
of 10.5
20mm
mm,
50mm x450
32mm
atoverlap. mmxThe 1.2mm
centre tomade
insulation centre, of shall
shall hotbedipbe galvanized
fixed inasa 'Non
classified steelCombustible'
direction cold rolled as
Supplying
BS 476,and
construction
perpendicular
per with
part fixing
to ribs
5G.I.
and in position
embossed
intermediate
'Class I' for25on mm 3 sides
channel
surface thickwith
spread BITUMEN
(designed
connecting
of flame forIMPREGNATED
strength,
asclips
per BS madelateral
476,out
FIBRE
of
part 7.BOARD
stability,
2.64 mm rollingdiaconforming
loads
x 230 and mm to tosupport
long IS:1838
G.I. wire of approved
panels quality
on alljunction,
at every four sides inincluding
expansion
for fixing
12 S002.26.02 BITUMEN FIBER joints
perimeterat allchannels
alignment), having counter 0.5 mmsunk thickholes27 mm at both ends for
high having fixing of
flanges to 20 pedestal
mm Sq.m 150.000 ₹ 1,270.00 ₹ 161,353.50
BOARD locations
head30
and and
assembly
mm long,levels
withthein M6 concrete
machine
perimeter structures
ofscrews.
ceiling (iii) etc.Removable
fixed All complete
to wall/partition andasre-usable
shown,
with the
specified
Floorof
help panels
rawlandplugsofdirected
sizeat600mm
450 mmx 600mm centre, with made of all long
25mm steeldry weldedwall screws @
construction
230
Supplying and(cleaned,
mm interval, including
sealing degreased
EXPANSION fixing of and
JOINTSphosphated
gypsum 25board
mm wide with
to 11 tank
ceiling
and section
12mm process,
and at
deep
finished
perimeter withchannel40-60 micron
with inthe epoxy
help ofcoating dry wall (and,
screwsheated of size to achieve
3.5two x 25partmm at
POLYSULPHIDE all
230
locations
adhesion
mm to
c/c,
and
the
levels
panel
including
Concrete
surface
jointing and
and
Structures
corrosion
finishing
with
resistance)
to a
approved
flush with
finish ofbottom
tapered
13 S002.26.04 SEALING liquid POLYSULPHIDE SEALING COMPOUND as per IS:12118 including RM 150.000 ₹ 500.00 ₹ 63,525.00
surface
and
raking ofconsisting
square edges
joints etc.ofallthemultipleboardhemispherical
complete with recomme-nded
as shown, and reverse
specified and cones
jointing and top ,
compound
directed.
COMPOUND plain sheet
jointing tapes (fuse weldedwith
, finishing at 129 locations)
jointing compoundto forminan enclosed
3 layers panelupto
covering of an
overall
150 mmdepth on both 37mm; sidesthe of inner
joint and empty twocore coats ofof the panelsuitable
primer injectedfor with light
board,
weight
all
AIR firemanufacturer¿s
asCONDITIONING
per retardant,SS-86 noncombustible
specification
(CT) :Air Conditioningcementitious
and also includingSystem compound the
for Sub (at
cost ofhigh
Station-86
pressureopenings
making
(Cooling to fill allBuilding
Tower) crevices
for of the panel),
lightDesign,
fittings, each panel
grills, diffusers,
engineering, finished
cutouts
procurement made onraw
of top
withwith
2mm thick
frame
materials andfirebought
of perimeter retardant outfloor
channels grade high
suitably
components, fixed, pressure
all complete
manufacturing, laminate/ as per
assembly 2mm atthick
drawings,
shop,
14 Q999.99.99V14 HVAC anti-static
specification PVC and tiles in approved
direction of thedesign/
Engineer
inspection, testing at manufacturer's works, painting (primer + finish shade/in texture;
Charge but fixed to
excluding flooring
the
coat), LOT 1.000 ### ###
panel
cost ofby means
painting of
with: approved
12.5 mm adhesive;
thick the
tapered
packing and delivery including supply of all commissioning spares, special edges
edge of the
gypsum finished
moisture panels
provided
resistant with
board conductive PVC edge trim
tools and tackles, first fill of refrigerant & lubricants for AC System 5mm wide on all sides
(mechanically
including locked and
all associated sealed
piping, in place). The itempumps,
valves/instruments, includes: i) Providing
ducting,
andConditioning
Air fixing all accessories
diffusers/grilles System
etc., likeScale
for
transportation screws, Room bolts,
from adhesive
Building
vendor's :worksetc. to
Supply asofsite,
perInverter
unloading
manufacturer's
Controlled
at Split specifications.
site, handling, Air Conditionerii)with
transportation toMaking
contractor'snecessary
compatible adjustment
stabilizer
store and from (copper in grid
contractor's
15 Q999.99.99V17 AIR dimensions,
winding)
store to work stringer
complete site, storage lengths,
with floorfabrication/assembly
allat site, panel dimensions etc. atatsite,ends or centre
installation, LOT 1.000 ₹ 70,000.00 ₹ 59,290.00
CONDITIONING accessories
(to cater
hook up, to specific
and fittings,
testing, roomincluding
painting, sizes) or supply
insulation, at panels locations,
of first
pre-commissioning, as required.
fill of refrigerants
commissioning, iii)
(non-
Cutting
CFC of floor
and eco-friendly),
performance panels as
guaranteetransportation required
run test at site, at ends.
from iv) Treating
vendor's
handing overworks the
to client underneath
to site,
and other
cement
unloading concrete
at site, floor
handling,with one component
transportation
field works including civil-structural, electrical & instrumentation work to polyurethane
contractor's floor
store coating
and from
MS-ANGLES
etc. all complete.
contractor's
complete in all110respect
store Xv)
to110work X 6per
Providing
as MM
site, THICK :at
additional
storage
enclosed Supplying,
steel
site, structural
Scope assembly
of transporting,
Supply supports/
at
and site,
Work storing,
fabricating
pedestal assembly
installation,
(Equipment and
testing,fixing
Division), in
Doc.position
atpainting,
edges, cut
No. M.S. etc.
outs
insulation, METAL INSERT (with
as required.
commissioning,
B015-000-80-43-SOW-8204, lugs)
vi) handingJob ofover
Providing any
all to
shape
necessary
client made
and
Specification other out
accessories of flats,
field
(Equipment such
works plates,
as rolled
outlet
including
Division), Doc. sections,
boxes, No.grommets,
civilstructural pipes etc.
works providing
Panel
B015-000-80-43-SP-8204 lifters (at
complete in and
all
16 S006.16.01 MS-INSERTS necessary
least one templates,
forforACeach staging,
building) cutting,
as required straightening, if required, bolting, MT 39.000 ₹ 100,200.00 ₹ 3,309,906.60
respect
other documents areas as marked
referred therein for Airetc.
in respective all complete.
architecture
Conditioning drawing. Split
System.Air
welding
unit as required
shall haveSystem
Conditioning and
wall mounted embedding
shall consist indoor in position
unit and outside
of following on both
major items: Plain
located and
a) air cooled
Single Effect
Reinforced
condenser
Vapour Absorption Cement based
(outdoor concrete
unit) with members
Chillier Units:inclusive
insulated 2refrigerant
Nos. (Both of adjusting
piping,
Working), shuttering
controlseachand of &
reinforcement/
line accessories,
minimum any
83 TR (Actual other
civil & electrical fixture,
Capacity,works welding
i.e. after(e.g.where necessary,
civil work related
considering tying and
capacitytoderation as
holding
concealing
per design to correct
of refrigerant
conditions level, line
piping,
mentioned and drainposition,
in abovepiping any
Jobtoauxiliary
the nearest
Specification) dummy drain,
b) AHUstructures
cabling
of
to
of support
AC
22400 CFMthe
units) heavy inserts,
as Working)
(1 required including
minimum paintingthe exposed
for structural
First Floor.surfaces
steel
c) AHU with
framework,
of 22100 a coatCFM (1
pedestal/bracket
Working) minimum to for
mount Second the Floor.
indoord)and outdoor
Chemical units,
Filter (2 supports
Nos.), each & of
clamps
3025 CFM for Capacity
refrigerant piping/cables,
minimum for Firststabilizer,
Floor. e) hold Chemical downFilter nuts (1 & No.)
bolts,of
spares
2650 CFM for commissioning
Capacity minimum and for start up etc.Floor.f)
Second as perDucting
enclosed and Scope of
associated
Supply
accessoriesand Work for Air(Equipment
DistributionDivision), (Lot) Doc. No. B015-000-80-43-SOW-
8204, Job Specification (Equipment Division), Doc. No. B015-000-80-43-SP-
8204 and other documents referred therein for Air Conditioning System.
Air Conditioning System shall consist of following major items: a) Inverter
Controlled Split Air conditioner (1 No.) of 2 TR capacity (Nominal)
S.NO SOR ITEM BROUGHTOUT ITEMS UOM DRG.QTY SCH. RATE AMOUNT APPROVED PO/WO ISSUED TO SPECCIFICATIONS
MAKE/VENDER
MS-ANGLES 65 X 65 X 6 MM THICK : Supplying, transporting, storing,
fabricating and fixing in position M.S. METAL INSERT (with lugs) of any
shape made out of flats, plates, rolled sections, pipes etc. providing
17 S006.16.01 MS-INSERTS necessary templates, staging, cutting, straightening, if required, bolting, MT 1.000 ₹ 100,200.00 ₹ 84,869.40
welding as required and embedding in position on both Plain and
Reinforced Cement concrete members inclusive of adjusting shuttering &
reinforcement/ any other fixture, welding where necessary, tying and
MS-FLAT
holding to25correct
X 6 MM THICK
level, linefor
andLUGS : Supplying,
position, transporting,
any auxiliary dummy storing,
structures
fabricating andheavy
to support the fixing inserts,
in position M.S. METAL
painting exposed INSERT (with
surfaces lugs)
with of any
a coat
shape made out of flats, plates, rolled sections, pipes etc. providing
18 S006.16.01 MS-INSERTS necessary templates, staging, cutting, straightening, if required, bolting, MT 1.500 ₹ 100,200.00 ₹ 127,304.10
welding as required and embedding in position on both Plain and
Reinforced Cement concrete members inclusive of adjusting shuttering &
reinforcement/ any other fixture, welding where necessary, tying and
HAND
holdingRAILS FOR STAIR
to correct level, CASE : Supplying,
line and position, assembling
any auxiliaryand installing
dummy 1000
structures
mm high satin
to support the finish
heavystainless steel (SSexposed
inserts, painting 304 grade) tubular
surfaces railing
with a coatof
approved design in staircases, ramps, around floor cut outs etc. consisting
19 A011.22.00 HAND RAILS of: 1. 50mm dia SS pipe top handrail 2. 32 mm dia SS pipe balusters (at RM 1200.000 ₹ 4,340.00 ₹ 4,411,176.00
every third step for staircase, @ maximum 1200mm c/c for ramp, floor
cutouts) 3. 3 nos minimum 18mm dia SS pipe intermediate handrails.
Including: 1. Fixing balusters to floor with 4 nos bolts änd 8mm thick,
100
100mmMMdia DIASSPVC
basePIPE : 110mm
plate dia O.D. 2.
& SS cap/collar. Size. embedded
Fixing PVC rain
top handrail to thewater
pipe jointed
balusters with
with 12mmbonding
dia SSsolution of approved
bar connector & 6mm quality
thickand make with
SS saddle plate. 3.
20 A008.12.07 PVC PIPE INSERTS pressure rating of 4kg/cm2
Fixing intermediate handrailsincluding clamps, connections
to the balusters with 12mm dia etc.SS
allbar
as per RM 360.000 ₹ 620.00 ₹ 189,050.40
approved
connector.manufacturer's
4. All end caps,details.
decorative caps over balustrades,necessary
bending, welding, polishing of all welded joints (Length of top handrail
shall be measured for payment).
160 MM DIA PVC PIPE : 160mm dia O.D. Size. embedded PVC rain water
pipe jointed with bonding solution of approved quality and make with
21 A008.12.08 PVC PIPE INSERTS pressure rating of 4kg/cm2 including clamps, connections etc. all as per RM
approved manufacturer's details.

22

23

24

25
S.NO SOR ITEM BROUGHTOUT ITEMS UOM DRG.QTY SCH. RATE AMOUNT APPROVED PO/WO ISSUED TO SPECCIFICATIONS
MAKE/VENDER

26

###
SS-86 PLANT AND NON-PLANT BUILDINGS : VRMP-HPCL,VSP
FLOOR NO S.NO ROOM DETAILS FLOOR TYPE AC FC UD GBP ROOM SIZE in M ROOM AREA

1 CABLE CELLAR CCF (66.550 x 15.30 ) + ( 12.00 x 11.70 ) 1158.615

LOADING/ UNLOADING PLATFORM ON


GROUND FLOOR ROOMS

2 HD 16.00 x 3.00 48.000


GROUND (EAST)
LOADING/ UNLOADING PLATFORM ON
3 HD 7.50 x 3.00 22.500
GROUND (WEST)
4 A C PLANT ROOM HD 12.00 x 12.00 144.000
5 STORE ROOM CCF 6.00 x 6.00 36.000
6 MAINTENANCE ROOM CCF 6.00 x 6.00 36.000
7 STAIRCASE On Ground (East) GS-ASG 7.50 x 3.00
8 STAIRCASE On Ground (Wast) GS-ASG 7.50 x 3.00
9 LOBBY on Ground (7-8 Grids ) VT (6.0 x 1.5 ) + (3.0 x 3.0 ) 18.000

10 TOILET on Ground (E-F Row) N-S VT 4.00 x 3.00 12.000


11 SWITCHGEAR HALL HD AC FC 66.550 x 15.000 997.500
12 GIS PANEL AREA HD 12.00 x 12.00
109.800
Deeduction area for Oprator Room (-) HD 6.00 x 5.70
Deduction for Slab Openings (-) HD -352.235
FRIST FLOOR ROOMS

13 AIR HANDLING UNIT HD 12.000 x 12.000 144.000


14 AIR LOCK LOBBY on Frist floor East VT FC 3.5 x 2.5 8.750
15 AIR LOCK LOBBY on Frist floor West VT FC 3.5 x 2.5 8.750
LOADING/ UNLOADING PLATFORM ON Frist
16 HD 12.00 x 3.50 42.000
floor (EAST)
LOADING/ UNLOADING PLATFORM ON Frist
17 HD 5.00 x 3.50 17.500
floor (West)
18 BATTERY ROOM EP 12.00 x 6.00 72.000
BATTREY ROOM Walls upto 2.50m EP 2 x (12.00+6.00) x 2.5 90.000
19 OPERATOR ROOM VT AC FC GBP 6.00 x 5.70 34.200
FRIST
FLOOR NO S.NO ROOM DETAILS FLOOR TYPE AC FC UD GBP ROOM SIZE in M ROOM AREA
Deduction for Slab Openings (-) VT -5.233
FLOOR NO S.NO ROOM DETAILS FLOOR TYPE AC FC UD GBP ROOM SIZE in M ROOM AREA
20 RACK ROOM FF AC FC UD 30.00 x 15.50 465.000
21 ENGG. ROOM FF AC FC UD 15.50 x 5.60 86.800
22 UPS ROOM FF AC FC UD 10.70 x 12.00 128.400
SECOUND FLOOR ROOMS

23 BATTREY ROOM EP 10.70 x 12.00 128.400


BATTREY ROOM Walls upto 2.50m EP 2 x (10.70+12.00) x 2.5 113.5
24 ELECTRICAL ROOM VT 10.20 x 5.70 58.140
25 TECH ROOM VT AC FC UD 12.00 x 12.00 144.000
26 AHU ROOM HD UD 12.00 x 12.00 144.000
27 LOBBY-01 VT AC FC UD 30.00 x 4.800 144.000
28 LOBBY-02 FF AC FC UD 15.5 x 6.00 93.000
LOADING/UNLOADING PLATFORM on Secound
29 HD 12.00 x 3.50
floor (East) 42.000
30 AIR LOCK LOBBY east VT FC 7.80 x 3.50 27.300
31 AIR LOCK LOBBY West VT FC 7.80 x 3.50 27.300
32 TOILET on Secound Floor (E-F Row) N-S VT FC 4.00 x 3.00 12.000
33 WATER PROOFING ON SLAB 1st Floor WP (36.550 x 14.00) + ( 57.0 x 7.0 ) 967.7
34 WATER PROOFING ON SLAB 2nd Floor WP ( 75.5 x 17.0 ) + ( 13.5 x 30.0 ) 1688.5
UOM

Sq.m

Sq.m

Sq.m

Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m

Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m

Sq.m

Sq.m

Sq.m
Sq.m
Sq.m
UOM
Sq.m
UOM
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
Sq.m

Sq.m

Sq.m
Sq.m
Sq.m
Sq.m
Sq.m
SCALE ROOM BROUGHTOUT ITEMS

S.no. Ground Floor Item Description Uom No No Length Width Qty Remarks

1 FALSE CELING Sq.m 1 1 5.000 4.000 20.000 EIL Spec.: 6-75-0010

2 Under deck Insulation Sq.m 1 1 5.000 4.000 20.000 EIL Spec.: 6-75-0010

3 Water Proofing on Slab Sq.m 1 1 7.300 7.100 51.830 EIL Spec.: 6-75-0006

4 Cement Creed on Slab Sq.m 1 1 7.300 7.100 51.830

5 Vertified Flooring Sq.m 1 1 5.000 4.000 20.000 Conform EN : 176 EIL Spec.: 6-75-0002

A002.21.00 Providing and laying anti slip (rough)Granite stone slabs, of thickness minimum 25mm, in
flooring, landing, tread,ramps over minimum 20mm thick cement mortor1:4 (1 cement : 4 course sand by
volume) over and including a bed of cement mortar including preparing the base surface, applying neat
cement slurry @ 2.75 kg. of cement per sq. mtr. of area to receive the mortar bed, jointing each slab with
6 Granite Flooring Outside Short side Sq.m 1 2 6.700 1.350 18.090 neat cement paste/ grout with white cement mixed with pigment (conforming to IS:2114, Table-1) to
match the colour of the granite stone slabs,finishing etc. A002.23.00 all complete. and Providing 3 nos. of
3mm grooves at spacing of 30mm in Kota/ Marble/ granite stone laid in stairs¿ treads/ landings all
complete as per the direction of Engineer-In-Charge. (Single measurement shall be considered for 3
parallel grooves)

7 Granite Flooring Outside Long side Sq.m 1 2 7.700 1.350 20.790

8 Granite Slab on Counter Slab Sq.m 1 1 5.000 0.600 3.000 A002.17.05 Extra for round nosing/ moulded edges (as per approved design) to Granite stone slabs.
ARCHITECTURAL FINISHES SCHEDULE

FLOOR NO ROOM FLOOR FINISH


G CABLE CELLAR CEMENT CONCRETE
LOADING/ UNLOADING PLATFORM HEAVY DUTY
G,1,2
TRANSFORMER GRAVEL
G
CAPACITOR BANK GRAVEL
G
A C PLANT ROOM HEAVY DUTY
G
STORE & MAINTENANCE ROOM CEMENT CONCRETE
G
SWITCHGEAR HALL HEAVY DUTY
1
1,2 AIR HANDLING UNIT(AHU) HEAVY DUTY
AIR LOCK LOBBY VITRIFIED TILE
1,2
TOILET NON-SLIP VITRIFIED
G,2
STAIRCASE GRANITE STONE FLOORING WITH
G,1,2 ATI SLIP GROOVES

BATTERY ROOM EPOXY PAINTED


1,2

OPERATOR ROOM VITRIFIED TILE


1
TECH ROOM VITRIFIED TILE
2
ELECTRICAL ROOM VITRIFIED TILE
2
UPS ROOM FALSE FLOOR
2
LOBBY -1 VITRIFIED TILE
2
LOBBY -2 FALSE FLOOR
2
ENGINEERING ROOM FALSE FLOOR
2
RACK ROOM FALSE FLOOR
2
SKIRTING/WALL BASE WALL FINISH
125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + OIL BOUND DISTEMPER
125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT

- CEMENT PLASTER + OIL BOUND DISTEMPER

- CEMENT PLASTER + OIL BOUND DISTEMPER

125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + OIL BOUND DISTEMPER

125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT

125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT
125mm HIGH CEMENT PLASTER SKIRTING CEMENT PLASTER + OIL BOUND DISTEMPER
125mm HIGH VITRIFIED TILES SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT
- CERAMIC TILES DADO UP
TO CEILING
125mm HIGH GRANITE SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT

- 2500 MM HIGH EPOXY PAINT ON WALL OVER


CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT ABOVE 2500MM HEIGHT

125mm HIGH VITRIFIED TILES SKIRTING CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT
CEILING FINISH
CEMENT PLASTER + OIL BOUND DISTEMPER
CEMENT PLASTER + POP PUNNING + PLASTIC
EMULSION PAINT

CEMENT PLASTER + OIL BOUND DISTEMPER

CEMENT PLASTER + OIL BOUND DISTEMPER

CEMENT PLASTER + OIL BOUND DISTEMPER

CEMENT PLASTER + POP PUNNING + PLASTIC


EMULSION PAINT

COMBINATION OF MINERAL FIBRE TILES &


GYPSUM BOARD PANEL FALSE CEILING

GYPSUM BOARD PANEL FALSE CEILING

CEMENT PLASTER + OIL BOUND DISTEMPER

CEMENT PLASTER + POP PUNNING + PLASTIC


EMULSION PAINT

CEMENT PLASTER + OIL BOUND DISTEMPER

GYPSUM BOARD PANEL FALSE CEILING


SUB-STATION 86 (CT) Floor Slab @ 105 m
110 x 110 x 6 mm Thick Equal Angle
Length Width Nos Nos Total in Rm
F to E 3.775 0.950 1 2 18.900
4.025 0.950 1 2 19.900
E to D 1.755 0.650 2 2 19.240
4.025 0.650 2 2 37.400
0.300 0.450 2 2 6.000
C2-C4 to D2-D4 4.275 1.600 1 2 23.500
5.550 1.600 1 2 28.600
4.275 0.950 1 2 20.900
5.550 0.950 1 2 26.000
C to B 4.275 1.200 1 2 21.900
5.550 1.200 1 2 27.000
4.275 1.600 1 2 23.500
5.550 1.600 1 2 28.600
B4 -D4 to B13 - D13 5.550 1.700 9 2 261.000
5.550 0.950 9 2 234.000
5.550 1.200 9 2 243.000
5.550 1.600 9 2 257.400
5.550 0.350 9 2 212.400
1509.240 Rm
25.700 Kg/m
38.787

25 x 6 mm Lugs 1509.240 6038 0.200 1207.600 Rm


1.180 Kg/m
1.425

65 x 65 x 6 mm Thick Equal Angle

B2 to B 13 0.200 1.000 10 2 48.000


B2 to B 13 0.200 0.400 32 2 76.800
124.800 RM
5.800 Kg/m
0.724 MT
25 x 6 mm Lugs 124.800 500 0.200 100.000 Rm
1.180 Kg/m
0.118 MT

S.no ABSTRACT QTY Total Wt UoM


1 110 x 110 x 6mm th 38.787 MT
2 65 x 65 x 6 mm th 0.724 MT
3 25 x 6 mm Flat Lugs 1.543 MT
Total Qty = 41.054 MT
SS-86 104m Slab 100 mm Dia PVC PIPES SLEAVES
S.No TYPE Set Nos Length To. Rm
1 Detail A 8 12 1.000 96.000
2 Detail B 6 11 1.000 66.000
3 Detail C 5 12 1.000 60.000
4 Detail D 10 11 1.000 110.000
5 1 19 1.000 19.000
Total PVC Pipe Sleaves in Rm = 351.000