You are on page 1of 4

Duri oil field is approximately 18km long and 18km wide.

It is located in the Riau Province, in the South


Sumatra Basin on the eastern coast of Sumatra, Indonesia.

Duri Field was discovered in 1941. The onshore oil field was brought on stream in 1954. The primary
production from the field peaked at 65,000 barrels per day (bpd) in the mid 1960s. The oil output of the
field is sent via a 25in pipeline to the port of Dumai for sale.

Following the decline of it production yield due to the drop in natural reservoir pressures, the oil field
started using steam-flood technology from 1985. Duri is considered to be one of the largest steam-flood
developments in the world.

The daily production from the Duri field currently averages to approximately 185,000 barrels accounting
for nearly half of CPI’s total production.

The oil field continues to undergo expansion to sustain production and increase oil recovery. A total of
186 additional production wells and 56 steam-injection and observation wells were drilled in the
producing areas of the oil field in 2012.

Steam-flooding pilot project at Duri field

A pilot steam-flood project was launched at the Indonesian oil field in 1975 in order to improve its
production. The steam-flooding technology is used for enhancing oil recovery by injecting steam into the
oil reservoir. The technology was first deployed at the field in 1985.

The gas meant for steam-flooding is supplied by the Grissik-Duri pipeline. The steam-flood project
receives power from the Chevron-operated 300MW North Duri Cogeneration Plant.

The steam-flooding technology, by 2008, enhanced the Duri oil production by more than three times
and allowed the recovery of more than two billion barrels of crude oil.

A total of 12 development areas in the field have been developed with the Duri Steam Flood project. As
of 2013, approximately 80% of the Duri field was steam injected.
North Duri Field Area 12 Expansion project details

The North Duri Field Area 12 Expansion involved drilling and development of new production wells in
the northern area of the Duri Field.

Production from the oil field expansion project started in November 2008. Steam-flood technology was
deployed at the project area in 2009.

The expansion project contributed an additional 40,000 barrels of oil per day to Duri Field’s total oil
output.

North Duri Development Area 13 expansion project

"The $500m expansion project broke ground in October 2012."

North Duri Development Area 13 is the latest expansion project at Duri. The Engineering, Procurement
and Construction (EPC) contract for the project was awarded in June 2012.

The $500m expansion project broke ground in October 2012. A total of 539 new wells including 358
producing wells, 145 steam injection wells and 36 temperature observation wells will be drilled as part
of the North Duri Development Area 13 project.

The expansion project is scheduled for completion by the end of 2013. It will add 17,000 barrels of oil to
the Duri field’s daily production capacity.

Contractors involved with North Duri Development Area 13 expansion project

A consortium led by the Indonesian company Wijaya Karya (WIKA) was awarded an EPC contract worth
$182.9m for the North Duri Development Area 13 expansion project. Other partners of the consortium
include Inwha Indonesia and Singgar Mulia. WIKA’s share in the contract is $146m, which is
approximately 80% of the contract value.
Lapangan minyak Duri memiliki panjang sekitar 18 km dan lebar 18 km. Terletak di Provinsi Riau, di
Cekungan Sumatra Selatan di pantai timur Sumatera, Indonesia.

Duri Field ditemukan pada tahun 1941. Ladang minyak onshore mulai beroperasi pada tahun 1954.
Produksi utama dari lapangan mencapai 65.000 barel per hari (bpd) pada pertengahan 1960-an. Output
minyak lapangan dikirim melalui pipa 25in ke pelabuhan Dumai untuk dijual.

Setelah penurunan hasil produksi karena penurunan tekanan reservoir alami, ladang minyak mulai
menggunakan teknologi steam-flood dari tahun 1985. Duri dianggap sebagai salah satu perkembangan
uap-banjir terbesar di dunia.

Produksi harian dari lapangan Duri saat ini rata-rata mencapai sekitar 185.000 barel yang menyumbang
hampir setengah dari total produksi CPI.

Ladang minyak terus mengalami ekspansi untuk mempertahankan produksi dan meningkatkan
pemulihan minyak. Sebanyak 186 sumur produksi tambahan dan 56 sumur injeksi uap dan sumur
observasi dibor di area produksi ladang minyak pada tahun 2012.

Proyek percontohan steam-flooding di lapangan Duri

Proyek percontohan banjir-uap diluncurkan di ladang minyak Indonesia pada tahun 1975 untuk
meningkatkan produksinya. Teknologi steam-flooding digunakan untuk meningkatkan pemulihan
minyak dengan menyuntikkan uap ke dalam reservoir minyak. Teknologi ini pertama kali digunakan di
lapangan pada tahun 1985.

Gas yang dimaksudkan untuk steam-flooding dipasok oleh pipa Grissik-Duri. Proyek steam-flood
menerima listrik dari 300MW North Duri Cogeneration Plant yang dioperasikan Chevron.

Teknologi steam-flooding, pada tahun 2008, meningkatkan produksi minyak Duri lebih dari tiga kali dan
memungkinkan pemulihan lebih dari dua miliar barel minyak mentah.

Sebanyak 12 bidang pembangunan di lapangan telah dikembangkan dengan proyek Duri Steam Flood.
Pada 2013, sekitar 80% dari bidang Duri disuntikkan uap.
Area Lapangan Duri Utara 12 Rincian proyek perluasan

Area Lapangan Duri Utara 12 Ekspansi melibatkan pengeboran dan pengembangan sumur produksi baru
di daerah utara Duri Field.

Produksi dari proyek perluasan ladang minyak dimulai pada November 2008. Teknologi Steam-flood
dikerahkan di area proyek pada tahun 2009.

Proyek perluasan menyumbangkan tambahan 40.000 barel minyak per hari ke total output minyak Duri
Field.

Pengembangan Area Pengembangan Wilayah Duri Utara 13

"Proyek perluasan $ 500 juta pecah pada Oktober 2012."

North Duri Development Area 13 adalah proyek perluasan terbaru di Duri. Kontrak Engineering,
Procurement and Construction (EPC) untuk proyek ini diberikan pada Juni 2012.

Proyek perluasan $ 500 juta pecah pada Oktober 2012. Sebanyak 539 sumur baru termasuk 358 sumur
produksi, 145 sumur injeksi uap dan 36 sumur observasi temperatur akan dibor sebagai bagian dari
proyek Pengembangan Wilayah Duri Utara 13.

Proyek perluasan dijadwalkan selesai pada akhir 2013. Ini akan menambah 17.000 barel minyak ke
kapasitas produksi harian lapangan Duri.

Kontraktor yang terlibat dengan proyek perluasan Pengembangan Wilayah Duri Utara 13

Sebuah konsorsium yang dipimpin oleh perusahaan Indonesia Wijaya Karya (WIKA) dianugerahi kontrak
EPC senilai $ 182.9m untuk proyek ekspansi North Duri Development Area 13. Mitra lain dari konsorsium
termasuk Inwha Indonesia dan Singgar Mulia. Bagian WIKA dalam kontrak adalah $ 146m, yang kira-kira
80% dari nilai kontrak.

You might also like