POST EARTHQUAKE ACTION PLAN


OBJECTIVES TARGET DATE OF ACTIVITY/IES PERSONS RESOURCES REMARKS
IMPLEMENTATION INVOLVED NEEDED
1. To discuss the most relevant issues on NOVEMBER 11,  Conference of School School head, DRRM Safe Area where
what to do after the earthquake 2019 Teaching and Non- Coordinator, Physical the meeting will
damages. Teaching Personnel facilities Coordinator, be conducted, Site
2. To assign competent teachers and  Creation of TWG and Teachers, Utility Development
other personnel/individuals to a Workers, PTA Board Plan, Electrical
Committee for Oplan
special task for clearing and removing Barangay Officials, and Plan, Electrical
Balik Kaayusan ng
immediate hazards that can be some Boy Scouts Tools, Carpentry
Paaralan Tools, Empty
managed by them.
 Creation of Committee Sacks, Human
3. To assign subject area coordinators
and competent teachers to for Curriculum Concerns Force, Curriculum
synchronize and coordinate school Guide, ADM
adoptive measures to the SDO for the Modules, Printers,
project “BARUG DIGOS”. Papers
4. To remove immediate hazards that NOVEMBER 12,  Clearing the Hazards School head, Special Electrical Tools,
can cause dangers to students and 2019  Locating office hubs and TWG, Barangay DRRM Carpentry Tools,
school personnel. TEMPORARY LEARNING Team, Selected Boy Empty Sacks,
5. To locate a strategic area for SHELTER Scouts, Teachers Human Force
temporary School Offices and  Dissemination of
Temporary Learning Shelter information for Gen. PTA
Assembly
6. To inform the PTA Officials, Parents NOVEMBER 13,  GENERAL PTA ASSEMBLY School head, Teachers, Sound system
and Other Stakeholders about the 2019 Non – teaching
Alternative Plan of the School; ADM Personnel, Parents
approach and shifting of classes.
7. To secure repair, and put in order NOVEMBER 14 - 15,  Repair of identified damage Physical facilities Electrical Tools,
functional including damage 2019 classrooms Coordinator, Property Carpentry Tools,
properties of the school.  Securing School properties Custodian, Teachers, Empty Sacks,
8. To prepare other classrooms for the  Cleaning of other Non-Teaching Staff, Human Force
resumption of classes. classrooms that are not parents, volunteers
damage
9. To finalized and recheck repaired NOVEMBER 16,  Finalized and check Physical facilities Electrical Tools,
classrooms and Temporary 2019 repaired classrooms and Coordinator, Property Carpentry Tools,
Learning Shelter. temporary learning shelter Custodian, Teachers, Empty Sacks,
Non-Teaching Staff, Human Force
parents, volunteers

10. To start the resumption of classes NOVEMBER 18,  Resumption of classes School Head, Teachers Human force,
based on the agreed CLASS SCHEDULE 2019  Orientation with and students sound system
psychological first aid and
earthquake drill

Prepared by:

ALAN B. TIZON

School In –Charge/HT-III