Professional Documents
Culture Documents
MANUAL
FOR
210 MW TOTALLY IMPREGNATED
TURBOGENERATOR
INDIRECT GAS COOLED STATOR WINDING
AND DIRECT GAS COOLED ROTOR WINDING
RAYALSEEMA TP,
STAGE-3
RAYALSEEMA TP ,STAGE-3
General
Description
Operation
Maintenance
Inspection
Appendix
2.0-0010-7500/2
Lowering Hydrogen Gas Pressure Preventive Measures to Avoid Moisture
in Generator........................................... 2.3-8610 Condensation............................................ 2.5-1005
Gas Removal - Replacing H2 with CO2........... 2.3-8620 inspection Schedule - Introduction.................... 2.5-1010
Gas Removal - Replacing CO2 with Air.......... 2.3-8630 Inspection Schedule - Stator............................. 2.5-1020
Exciter.............................................................. 2.3-8900 Inspection Schedule - Rotor.............................. 2.5-1030
Inspection Schedule - Coolers.......................... 2.5-1040
Fault Tracing Inspection Schedule - Bearings........................ 2.5-1050
General.......................................................... 2.3-9000 Inspection Schedule - Shaft Seals................... 2.5-1060
Stator and Generator Supervisory Inspection Schedule - Seal Oil system............. 2.5-1071
Equipment............................................... 2.3-9200 Inspection Schedule - Gas System................... 2.5-1072
Rotor................................................................ 2.3-9310 inspection Schedule - Generator
Hydrogen Coolers......................................... 2.3-9440 Supervisory Equipment............................. 2.5-1080
Bearings........................................................ 2.3-9450 Inspection Schedule - Excitation System.......... 2.5-1090
Bearing Vapor Exhausters............................ 2.3-9521 Measures for Preservation............................... 2.5-1100
Seal Oil Pumps............................................... 2.3-9523 Stator................................................................. 2.5-2000
Seal Oil Pressures and Temperatures.......... 2.3-9531 Check list on works on Generator............................2.5-2001
Oil Level in Seal Oil System........................... 2.3-9561 Cementing the Joints of Porfiled Gaskets......... 2.5-2120
CO2 Flash Evaporator and Gas Dryer-.......... 2.3-9630 Mounting of Inner Labyrinth Rings.................... 2.5-2126
Gas Pressure and Volumetric Flow Rates.... 2.3-9640 Generator Drying System................................. 2.5-2155
Gas Purity Meter System.............................. 2.3-9680 Fitting New Seal Strips to Labyrinth Rings........ 2.5-2163
Insulation Resistance Measurements
Fuses on Rectific Wheeles........................... 2.3-9901
on Stator Winding...................................... 2.5-2300
Exciter Temperatures.................................... 2.3-9911
Drying the Windings.......................................... 2.5-2310
Exciter Cooler................................................ 2.3-9914
Treatment of Bolted Contact Surface................ 2.5-2350
Storboscope.................................................. 2.3-9941
Rotor.................................................................. 2.5-3000
Exciter Drying System.................................... 2.3-9955
Insulation Resistance Measurements on
Exciter Fault Detection System in
Rotor and Exciter Winding......................... 2.5-3300
Exciter Field Circuit................................. 2.3-9980
Ultrasonic Examination of Rotor Retaining
Ring at Power Plant................................... 2.5-3367
Maintenance
Hydrogen Cooler................................................ 2.5-4000
Maintenance and Supervision-Introduction.... 2.4-4200
Bearings............................................................ 2.5-5000
Survey on Maintenance and Supervision...................2.4-4205 Shaft Seal.......................................................... 2.5-6000
Stator................................................................. 2.4-4210 Seal Oil System................................................. 2.5-7100
Hydrogen Coolers.......................................... 2.4-4240 Seal Oil Pumps and Bearing
Bearings........................................................ 2.4-4250 Vapor Exhausters..................................... 2.5-7120
Barton Cells(Vacuum Indication)...................... 2.4-4281 Vacuum Pumps.........................................................2.5-7121
Rotor.................................................................. 2.4-4310 Seal Oil Coolers................................................. 2.5-7130
Seal Oil Pumps and Bearing Vapor Exhausters.... 2.4-4520 Gas System....................................................... 2.5-7200
Seal Oil Coolers.............................................. 2.4-4540 Exciter................................................................ 2.5-9000
Seal Oil Filters................................................ 2.4-4550 Checking the Insulation Resistance of
Gas Consumption........................................... 2.4-4610 the Heat Sink Insulation.............................. 2.5-9010
Replacing Gas Dryer Desiccant..................... 2.4-4661 Checking the Insulation Rectifier Wheels..................2.5-9011
Fuses on Rectifier Wheels............................ 2.4-4910 Exciter Cooler.................................................... 2.5-9440
Emergency Ventilation and
Make-up Filter of Exciter................................. 2.4-4930 Appendix
Exciter Coolers............................................... 2.4-4940 Introduction........................................................ 2.9-0060
Ground Fault Detection System...................... 2.4-4990 Symbols for Supply Circuit and
Supervisory Equipment............................. 2.9-0210
Inspection Electrical Tests on Stator Winding
Introduction.................................................... 2.5-0010 with Vaccum Impregnated
Determination of Dewpoint Temperature....... 2.5-0019 Micalastlc High Voltage Insulation........................ 2.9-2300
Packing, Transport and Storage
pf Generator Rotors.............................. 2.5-0030
Preventive Measures for Transport and
Storage of Generator Rotors(Summary) 2.5-0031
Checking Desiccant Inpacking of
Components.......................................... 2.5-0032
Insulation Resistance Measurements
on Rotor and Exciter Windings...................... 2.5-0033
Preparation of Machinery Parts.................... 2.5-0200
Checking the Bearing and Seal Insulation...... 2.5-0300
Leakage Tests............................................. 2.5-0310
Flushing the Oil Piping.................................... 2.5-0320
Measures to Prevent Corrosion
During Inspections......................................... 2.5-1003
2.0-0010-7500/3
Turbogenerators Preface
General
The Turbogenerator set has been designed and manufactured to meet the contract
commitment as regards to the capability for the continuous operation or variable
load operation below maximum continuous rating with an aim to achieve to
objective of securing long life and trouble free operation.
Because of the margin provided in the design it may be possible to operate the
turbogenerator at overloads for the time specified in the manual. However, such
operations although possible for the short time will encroach upon the design
margin built into the generator.
BHEL reserves the right of changing the operation and maintenance instructions
based on experience gained.
z Any personnel working on the generator and its 8. Shipment, Erection, Startup, Operation,
auxiliary systems must be familiarized with the Service and Shutdown
operating instructions and shift procedures and in
particular with the safety instructions and regulations 8.1 Shipment
before starting work. This particularly applies to The following safety instructions apply during
personnel such as maintenance personnel who do generator shipment
not work on the generator on a regular basis.
z Protective apparel and equipment must be used
where stipulated or required.
z Ensure that the relevant personnel understands all Danger:
safety instructions and warnings.
z Compliance with all safety instructions and warnings Suspended load. Falling loads may
must be ensured. cause injury to persons. Keep away.
z Any irregular events which occur during operation
must be reported directly, and the generator shut
down if necessary. Notice:
z Carefully check components for any damage. Notify z All mechanical and hydraulic components as well
manufacturer in writing of any damage. as the generator protection system must be checked
z Empty pockets before entering generator. Record with regard to function and settings.
all tools used in a list and check that tools have z Check insulation resistance of winding.
been completely removed from generator when z Check shaft voltages and currents.
finishing work. z Before excitation remove any moisture caused by
z Remove any foreign materials from the generator. temperature drops below the dewpoint using
z Check efficiency of bearing insulation. suitable methods (e.g. drying).
z Check shaft voltages and currents. z Record all operating data after allowing sufficient
time for steady-state conditions to be established.
8.3 Generator Startup z Prepare startup record.
The following safety instructions apply during
generator startup: 8.4 Operation
The following safety instructions apply during
generator operation:
Danger:
Generator startup. This may cause injury Waste products of any kind (e.g. lubricants) must be
to persons. When working on generator disposed of in compliance with the applicable waste
or auxiliary equipment ensure that this is disposal regulations.
electrically isolated and cannot
accidentally be reconnected. In case of 10. Special Hazards
single shaft combined cycle plants
activities at the rotor, the bearings or See below for safety instructions with regard to elec-
opening of the generator stator are only tric current, heat and noise.
accepted after the steam turbine has been
run down. 10.1 Electric Current
Ensure compliance with the following instructions:
Danger:
Danger:
Do not start turbine-generator set if work
is being carried out on or near the Electric current. The generator must be
generator. shut down immediately in the event of loss
of control voltage.
z Work may only be performed by qualified personnel.
z Ensure compliance with the maintenance and z Work on the electrical systems of the generator may
inspection intervals and the scope of work set forth only be performed by electrical engineers or by suit-
in the operating instructions. ably qualified personnel under the supervision of an
z Operating personnel must be notified before starting electrical engineer in compliance with the relevant
and maintenance, inspections or repair work. electrical engineering standards.
Appoint a suitably qualified supervisor. z Components which are undergoing maintenance
z Empty pockets before entering generator. Record or repairs must be isolated. Check that isolated parts
all tools used in a list and check that tools have are de-energized, then ground and short-circuit. Iso-
been completely removed from generator when late adjacent parts which are still energized.
finishing work. z Regularly check the electrical equipment of the gen-
z Remove any foreign materials from the generator. erator and immediately repair any defects.
z Establish cause of any deposits, abrasion, fretting
corrosion or discoloration and prevent reoccurrence. 10.2 Heat
8.6 Shutdown
The following safety instructions apply during
Danger:
generator shutdown:
Hot surface. May cause serious burns. Do
not touch.
Danger:
10.3 Noise
Rotating components. These may cause
injury to persons. Ensure that rotor has
coasted down. Do not remove any guards Danger:
until generator has come to a full standstill.
Operating noise of generator may dam-
z Perform and record the requisite checks during and age hearing. Wear ear plugs when in the
following generator shutdown. vicinity of the generator.
z Prepare shutdown report.
z For long shutdown periods, electrically isolate the The generator may produce noise levels of approx.
generator. 90 dB(A) depending on model and type. In the long term
z Take appropriate measures to protect and preserve such noise levels may result in damage to hearing.
generator during shutdown.
Turbogenerator
1. Rotor Shaft fiber fabric with Nomex filler are used for slot insulation.
The slot wedges are made of high-conductivity material
The rotor shaft is a single-piece solid forging and thus act as damper winding. At their ends the slot
manufactured from a vacuum casting. Slots for insertion wedges are ‘short-circuited through the retaining rings.
of the field winding are milled into the rotor body. The
longitudinal slots are distributed over the circumference
so that two solid poles are obtained. 3. Rotor Retaining Rings
To ensure that only high-quality forgings are used,
strength tests, material analysis, and ultrasonic tests are The centrifugal forces of the rotor end windings are
performed during manufacture of the rotor. contained by single-piece rotor retaining rings. The
After completion, the rotor is balanced in various retaining rings are made of non-magnetic high-strength
planes at different speeds and then subjected to an steel in order to reduce stray losses. Each retaining ring
overspeed test at 120% of rated speed for two minutes. with its shrink-fitted insert ring is shrunk onto the rotor
body in an overhung position. The retaining ring is
secured in the axial position by a snap ring.
The hydrogen cooler is a shell and tube type heat All parallel-connected water paths must have equal
exchanger which cools the hydrogen gas in the generator. flow resistances to ensure a uniform cooling water supply
The heat removed from the hydrogen Is dissipated to the cooler sections and equal cold gas temperatures
through the cooling water. The cooling water flows downstream of the individual sections. The required
through the tubes, while the hydrogen is passed around cooling water volume flow is adjusted by control valves
the finned tubes. on the hot water side. Controlling the cooling water
The hydrogen cooler is subdivided into sections which volume flow on the outlet side ensures an uninterrupted
are horizontally mounted In the stator frame. water flow through the cooler sections so that proper
At the turbine end, the water connections are brought cooler performance will not be impaired.
out from the stator frame through gland-type seals To maintain the cold gas temperature at an
allowing for free movement. At the exciter end, the cooler approximately constant level under all operating
tubesheet is solidly bolted to the stator frame. conditions, a motor-operated control valve is arranged
The cooler sections are parallel-connected on their in the common cooling waler outlet line. This control valve
water sides. Shutoff valves are Installed in the lines is activated by temperature transmitters located upstream
upstream of the cooler sections. and downstream of the cooler sections.
1. Bearings
The points where the rotor shaft passes through maintained at a higher level than the gas pressure
the stator casing are provided with a radial seal ring. within the generator casing. The oil drained on the
The seal ring is guided in the seal ring carrier which hydrogen and air sides of the seal rings is returned
is bolted to the seal ring carrier flange and insulated to the seal oil system through drains in the stator
to prevent the flow of shaft currents. The seal ring is end shields. In the seal oil system the oil is
lined with babbitt on the shaft journal side. The gap regenerated by a vacuum treatment and then
between the seal ring and the shaft is sealed with returned to the shaft seals.
seal oil. The seal oil is supplied to the sealing gap On the air side, pressure oil is supplied laterally
from the seal ring chamber via radial bores and an to the seal ring via an annular groove. This ensures
annular groove in the seal ring. To ensure effective free axial movement of the seal ring.
sealing, the seal oil pressure in the annular gap is
1 Construction of the Seal Oil System A vacuum pump keeps the seal oil in the seal oil
tank under vacuum and largely extracts the gas absorbed
The shaft seals are supplied with seal oil from the
by the oil while passing through the hydrogen and air
seal oil system which consists of the following principal
atmospheres. A deterioration of the hydrogen purity in
components:
the generator is thus largely avoided.
Seal oil storage tank (in bearing oil drain line)
Seal oil tank incl. vacuum pump
2.3 Seal Oil Pumps
Intermediate oil tank
Two seal oil pumps are directly connected to the
Seal oil pumps (2 x 100%)
seal oil tank on their suction sides.
Standby seal oil pump (1 x 100%)
One of the two seal oil pumps is always in operation
Pressure controller downstream of each pump
while the second one remains activated for starting. If
Seal oil coolers (2 x 100%)
neither of the two pumps can establish the specified seal
Seal oil filters (2 x 100 %)
oil pressure, the standby seal oil pump is automatically
Differential pressure control valves (2 x 100%)
started. It is directly connected to the seal oil storage
Except for the seal oil storage tank, all the above
tank.
major components are combined in one unit.
The seal oil pressure downstream of each full-capacity
seal oil pump is maintained constant by one pressure
2 Seal Oil Circuit controller each while the respective pump is in service.
The seal oil is drawn from the seal oil tank by the
seal oil pump in service and passed to the shaft seals 2.4 Seal Oil Pressure Regulation
via coolers, filters and differential pressure regulating The seal oil pressure required upstream of the shaft
valve. seals is controlled by the differential pressure control
valve according to the preset value, i.e., the specified
difference between the seal oil pressure and the hydrogen
2.1 Seal Oil Storage Tank pressure.
The seal oil storage tank is a larger-diameter pipe For reasons of availability, two differential pressure
section in the bearing oil return line of the generator. After control valves with graded settings are provided.
the bearing oil supply system has been taken into
operation, the seal oil storage tank will always be partly
filled, which ensures continuous operation of the seal oil 3. Seal Oil Drain
system. The seal oil storage tank and the seal oil tank
are interconnected by piping. 3.1 Hydrogen Side Seal Oil Drain
The exhauster of the waste gas system maintains a The seal oil drained from the hydrogen side is passed
slight vacuum in the seal oil storage tank. to the intermediate oil tank via the generator
prechambers. The intermediate oil tank acts as a gas
barrier. A float-operated valve in the drain line keeps the
2.2 Seal Oil Tank oil level in the Intermediate oil tank at a predetermined
The seal oil tank is arranged below the seal oil level, thus preventing gas from entering the oil drain
storage tank. The oil from the seal oil storage tank is system. During normal operation, the float-operated valve
available at oil column pressure upstream of the float- remains continuously activated to return the hydrogen
operated valve in the seal oil tank inlet. side seal oil to the seal oil circuit. The seal oil leaving the
The float-operated valve in the inlet pipe keeps the intermediate oil tank is admitted into the seal oil tank by
oil level in the seal oil tank at a predetermined level and the action of the vacuum maintained in the seal oil tank.
compensates for a low oil level in the tank by admitting
oil from the seal oil storage tank and the intermediate oil
tank. During normal operation, the float-operated valve 3.2 Air Side Seal Oil Drain
remains continuously activated to admit the volume of The seal oil drained from the air side of the shaft
oil drawn by the seal oil pump in service. seals flows directly into the bearing oil return line for being
returned to the seal oil storage tank.
1. General is eight times higher than that of air. For more effective
coolIng, the hydrogen in the generator is pressurized.
The gas system contains all equipment necessary
for filling the generator with CO2, hydrogen or air and
removal of these media, and for operation of the generator 3. Carbon Dioxide Supply (CO2)
filled with hydrogen.
The gas system consists of: As a precaution against explosive hydrogen-air
H2 supply mixtures, the generator must be filled with an inert gas
CO2 supply (CO2 prior to H2 filling and H2 removal.
Pressure reducers The generator must be filled with CO2 until it is
Pressure gauges positively ensured that no explosive mixture will form
Miscellaneous shutoff valves during the subsequent filling or emptying procedures.
Purity metering equipment
Gas dryer CO2 flash evaporator
Flowmeters 4. Compressed Air Supply
2. Hydrogen Supply (H2) To remove the CO2 from the generator, compressed
air must be admitted into the generator.
The heat losses arising in the generator are dissipated The compressed air must be clean and dry. For this
through hydrogen. The heat dissipating capacity of hydrogen reason, a compressed air filter is installed the filler line.
General
Job Name RAYALSEEMA TP, STAGE-3
Generator Type THRI 108/39
Excitation BRUSHLESS
Year of manufacture 2009
* CO2 quantities kept on stock must always be sufficient for removal of existing hydrogen filling.
All values are approximate.
Design Data
Design Data for seal oil cooler Units Materials and Pressure
2 Sections, 100% each
Oil Flow 12 M3/hr Materials :
Heat dissipating capacity 70 KW Tubes Admirality Brass
Tubesheet C-Steel
Oil inlet temperature 57.5 0
C
Water Channels C-Steel
Oil outlet temperature 45 0
C
Cooling Water Side pressure:
Oil Pressure drop (approximate) 0.7 bar Design pressure 12 Kg/cm2
Cooling water flow 130 m3/hr Test pressure 18 Kg/cm2
Maximum inlet water temperature 38 0
C Oil Side Pressure:
Water outlet temperature 38.5 0
C Design pressure 12 Kg/cm2
Test Pressure 18 Kg/cm2
Water Pressure drop (approximate) 3.5 MWC
Design Data for Exciter Air Cooler Units Materials and Pressure
2 Sections, 50% each
Air Flow 11 m 3 /s Materials :
Heat dissipating capacity 210 KW Fins Cu
Tubes 90/10 Cu Ni
Cold air temperature 43.5 0
C
Tubesheets C-Steel
Hot air temperature 60.1 0
C
Water Channels C-Steel
Air pressure drop 500 Pa
Cooling water flow 200 m3/hr Pressure:
Maximum inlet water temperature 38 0
C Design pressure 10 Kg/cm2
Water outlet temperature 39 0
C Test pressure 15 Kg/cm2
Water Pressure drop 4.5 MWC
1) stp=standard temperature and pressure, 00C and 1.013 bar, to DIN 1343
The gauge pressures and temperatures indicated are those at the inlets of the generator gas supply units.
After stacking of the stator core, the insulated guide The supporting rings are welded together to form a
bars are installed in the respective slots. The required cage. They transmit the mechanical forces to the outer
stiffness is obtained by welding supporting rings and the casing via welded springs.
pressure plates to the guide bars.
The complete core and winding assembly is pre- drains off the exposed areas of the stator core on heating
dried in a vacuum tank, evacuated and impregnated by without blocking any cooling air passages.
being immersed in epoxy resin. Numerous control measures are performed during
evacuation, impregnation and curing for quality
assurance of the various treatment steps.
Prior to installation of the core and winding assembly
in the outer casing, a dissipation factor measurement of
each phase winding is performed, dependent on the
machine voltage and as stipulated in the applicable
national and International specifications.
A final dielectric test provides evidence of proper
impregnation and confirms the electrical quality of the
stator winding Insulation.
Fig.3 Winding Bars with green Insulation Fig 4. Bars layed in stator slots Fig.5 Preperation for
Impregnation
Fig.6 Impregnated Stator Fig.7 Impregnated Stator Winding Fig 8. Impregnated Stator Winding,
Winding after curing in the oven ready for insertion in Stator Body
Following manufacturing, the empty stator frame with The bolted flange joints which must be gastight (e.g.,
attached cooler header, end shields and terminal box is end shields) are sealed with a plastic sealing compound.
subjected to a hydraulic test at 10 bar to ensure that it will On completion of the assembly of each component, the
be capable of withstanding maximum explosion pressures. sealing compound is injected into the respective
The water pressure is increased in steps, with the pres- grooves.
sure being reduced to atmospheric pressure after each step Round flanges (e.g., manhole covers, bushings.
to allow for measurement of any permanent deformations. terminal box) are sealed with O-ring packings.
This test also checks for leakage at the weld seams.
In addition, the welded structure is subjected to an air Gastight sealing of the flanged connection between
pressure test to check its gastightness. the cooler assembly and the rotor frame is achieved by
field welding.
1 2 3
1. Nipple
2. Press
3. End Shield
1. Stator frame
2. Stator foot
3. Foundation
4. Anchor bolt
5. Gravel
In order to minimize the hysteresis and eddy-current The stepped arrangement of the laminations at the
losses of the rotating magnetic flux, which interacts with core ends provides for an efficient support of the tooth
the core, the entire core is built up of thin laminations. portion and, in addition, contributes to a reduction of eddy-
Each lamination layer is made up from a number of indi- current losses and local heating in this area. The clamp-
vidual segments. ing fingers are made of non-magnetic steel to avoid eddy-
current losses.
The segments are punched in one operation from After compression and clamping of the core, the core
0.65 mm (0.0256in.) thick electrical sheet-steel lamina- key bars are inserted into the slots provided in the back
tions having a high silicon content, carefully deburred of the core and welded to the pressure plates.
and then coated with insulating varnish on both sides.
1 2 3 4
1 6 5
Fig.1 Grounding of Stator Core
Note: The figure does not correspond to the condition as installed. The stotted core beam with the cu-rope was turned
by 1800 for the figure.
Fig.2 Solid Model of Stator Core showing the arrangement of Support Rings and Flat springs
1. General, Connection strands due to the slot crossfield and end winding flux
The three-phase stator winding is a fractional-pitch leakage and ensures that minimum circulating currents
two layer type consisting of individual bars. Each stator exist. The current flowing through the conductor is thus
slot accommodates two bars. uniformly distributed over the entire bar cross-section so
that the current-dependent losses are reduced.
At the Roebel crossover points, the insulation is rein-
forced with insulating strip inserts.
Tp = pole pitch 1 2
Fig. 1 Lap Type Winding Fig.2 Stator Bar
1. Strand
The slot bottom bars and top bars are displaced 2. Crossover insulation
from each other by one winding pitch and connected at
their ends to form coil groups. To ensure that the strands are firmly bonded
The coil groups are connected together with phase together and to give dimensional stability in the slot
connectors inside the stator frame as shown in the portion, the bars are cured in an electrically heated press.
connection diagram. Prior to applying the bar insulation, the bar ends are
This arrangement and the shape of the bars at the bent with a special device which shapes the involutes
ends result in a cone-shaped winding having particularly over a cone shell. This ensures a uniform spacing of the
favorable characteristics both in respect of its electrical bars over the entire length of the end turns after
properties and resistance to magnetically induced forces. installation.
The bars afford maximum operating reliability, since each In the course of manufacture, the bars are subjected to
coil consists of only one turn. This makes the turn numerous electrical tests for quality control.
insulation and the main insulation identical.
2. High-Voltage Insulation
2. Conductor Construction
The high-voltage insulation is provided according
The bar consists of a large number of separately
to the proven Micalastlc system. With this insulation
insulated strands which are transposed to reduce the
system, several half-overlapped continuous layers of dry
skin effect losses.
mica/glass fabric tape are applied from end to end on
The strands of small rectangular cross-section are
the stator bars. The tape is a composite tape built up
provided with a braided glass fiber insulation and arranged
from a thin, high-strength backing material to which the
side by side over the slot width. The individual layers are
mica is bonded by a small amount of epoxy as an
insulated from each other by a vertical separator. In the
adhesive for further processing.
straightslot portion the strands are transposed by 3600.
The bent bar ends are then provided with a final
The transposition provides for a mutual
protective wrapping of highly flexible glass fabric tapes
neutralization of the voltages induced in the individual
in order to obtain a smooth surface.
High-quality mica, selected epoxy resins and a This high-quality insulation system is the result of
matching vacuum impregnation process are the systematic development. Its reliability is assured by
characteristic features of the Micalastic insulation for large continuous quality control throughout the manufacturing
turbogenerators. process.
Bar Manufacture system which ensures uniform control of the electric field
The bars consisting of insulated strands are without corona discharges.
consolidated to the required size and shape by applying The end turns are provided with an outer cover of
heat and pressure to resin-saturated filler layers in the highly flexible armoring tape in order to obtain a smooth
straight slot section and in the end winding areas. . surface.
The high voltage insulation consists of the
specified number of half-overlapped, continuous Winding Assembly
layers of dry mica tape applied from end to end on The pre-insulated and pre-shaped bars are
the stator bars. A semiconducting tape applied as a carefully placed into the slots of the stator core. In the
final wrapping in the slot section provides for a good end windings, dry glass fabric pads are inserted between
electrical contact with the grounded parts via the stator the coils as spacers, and the end turns are then lashed
core. Specially treated tapes are applied to the bar to each other and to the end winding support structure
portions just outside the slot to provide a corona grading with glass fabric
X= mean value
l l = 1 sigma scatterband
Fig. 7 Electrical Life of Full-Size Bars With
Mlcalastlc Insulation
Fig. 6 Dielectric Dissipation Factor of a Phase
Winding of a Post-Impregnated Fully Wound-Stator Mlcalastic has a long electrical life as determined on
for UN = 10.5 kV as a Function of the Voltage, hundreds of experimental bars and verified on numerous
Measured at RT fullsize bars.
Mlcalastic is a good conductor of heat by reason of
Guiding values for the dissipation factor and its rise its high mica content and the voidfree synthetic resin.
with the voltage are merely given in the KEMA Efficient heat transfer is particularly Important for dissi-
specifications. According to these specifications, the pation of the upper losses in machines that require thick
maximum value shall not exceed 0.04 at 20 % of rated insulation because of the high voltages and are not de-
voltage, and the rise shall not be greater than 0.006 per signed with direct cooled windings.
20 % of rated voltage up to 60 % of rated voltage and
0.008 per 20 % of rated voltage upto rated voltage.
Windings manufactured by the Mlcalastlc post-
impregnation process comply with these limits.
The higher rise of the dissipation factor as compared
to the limit values established for individual conductor
insulations using a guard electrode arrangement
results from the loss attributable to the voltage grading
material applied at the slot ends, A final dielectric
strength test performed at 105 % of the winding test
voltage (Up = 2 UN + 1 kV) serves to verify proper
impregnation and the electrical quality of the insulation
before the stator is installed in the outer frame.
Properties of Mlcalastic
The Micalastic post-impregnation process ensures a
mechanically firm bond between all winding components
and between the winding and the stator which is capable
of withstanding the various temperature rises occurring Fig. 8 Dielectric Dissipation Factor of a Phase Wind-
during operation. The Mlcalastlc system thus provides for ing of a Post-Impregnated Fully Wound Stator for UN
reliable insulation of the windings at all machine voltages. = 10.5 KV as a Function of Voltage and Temperature
®
Registered trade-mark.
To prevent potential differences and possible corona good electrical contact with the grounded stator frame
discharges between the insulation and the slot wall, the via the core.
bars are provided with an outer corona protection in the The semi-conductive end corona protection applied at the
slot section and with an end corona protection at the transitions from the slots to the end winding portions ensures
transitions from the slots to the end winding portions. uniform control of the electric field without corona discharges.
After application of the high-voltage insulation, a semi- The bent bar ends are then provided with a final wrapping
conductive polyester mat tape is applied to ensure a of highly flexible tapes in order to obtain a smooth surface.
1 2 3 1 2 3
The insulated bars are placed in the slots of the obtained. A small taper angle is used to keep the stray
stator core. All gaps and spaces, due to the design and losses to a minimum.
manufacturing, are filled with pads of glass fabric mat In the end winding areas, the involute-shaped indi-
capable of being impregnated. vidual bars are arranged in parallel and with uniform spac-
After installation of the bars, dc tests are performed to ing. To obtain a short-circuit-proof structure, the bars are
promptly identify and correct any weak points in the insulation. lashed to winding supports and one support ring over
In the slot section of the stator core, the bars are pads of glass fabric mat with glass fabric tapes capable
secured in position with slot wedges. Outside the slot of being impregnated.
section, the bars are shaped so that, with the winding Both the bottom bars and top bars thus form a cone-
placed in the slots, cone-shaped end windings are shaped layer each which ensures mutual support of the bars.
1 2 3 4 5 6 7
Fig.1 End Winding Support System
1 2 3
1. Core
2. Clamping Finger
3. Pressure Plate for core
4. Phase Connector
5. Terminal Bushing
The electrical connection between the top and bot- The phase connectors consist of flat copper sections,
tom bars is made by brazing. Before brazing, the bar the cross-section of which results in a low specific current
ends are attached to copper straps or sleeves. After braz- loading. The connections to the stator winding are of
ing, the bar ends and copper straps or sleeves form solid riveted and soldered type and are likewise wrapped with
conductive connections. dry micapaper/glass fabric tapes.
The coil connections are then wrapped with dry The phase connectors are firmly mounted on the
micapaper/glass fabric tapes applied half-overlapped. The winding support, using clamping pieces and glass fabric
thickness of the wrapper depends on the machine volt- tapes.
age. The gaps between the individual coil connections
being sufficiently large, no additional insulation is required.
1 2 3 4
5
1 2 3 4 5 6
The rotor shaft is forged from a vacuum cast steel Due to the non-uniform slot distribution on the cir-
ingot. Comprehensive tests ensure adherence to the cumference, different moments of inertia are obtained in
specified mechanical and magnetic properties as well as the main axes of the rotor. This in turn causes oscillating
a homogeneous forging. shaft deflections at twice the system frequency. To re-
The rotor consists of an electrically active portion and duce these vibrations, the deflections in the direction of
the two shaft ends. An integrally forged flange coupling the pole axis and the neutral axis are compensated by
to connect the rotor to the turbine is located outboard of transverse slotting of the poles.
the bearing. The rotor teeth at the ends of the rotor body are pro-
Approximately 60% of the rotor body circumference is vided with axial and radial ducts, enabling the cooling
provided with longitudinal slots which hold the field wind- gas to be discharged into the air gap for intensive cool-
ing. Slot pitch is selected so that the two solid poles are ing of the end windings.
displaced by 1800.
1.3 Insulation
2. Location of Parts In Rotor Winding Flg.1 Rotor End Winding With Fillers
Note:- The number of conductors shown does not necessary correspond to the number of conductors of the generator described.
1 Rotor body
2 Damper bar
3 Silver-plated rotor end wedge
4 Rotor winding
5 Retaining ring
6 Silver-plated shrink seat
7 Transverse slot in the pole area
8 Rotor wedge
Note:- The sketch must not in agreement with all design details of the actual generator.
The generator cooling gas is circulated by two axial- The moving blades of the fan have threaded roots for
flow fans located on the two shaft journals. To augment being screwed into the rotor shaft. The blades are drop
the cooling of the rotor winding, the pressure established forged from an aluminum alloy. Threaded root fastening
by the fan works in conjunction with the gas expelled from permits the blade angle to be changed. Each blade is
the discharge ports along the rotor. secured at its root with a threaded pin.
The hydrogen cooler is a shell-and-tube type heat The return water channel is bolted to the exciter-end
exchanger which cools the hydrogen gas in the generator. tubesheet over a flat gasket. This arrangement permits
The heat removed from the hydrogen is dissipated through the return water channel to be detached for cleaning, even
the cooling water. The cooling water flows through the when the generator is in operation and filled with
tubes, while the hydrogen is passed around the finned hydrogen.
tubes. The turbine-end tubesheet is sealed in the stator
The cooler is subdivided into sections which are housing but is freely movable and capable of following
horizontally mounted in the stator housing. the differential movements between stator and cooler due
The cooling water flows through the tubes to the different thermal expansions resulting from the
according to the cross flow counter-current principle as different materials and temperatures.
referred to the hydrogen flow. The water flows through Attached to the turbine-end tubesheet is the inlet/
the cooler in a horizontal direction. The cold cooling water outlet water channel with its cooling water inlet and outlet
flows to the return water channel on the cold gas side, pipes.
and the heated water is returned on the hot gas side. A seal cap is bolted to the stator housing over the
This cooling water flow passage is obtained through a inlet/outlet water channel. The seal cap has openings for
partition in the inlet/outlet water channel. bringing out the cooling water pipes. Gastight sealing is
Each cooler section consists of the tube bundle, done by gland type seals which are simultaneously
the two tubesheets, the return water channel, and the pressed against the outer circumference of the cooling
inlet/outlet water channel. To obtain a larger heat transfer water inlet/outlet pipes and against the sealing face of
surface, the tubes have copper fins which are metallically these seal gap by a compression ring. This sealing
joined to the tubes by tinning. The ends of the tubes are arrangement allows for free thermal expansion of the
expanded into the tube-sheets. cooler.
The two side walls of structural steel brace the The cooler sections are parallel-connected on their
cooler and direct the hydrogen flow. They are attached to water sides. Shutoff valves are installed in the lines
the tube sheets in a manner which permits them to move upstream and downstream of the cooler sections. The
freely to allow for expansion of the tube bundle. required cooling water volume flow depends on the
Flexible seal strips bolted to the side walls seal the generator output and is adjusted by a control valve on
gaps between the cooler section and the cooler wall, thus the heated water side. Controlling the cooling water
preventing uncooled hydrogen from flowing past the cooler volume flow on the outlet side ensures an uninterrupted
section. water flow through the cooler sections so that proper
The exciter-end tubesheet is larger than the cooler performance will not be impaired.
wall opening and is bolted to the stator housing. Gastight
sealing of this tubesheet is done by a packing.
1 2
II
3
The rotor shaft is supported in sleeve bearings having upper half of the stator end shield. The locator should be
forced-oil lubrication. The bearings are located in the adjusted to maintain a clearance of 0.2 mm between the
stator end shields. The oil required for bearing lubrication bearing sleeve and the insulation of the radial locator.
and cooling is obtained from the turbine oil supply system A stop is provided at the bearing sleeve joint to
and supplied to the lubricating gap via pipes permanently prevent the bearing from turning in the saddle.
installed inside the lower half of the stator end shield and The inner surface of the cast bearing sleeve body is
via grooves in the bearing saddle and lower bearing provided with spiral dovetail grooves which firmly hold
sleeve. the babbitt liner to the bearing sleeve body. The lower
The lower bearing sleeve with its self-aligning outer bearing sleeve has a groove to admit the bearing oil to
portion rests on the bearing saddle. The bearing saddle the bearing surface. The upper sleeve consists of an
is insulated from the stator end shield to prevent the flow overflow groove through which the oil flows over the shaft
of shaft currents and provide for insulation of the generator journals and is fed to the lubricating gap. The oil is drained
bearing from ground. The radial locator serves to locate laterally from the lubricating gap, caught by wipers,
the bearing in the vertical direction and is bolted to the collected in the bearing compartment and returned to the
1. Overflow groove
2. Babbitt
3. Stop
1. Connection for bearing vapor exhauster 11. Connection for shaft lift oil
2. End shield, upper half 12. Bearing oil inlet
3. Radial bearing locator 13. Hex plug
4. Upper bearing sleeve 14. Bearing oil drain
5. Tangential bearing locator 15. Connection for level detector
6. Rotor shaft 16. Connection for seal oil inlet
7. Shaft lift oil system 17. Connection for ring relief
8. Bearing saddle 18. Drain for air side seal oil
9. Bearing insulation 19. Drain for H2 side seal oil
10. End shield, lower half * Joint
The rotor shaft ends are brought out of the gastight annular groove of the seal ring via passages in the seal
enclosure through shaft seals as shown on the attached ring carrier and seal ring. A continuous film of oil is
drawing. (See also 2.1.4-10610, Shaft Seal- Drawing.) maintained between the shaft and the seal ring. The
With this type of shaft seal, the escape of hydrogen clearance between shaft and seal ring is such that friction
between the rotating shaft and the housing is prevented losses are minimized and an oil film of sufficient
by maintaining a continuous film of oil between the shaft thickness is maintained without an unnecessarily large
and a non-rotating floating seal ring. To accomplish this, oil flow. Temperature rise of the seal oil is therefore small
seal oil is fed to the seal ring in a closed circuit at a which contributes to reliable sealing. The babbitt lining
pressure which is slightly higher than the hydrogen of the seal ring ensures high reliability even in the event
pressure. In addition, the air side seal ring is supplied of mixed friction.
with jacking oil to assure free axial movement. The seal oil pump delivers the oil at a pressure
The shaft seal is characterized by its short axial maintained 0.7 to 1.0 bar above the generator hydrogen
length, its independence from the-respective axial and gas pressure at the shaft seal by means of a differential
radial position of the shaft and an oil supply circuit with pressure valve.
facilities for continuous vacuum treatment of the oil. More Higher pressure oil for ring relief is fed to the annular
details are given in a separate description. (See also groove in the air side seal ring carrier and forced between
2.1.4-44000, Description of Seal Oil System.) the seal ring and the seal ring carrier. In this way the oil
The two halves of the babbitted seal ring float on the and gas pressures acting on the seal ring are balanced,
shaft journal with a small clearance and are guided in and the friction between seal ring and seal ring carrier is
axial direction by a divided seal ring carrier resistant to reduced. The seal ring is thus free to adjust its radial
distortion and bending. The seal ring is relatively free to position, which is important during the starting period.
move in the radial direction, but is restrained from rotating The seal ring will adjust its position according to the
by use of a pin. The seal ring carrier, bolted to the end shaft position as dictated by the oil film thickness and
shield, is insulated to prevent the flow of shaft currents. the vibratory condition.
The oil is supplied to the shaft seal at two different The seal ring need not follow the axial movement of
pressures (seal oil pressure and higher pressure oil for the generator shaft, which is primarily caused by the
ring relief) through the mounting flange of the seal ring turbine expansion. The design permits the shaft to slide
carrier at the end shield. The seal oil is admitted into the through the seal ring without impairing the sealing effect.
MKW01 AA151 Gate valve between SEAL Oil Storage Tank and Vacuum Tank
MKW01 AA201 Seal Oil Storage Tank drain
MKW01 AA211 U-loop drain after Seal Oil Storage tank
MKW01 BB001 Seal Oil Storage Tank (SOST)
MKW01 CL001 Level switch at SOST
MKW11 AA001 Constant Pressure Regulator after AC Seal Oil Pump (SOP) 1
MKW11 AA031 Safety valve at AC Seal Oil Pump 1
MKW11 AA051 Non return shut off valve after AC Seal Oil Pump 1
MKW11 AA101 Gate valve at inlet of AC Seal Oil Pump 1
MKW11 AA181 Gate valve after constant pr. regulator (CPR) 1
MKW11 AA185 Bypass valve to seal oil system
Mode of Operation
The oil flows through the regulator in the direction of the actuating diaphragm via a bore in the cone. The
the arrow. The flow rate depends on the cross-sectional actuating diaghragm converts the differential pressure
areas adjusted by the orifice and the cone. For flow produced by the orifice into an actuating force which in
regulation, the pressure before the orifice is transmitted turn adjusts the cone. The pressure drop across the
to the high-pressure side of the actuating diaphragm and regulator is constant and nearly independent of the
the pressure after the orifice to the low-pressure side of pressure before the orifice. This ensures a constant
volumetric flow rate for seal ring relief under all conditions
of operation.
1. General
Oil lubricated radial seals at the rotor shaft ends 2. Construction and Mode of Operation
prevent the hydrogen gas from escaping from the The seal oil pumps are three-screw pumps. One
generator to the atmosphere. double-thread driving rotor and two driven idler screws
Seal oil pumps are used to supply the seal oil to are closely, meshed and run with a close clearance in
the shaft seals in a closed circuit. the casing insert. The pump casing accommodates the
casing insert and is closed off by covers at the drive end
and non drive end.
The screw pump is suitable for rigorous service and,
due to the absence of control parts sensitive to dirt, allows
for relatively large variations of seal oil viscosity.
High speeds are readily attainable because all
moving parts perform rotary movements only.
The main components of the pump are illustrated
in the sectional view of a screw pump.
By intermeshing, the helical passages in the rotors
are divided into compartments completely sealed which,
while rotating progress completely uniformly and without
undue stressing from the suction to the discharge end,
thus acting like a piston. Dummy pistons compensate
for the axial thrust on the thread flank faces at the
discharge end. Axial thrust on the deep-groove ball
bearing is thus eliminated.
1. Idler screw The idler screws are hydraulically driven due to
2 Driving rotor suitable screw dimensioning. The thread flanks transmit
3. Dummy piston
only the torque resulting from fluid friction. which ensures
4. Shaft seal (sliding ring gland)
very quiet running.
The screw pumps are driven by electric motors
Fig.1 Screw Pump With Relief Valve through a coupling. The motor speed and rating are
matched to the expected delivery flow and heads.
1. Seal Oil Coolers sealed with viton ‘O’ Ring. The Iower tube plate is held
The seal oil coolers are multiple-pass heat ex- between the lower water box. Drain and vent plugs are
changers with bare tubes. The seal oil circulates through provided on upper & lower water box to facilitate draining
the coolers outside of the tubes with shell baffles of water/oil.
directing the fluid in crossflow. The cooling water flows
through the tubes. 2. Seal Oil Filters
The cooler consists of the cooler shell the upper and
lower water boxes and the tube bundle with integral inner The seal oil filters are of magnetic strainer type, the
casing with the upper and lower tube sheets. The inner magnetic strainer consists of the filter housing with a
casing ensure perfect sealing with baffles and prevents filtering cage and the filter cover.
oil by-passing. The filtering cage consists of fine-mesh wire cloth
The cooling water inlet and outlet flanges and an with support strainers on both sides and the magnet bars.
opening for cooler cleaning are located at the lower water The seal oil entering the filter must first passes through
box. The seal oil inlet and outlet flanges are located on the magnetic field set up by the magnet bars so that aII
the cooler shell. The lower tube sheet is stationary and iron particles contained in the seal oil are attracted by
fixed in position between the lower water box and the the magnet bars. The seal oil then flows through the fine-
cooler shell. mesh wire cloth which retains all dirt particles containing
The upper tube sheet is a floating type and no iron.
General
time constant and so precisely that the preselected
The MR 16 diaphragm pressure regulator is an
control pressure is kept constant with an inaccuracy of
absolute pressure controller by means of which the
only approximately 2%.
pumping speed of vacuum pumps can be matched
automatically and without input of energy to the gas
The instrument is equipped with all valves and
accumulation in the vacuum system.
Connections required to enable easy adjustment and
control of reference pressure and system pressure under
This regulation is achieved with an extremely low
varying operating conditions.
time constant and so precisely that the preselected control
1. General
The gas system consists of the following and low pressure side protects the pipe system against
components: inadmissible high pressure.
CO2 Distributor
H2 Distributor 4. Compressed Air Supply
Gas dryer To remove the CO 2 from the generator, a com-
Gas Unit pressed air supply with compressed air filter is connected
The design of the gas system complies with the to the compressed air system of the power plant.
safety regulations according to DIN VDE 0530, Para 3 Under all operating conditions, except for CO2 purging,
and with the German pressure vessel code. the compressed air hose between the filter and the
generator pipe system should be disconnected. This
2. Hydrogen Supply visible break Is to ensure that no air can be admitted into
The hydrogen for the generator is supplied from a hydrogen filled generator.
the Hydrogen Distributor. The hydrogen should have a
minimum purity of > 99.9% v/v. 5. H2 Supply System
MKG10 AA111 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA112 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA113 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA114 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA115 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA116 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA117 Gas valve between hydrogen cylinders and gas manifold
MKG10 AA118 Gas valve between hydrogen cylinders and gas manifold
MKG10 CP001 Pressure transmitter on hydrogen gas manifold
MKG10 CP501 Pressure gauge on hydrogen gas manifold
MKG12 AA121 Gas valve at inlet of first stage hydrogen pressure regulator 2
MKG12 AA151 Gas valve at outlet of first stage hydrogen pressure regulator 2
MKG15 AA121 Gas valve at inlet of second stage hydrogen pressure regulator 1
MKG15 AA151 3-way valve at outlet of second stage pressure regulator
MKG15 BY001 Second stage hydrogen pressure regulator 1
MKG16 AA121 Gas valve at inlet of second stage hydrogen pressure regulator 2
MKG25 AA021 Gas valve between generator and gas analyser cabinet
MKG25 AA022 Gas valve between generator and gas analyser cabinet
MKG31 AA101 Isolating valve for cylinder hydrogen/ carbon dioxide gas to
gas analyzer
MKG31 CQ001 Gas Analyser
MKG35 AA381 Isolating valve at generator for gas from Gas Analyser.
MKG70 AA111 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA112 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA113 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA114 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA115 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA116 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA117 Gas valve between carbon dioxide cylinders and manifold
MKG70 AA118 Gas valve between carbon dioxide cylinders and manifold
MKG91 AA101 Air inlet valve before water and oil trap
MKG91 AA105 Air inlet valve after water and oil trap
MKG91 AT001 Water and oil trap
1 General heat transfer to the copper pipe coil and thus to the
CO2 is used to displace air from the generator CO2 flowing through the pipe coil.
before hydrogen filling and to displace hydrogen from The heat transmitting liquid is filled into the CO2
the generator before filling the generator with air. vapourisor through the expansion vessel mounted on
Since the CO2 is available in the liquid state, it top of the housing. For protection against excessive
must be expanded into a gas before use. The CO2 is heating, a thermostat maintaining a constant
expanded in a CO2 vapourisor. temperature is arranged in the housing holding the
heat transmitting liquid. For protection against
2 Design features and mode of operation
excessive pressures in the CO2 line, one relief valve is
The CO 2 vapourisor consists of a tubular
housing closed by flanges at both ends. One arranged before and after the CO2 vapourisor.
flange carries electrical heating elements, which are The orifice at the CO2 outlet of the expansion
connected to terminals in the terminal box mounted vessel provides for an expansion of the CO2 obtained
external to the flange. The opposite flange contains from the bottles from a pressure of 25 to 7 psig.
the inlet and outlet to the cooled copper pipe Heating of the CO2 in the copper pipe coil is sufficient
of the evaporator. The horizontally arranged housing is to prevent icing of the expansion device at the prevailing
filled with a heat transmitting liquid to ensure a better flow velocities.
1. Activation 2. Deactivation
The heater of the CO2 flash evaporator is switched The heater of the CO2 flash evaporator is switched
on by setting the switch to the On position. off by setting the switch to the Off position.
The temperature of the heat transfer liquid in the
CO2 flash evaporator is controlled by the thermostat. 2.1 Conditions for Switching Off
which is designed as an on-off controller to maintain Switch in position Off
proper temperature. and
temperature of CO2 flash evaporator heater MKG71
1.1 Conditions for Switching On CTOO1 > set value.
Switch in position On
and
temperature of CO2 flash evaporator heater MKG71
CTOO1 < set value.
MKG71 CT001 < set value
1.0 Introduction a gas to gas heat exchanger. The hot moist gas on the primary
The gas to be dried is passed through the drier side is cooled in advance through the dried and cold gas on the
and is cooled sufficiently to condense the moisture from secondary side. This heat exchanger is shell and tube type with
gaseous to liquid state with the help of Refrigeration cold gas passing through tubes.
system. The moisture is separated from the gas in the After the pre-cooling, the H2 gas passes through
form of water droplets and is collected in drain collec- the evaporator which is Freon to gas heat exchanger. In
tor. The dried gas is returned to the generator. The drier this way cooling takes place at constant pressure dew
also condenses any oil vapours present in the hydro- point up to 2-3° C. The evaporator is again a shell and
gen gas. tube type heat exchanger in which refrigerant from con-
denser passes through copper tubes and precooled
2.0 Technical Data : H2 gas surrounding the tubes. This way heat from H2
a)Capacity : 40 m3 / hr gas is taken way by liquid circulating through tubes.
b)Inlet temperature : 60 ° C max . The H2 gas sheds excess moisture, which is col-
c)Inlet pressure (Design) : 4 kg/ cm2 (g) max lected in the condensate chamber. The cold dry H2 gas
d)Outlet gas dew point : + 3 ° C to + 5 ° C is passed through pre-cooler where it is heated to about
e)Refrigerant : Freon 22 8-10° C below the inlet gas temperature and is finally
f)Compressor capacity : 3225 Kcal / hr led to the generator.
g)Power supply : 230 V AC. 1 phase The condensate chamber is provided with a sight
h)Inlet / Outlet flange : Nb 50 NP 10 glass. The water from the condensate chamber shall
Connections be manually drained. The gaseous Freon leaving evapo-
i)Unit size ( Lx BxH ) : ~ 1100 x 900 x 1620 rator is compressed by a hermetically sealed compres-
j)Unit weight : 400 kg (approx.) sor and cooled in the condenser. The compressor,
therefore, provides the required cooling power.
3.0 Main Components:
The dryer comprises of the following main 6.0 Instrumentation
components: For monitoring the performance of the dryer, following
• Hermetically scaled compressor instruments are provided on the front panel of the dryer:·
• Condenser
• Shell / tube type evaporator (Freon to H2 heat • Temperature gauge at H2 gas inlet to dryer
exchanger) • Temperature gauge at H2 gas outlet from dryer
• Fan for condenser • Evaporator gas temperature indicator
• Pre- cooler (Gas to gas heat exchanger )
• Condensate chamber The setting of the Digital temperature controller
shall decide the pressure dew Point of dried H2 gas.
4.0 Special Constructional Features The compressor shall be cut off automatically when
Designed to ensure very low pressure drop in the primary the gas is cooled to 2-3°C in the evaporator and shall
Gas Circuit of the order of 8mm water column. restart at about 6-7°C which is the reset temperature.
Electrical equipment and Hydrogen containing equipment All the gauges, controls and lamp indications are
are isolated through a physical barrier for ensuring safety. The provided on the front panel of the dryer for ease of
electrical equipment is housed in the bottom portion and equip- operation.The electrical items of the dryer are housed
ment containing hydrogen gas including piping are housed in the in the bottom part of the dryer and Hydrogen circuit is
top portion. Any H2 gas leakage gets vented out from the top housed in the upper part with a separator in between.
ventilating holes. The drier can be programmed to The top portion is provided with vent outlet. The dryer
shall be mounted on a fixed foundation and connected
run automatically for a chosen cycle of - On Time - Off Time.
across turbine end generator fan.
Modular Construction: Major components of the refrig-
eration circuit ( electrical circuit ) can be taken out and replaced
7.0 General Arrangement and Installation
in situ.
All butt welds are 100% radiographed. The electrical items of the dryer are housed in
Incorporation of a precooler to increase efficiency as well the bottom part of the dryer and Hydrogen circuit is
as to increase the temperature of outgoing gas from chiller to housed in the upper part with a separator in between.
generator to avoid thermal jerks. The top portion is provided with vent outlet. The dryer
shall be mounted on a fixed foundation and connected
5.0 Description across turbine end generator fan.
Moist Hydrogen from the generator is first passed through
Due to load variations during operation and the The resulting deviation is fed back to the controller which
resulting thermal expansions and contractions. the actuates the cooling water control valve with its output
generator is subjected to stresses. signals.
In order to reduce these stresses. the hydrogen To improve the quality of control, the hot gas
cooling circuit is provided with a temperature control temperature is additionally fed to the controller as
system to control the hydrogen cooling gas temperature vanishing pulse. Fast-rate load changes are thus detected
so that the active generator components are maintained and evaluated at an early stage
at the proper temperature level. The cooling water supply to the hydrogen coolers is
The requirements for the temperature control system opened already during startup of the unit when the
are described below: temperature of the hydrogen cooling gas has risen due
to the windage losses at the gas.
In order to maintain a low temperature level In the
ϑ cold = Cold gas temperature generator, the reference of the cold gas temperature (26-
ϑ hot = Hot gas temperature 50°C) should be set at the lowest possible value
dependent on the cooling water temperature, ensuring
Δϑ = ϑhot - ϑcold with generator carrying full load that the cold gas temperature will not drop below the
minimum level of 10°C during startup. .
The temperature rise Δϑ at full load is the temperature Parallel shifting of the curves shown in Fig. 1 is
difference between the hot and cold hydrogen cooling possible by adjustment of the cold gas reference.
gas as given in the hydrogen cooler design data. The control valve must be absolutely tight when in
The hydrogen cooling gas temperature control the closed position to ensure that the cooling gas
system controls the cold gas temperature by throttling temperature will not drop while the generator is being
the cooling water flow on the hydrogen cooler outlet side shut down.
so that a constant cold gas temperature is maintained For details on the operation and technical features
over the entira load range. of this equipment, see equipment supplier’s operating
The cold gas temperature is measured directly after instructions.
the hydrogen cooler and fed to the PI controller as The required temperatures for setting the cooling
controlled variable. In the controller. the controlled variable gas temperature control system are stated In Cooler Date
is compared with a constant reference set value. and Oparating Values.
+ -
SUM
2
S
6
40 O C
+ -
SUM
2
Adjustable 5-50O C
3
5
PI
1 4
Feedback 4-20 ma
H2 cooling gas
Actuator
M Motor
7
Cooling Water
Cold Gas Temperature Control valve
GENERATOR
2.1-8010-0007/2
Turbogenerators Control, Protection and Monitoring Devices
Description Safety Equipment for Hydrogen Operation
The use of hydrogen as coolant in the generator The loop is designed to withstand momentary pressure
calls for special safety equipment to ensure that surges.
hazardous operating conditions which, might endanger
personnel or the plant, will not occur. The bearing oil circuit and the seal oil circuit are
separated from each other. Via the ring relief a small
The safety and protective measures provided for the amount of oil is continuously admitted into the seal oil
generator are described in detail in this section. The circuit. The oil admitted is returned to the bearing oil
required measuring and alarm equipment is discussed circuit from the oil drained towards the air side. The return
elsewhere in this manual. oil is admitted to the seal oil storage tank.
During normal operation. leaks may develop which The measures outlined above have the following effects:
result in a continuous escape of hydrogen. Long-time z The bearing compartments and the oil drain pipe
experience has shown that no operational restrictions
are ventilated continuously so that no explosive
are required as long as the hydrogen losses do not
hazard will arise during normal operation.
exceed 18 m3 (s.t.p.)* during any 24-hour period. The z During normal operation, practically no hydrogen will
surroundings of the generator and the hydrogen supply enter the turbine lube oil tank via the loop seal
system should not be endangered if sound engineering together with the seal oil drained from the shaft
principles were followed in plant design and provision is seals, since the hydrogen is already extracted in the
made for ample ventilation of these areas so that the seal oil storage tank.
formation of localized hydrogen pockets or explosive z The isolating action of the loop seal prevents the
hydrogen-air mixtures is precluded. hydrogen escaping due to small leakages from
flowing into the turbine through the only partly filled
Particular precautions are taken with respect to a H2 oil drain pipe.
leak in the bearing compartment. A special vapor
exhauster creates a slight vacuum in the generator The seal oil storage tank is continuously vented via
bearing compartments to prevent the escape of oil vapor the vapor exhauster provided for the bearing
from the bearing compartments along the shaft. Any compartments. The exhauster creates a slight vacuum
hydrogen collecting in the bearing compartment will be in the seal oil storage tank so that the oil saturated with
drawn off by the exhauster and vented. hydrogen is degassed. After remaining in this tank for a
predetermined time, the degassed oil is returned to the
Operation of the exhauster is monitored by a turbine oil tank together with the bearing oil via a loop
pressure transmitter with limit switch. If the exhauster seal.
fails, the second exhauster on standby is automatically
started. This continuous ventilation of the seal oil storage tank
prevents the formation of any explosive hydrogen-air
To prevent the hydrogen which enters the bearing mixture.
compartment from escaping via the oil drain pipes, the
To avoid any danger to the unit due to the hydrogen supply,
drain oil is returned to the turbine oil tank via the seal oil
only two hydrogen bottles should be opened if the bottle
storage tank and a loop seal. This loop seal is
supply is used.
permanently filled with oil to prevent the escape of gas.
The Waste fluid system serves for controlled Any waste fluid collected is discharged to the waste
discharge of fluid to be drained from the fluid system either directly or via collecting vessels
that are integrated in the respective systems.
• seal oil system
• generator liquid level detection system In the waste fluid system, the fluid is collected in a
• waste gas system pipe section of large nominal size. This pipe section is
as a result of venting or minor leaks. fitted with a shutoff valve for fluid draining and a level
detector for activating a high level alarm. The fluid
In addition, the fluids to be drained for carrying out drained should be transferred to the waste oil tank of
repair or maintenance work in the above areas are the power station for controlled waste disposal.
discharged to the waste fluid system.
TT GCB FB A
TT = Turbine trip
GCB = Generator circuit breaker
FB = Field breaker
A = Alarm
Generators are high-quality machines for securing z A one-line-to-ground fault may develop to a double
the best possible continuity of power supply. In addition ground fault, resulting in dangerous magnetic
to a suitable technical design and responsible mode of unbalances, especially on four-pole generators.
operation, provision must therefore be made for automatic
To minimize the consequential damage, it is
protection facilities. This protection must ensure a fast
recommended to provide two-pole and four-pole
and selective detection of any faults in order to minimize
generators with a protection circuit featuring a delayed
their dangerous effects.
response. In the core of four-pole generators, the rotor
The protective equipment must be designed so that
ground fault protection must always operate to avoid the
any serious fault will result in an immediate disconnection
hazard of sudden, extremely high vibrations due to
and de-excitation of the generator. Faults which do not
magnetic unbalances.
cause any direct damage must be brought to the attention
of the operating staff, enabling them to operate the unit Relay time: approximately 1 s
outside the critical range or to take precautionary
measures for shutdown. 4. Underexcitation Protection
Generators may be endangered by short-circuits, Failure of the voltage regulator, maloperation of the
ground faults, overvoltages, underexcitation and generator or transformer control systems, and generator
excessive thermal stresses. operation in a system with capacitive load may result in
The following protective equipment is recommended: a reduction of the excitation required to ensure system
stability below a predetermined minimum value. Short-
1. Differential Protection circuits or interruptions in the field circuit result in a
Breakdown of insulation between different stator complete loss of field and thus in instability of the
phase windings results in an internal short-circuit The generator. This causes higher temperature rises in the
fault is ‘detected by a differential relay which initiates rotor and core end portions, rotor overvoltage, system
immediate isolation and de-excitation of the generator. swings and torsional vibrations of the shaft.
In order to obtain a hIgh sensitivity, the protected area A momentary excursion beyond the steady-state
should include the generator only. stability limit must not necessarily result in a loss of
stability. Therefore it is advisable to design the
Operating value: 0,2 ... 0,4 /N
underexcitation protection so that a warning will be given
Relay time: < 60 ms when the steady-state stability limit is reached. The
In certain cases, the generator may also be included generator will be shut down after a few seconds only.
In the differential protection for the main transformer and The protection must operate instantaneously if a loss
station service feeder. Generator faults are then detected of field occurs when the steady-state stability limit is
by two differential protection devices. reached.
If the loss of field cannot be detected directly (e.g.
exciters with rotating diodes), it is recommended to
2. Stator Ground Fault Protection introduce a second stator criterion covering the range of
the permeance values 1/xd and 1/X’d and to provide for
Breakdown of insulation between the stator winding
instantaneous tripping when this criterion is exceeded.
and frame results in a stator ground fault. If possible, the
stator ground fault protection should cover the complete
winding, including the neutral point of the generator. The 5. Overcurrent Protection
protection is to initiate immediate isolation and de- System faults may result in (inadmissible) thermal
excitation of the generator. . stressing of the generator. For this reason, an overcurrent
Relay time: < 1s protection should be provided which operates on failure
of the system protection.
The load resistance of a grounding transformer and
A definite-time delay overcurrent relay may be used
any required boost to raise the neutral point potential
for this purpose, however, its relay time should be longer
should be selected so that the ground current due to a
than that of the system protection.
fault will amount to less than 15 A.
Operating value: 1.3 IN
3. Rotor Ground Fault Protection Relay time: 6... 8 s maximum
To avoid long relay times, it is recommended to equip
Rapid fault detection is required for the following reasons:
large generators with an inverse-time-delay (impedance)
z An interruption of the field circuit with arcing releases relay. This relay is energized by overcurrent and operates
high amounts of energy in the form of heat which with long or short-time setting, dependent on the location
may cause severe burning. of the short circuit.
If connected to the generator neutral point, the At rated voltage, the generator can be continuously
overcurrent protection serves as back-up protection for operated at rated kVA up to 95 % of rated frequency.
the differential protection. To avoid excessive magnetic and thermal stressing,
it is recommended to provide an under-frequency
protection.
6. Load Unbalance Protection Since the frequency deviation due to a system
Generators operating in an interconnected system disturbance is normally accompanied by a voltage
are normally subjected to small load unbalances only. deviation. the protection should be designed on the basis
However, all one and two-line-to-ground faults occurring of the permissible load characteristic of the generator on
in the system, phase breakages or circuit breaker failures frequency and voltage deviations.
are in fact load unbalances which may result in unduly
high thermal stressing of the rotor. 9. Reverse Power Protection
It is recommended to provide a two-stage-Ioad
The reserve power protection system acts as standby
unbalance protection. When the continuously permissible
for the operational shutdown programme of the turbine I
load unbalance is reached, an alarm is given, whereas a
& C system which disconnects the generator from the
time dependent isolation from the system occurs when
grid. In addition, this system gets into action, if the tuboset
this value is exceeded.
runs at reserve power due to operation reasons, e.g. due
In case of Iarge units, it is recommended to provide
to increasing system frequencies.
a protection with unbalanced load time characteristic.
Continuous reserve power operation is allowed; it
Operating value and relay time should be matched to the
endangers neither the gas turbine nor the generator. The
load unbalance time characteristic applicable to the
generator should be disconnected from the grid, however,
particular generator.
after about 4 seconds to avoid taking the relatively large
motoring power of about 20 % generator rating from the
7. Rise-in-Voltage Protection system for an undue period of time.
Alarm is initiated when the electrical generator protection system is tripped. Individual alarms for each criterion are provided.
1. Brush holder
2. Grounding brush (Design A)
3. Grounding brush (Design B)
4. Brush Spindle
5. Insulation
6. Rotor shaft
7. Labyrinth ring
8. End shield
The supervisory equipment consists of alarms and devices are combinedto form one supervisory unit.
measuring devices. The measuring devices give visual
indication of the syatem parameters, the alarm devices Closely associated with the supervisory equipment
initiate visual or audible signals in the event of a controlled are regulating alarms, automatic controls and protective
quantity falling below or exceeding the predetermined devices which provide for a reduction of the manual
limit values. In many cases, the measuring and alarm supervisory work.
devices are
R = R0 • (1 + alpha • 7)
where
R0 = reference resistance at 0°C
alpha = temperature coefficient and
T = temperature in °C.
2. Thermocouples
Thermocouples are used for temperature
Fig. 1 Resistance Characteristic for measurements on the generator, e.g. to measure the
Platinum RTD’s 100 ohm at °C generator and exciter bearing temperatures.
Thermocouples are mainly employed where small time
1.1 Circuit Connections constants require fast temperature indication,
The two-wire connection, far commonly used,
involves errors in case of long leads. Long leads are 2.1 Principle
exposed to different temperatures, and the lead Temperature measurement with thermocouples is
resistances then reach values in the order of the carried out as follows:
resistance of the RTD element. Two conductors of dissimilar materials, i.e. the
positive and the negative conductor (thermoelectric
1.1.1 Three-Wire Connection elements), are joined at one end (hot junction) so as to
If a third lead is connected to the element in produce an electromotive force (emf), i.e., a
addition to the two element leads, automatic thermoelectric emf (in mV). The magnitude of the emf is
compensation for lead wire resistance including its dependent upon the temperature difference between
changes can be achieved by relatively simple means, the temperature to be measured and that of the other
the only prerequisite being that the resistance of the two ends of the conductors.
two leads forming the pair to the element are always
the same.
Cu-CuNi brown
Fe-CuNi blue
NlCr-Ni green
PtRh-Pt white
NiCr-Constantan red
The insulating sleeve of the positive lead is
provided with a red mark in addition to the color code
1. Hot junction 5 Connecting cables
2. Thermocouple 6 Millivoltmeter 2.3 Cold Junction
3. Compensation lead 7 Compensating resistotor For measuring a temperature by means of a
4 Cold junction correction thermocouple the cold junction temperature must be
known. A cold junction at a temperature of 0°C can
Fig. 3 Thermocouple be very earily produced oy melting ice. The use of
thermostats with reference junction tempera
To use the thermoelectric emf for temperature tures of 20°C and 50°C is also possible. Note that in
measurement, the free ends of the conductors are these cases certain corrections must be added to the
exposed to a constant temperature (cold junction calibration figures of the particular thermocouple
temperature) and connected to a millivoltmeter which are referred to 0°C. To do this, add the
calibrated in °C thermoelectric emf due to the cold junction temperature
to the measured thermoelectric emf and
add measuring point temperature to obtain the total
thermoelectric emf.
Temperature in °C
2.1-8410-0004/2
The cold junction can, however, also be To obtain a simpler circuit, the large number of
implemented by using a PT100 RTD for thermocouples used on the generator can be
determination of the actual temperature. The connected to a double-pole measuring point selector
temperature is refered to the calibration figure for 0 switch enabling the respective thermocouple to be
°C by electronic means. The electronic cold junction connected to a compensator for measurement.
also avoids the temperature error due to the junction
between the compensating leads and the copper
leads.
2.1-8410-0004/3
Turbogenerators Temperature Transducers
Description Rod-Type Thermostats
1 Barton cell
2 Vacuum indicator
Two pickups. displaced by 90°, are used to measure Each radial displacement of the shaft relative to the
the vibration of the rotating shaft relative to the stationary casing and thus relative to the transducer unbalances
casing. the balanced bridge circuit and produces an ac voltage.
The system for measurement of the relative shaft The amplitude of this ac voltage is a measure of the air
vibration detects each radial periodic movement of the gap and thus of the radial shaft position.
shaft relative to the casing. The mechanical shaft vibration also changes the
The system is of a noncontact type and measure the amplitude of the bridge ac voltage with the frequency of
distance between the transducer and the shaft by a the mechanical shaft vibration (relative vibration).
inductive method.
The transducer is attached to the bearing or casing
so that an air gap is obtained between the transducer tip
and the shaft, with the shaft providing the magnetic flux
return path for the coil. A change in the air gap results in
a change in the resistance of the magnetic circuit and
thus in the inductance of the coil.
The arrangement of the measuring points and su- 2. Cold and Hot Gas Temperatures
pervisory equipment at the generator is illustrated in the
attached diagram. The temperatures of the hot and cold gases are
measured by RTD’s upstream and downstream of the
1. Stator Slot Temperature hydrogen coolers Separate RTD’s are provided to be
used with the hydrogen temperature control system and
The slot temperatures are measured with resistance the generator electronical equipment protection.
temperature detectors (RTD’s). The platinum measur- Temperature detectors located in the generator
ing wire is embedded in a molded plastic body which interior are mounted in gastight protective tubes welded
provides for insulation and pressure relief. to the stator frame.
1. Thread ing
2. Aluminium housing 4. Detectors
3. Remove seal cup by turn- 5. Cable connection
TAG NO . DESCRIPTION
MKA75 CT011 Duplex RTD for Cold Gas Temperature after H2 coolers A & B
MKA75 CT012 Duplex RTD for Cold Gas Temperature after H2 coolers A & B
MKA75 CT013 Duplex RTD for Cold Gas Temperature after H2 coolers A & B
MKA75 CT031 Duplex RTD for Cold Gas Temperature after H2 coolers C & D
MKA75 CT032 Duplex RTD for Cold Gas Temperature after H2 coolers C & D
MKA75 CT033 Duplex RTD for Cold Gas Temperature after H2 coolers C & D
MKA76 CT011 Duplex RTD for Hot Gas Temperature before H2 cooler A & B
MKA76 CT012 Duplex RTD for Hot Gas Temperature before H2 cooler A & B
MKA76 CT021 Duplex RTD for Hot Gas Temperature before H2 cooler C& D
MKA76 CT022 Duplex RTD for Hot Gas Temperature before H2 cooler C& D
PGB32 CT001 Duplex RTD for outlet Cooling Water Temp of H2 Cooler ‘A’
PGB32 CT002 Duplex RTD for outlet Cooling Water Temp of H2 Cooler ‘B’
PGB32 CT003 Duplex RTD for outlet Cooling Water Temp of H2 Cooler ‘C’
PGB32 CT004 Duplex RTD for outlet Cooling Water Temp of H2 Cooler ‘D’
PGB33 AA001 Motorized Temp Control Valve for Cold Gas Temp. Control
PGB33 CT501 Temp Gauge on outlet Cooling water Header of H2 coolers
The location of the transmitters of the measuring and Local indication is provided for setting the pressure
supervisory equipment in the seal oil system is shown in the regulator and for observation.
Seal Oil Diagram.(Refer to 2.1-7111, Seal Oil Diagram)
The most essential measuring and supervisory 2.4 Seal Oil Pressure Downstream of Filter
devices in the seal oil system are: At this pressure gauge the seal oil pressure
Level detectors downstream of the filter can be observed.
Pressure measuring devices The pressure switch activates the standby seal oil
Temperature measuring devices pump, if the set seal oil pressure is not reached.
Volumetric flow rate measuring devices
2.5 Seal Oil Pressures Upstream of TE and
1. Level Detectors EE Shaft Seals
The readings are required for manual adjustment
Within the seal oil system of the seal oil pressures. Pressure transmitters trigger
The oil levels in the TE and EE prechambers alarm signals if the seal oil pressure drops below a
The oil level in the seal oil tank specified low limit.
The oil level in the seal oil storage tank
The oil level in the intermediate oil tank are super- 2.6 Vacuum in Seal Oil Tank
vised. This pressure transmitter signals a loss of vacuum.
A high oil level in the generator prechambers, due to
2.7 Differential Pressure Across Seal Oil Filter
an Increase In the amount of seal oil on the hydrogen
This local indicator displays the degree of filter
side of the shaft seal, results in an alarm. The alarm is
contamination on a dial (red/white) and activates an
initiated when the probe is immersed in oil.
alarm at a preset pressure differential.
A low oil level in the intermediate oil tank and in the
seal oil storage tank is monitored such that an alarm is
activated when the probe is no longer immersed in oil. 3. Temperature Measuring Devices
At high oil level in the seal oil tank, the vacuum pump
is stopped to prevent it from drawing seal oil. The alarm The following temperatures are measured locally:
is activated when the probe is immersed in oil. Seal oil temperature upstream and downstream of
To prevent dry running of seal oil pumps 1 and 2 with seal oil coolers.
low oil level in the seal oil tank, a second probe is provided
to stop seal oil pumps 1 and 2 when the probe is no In addition, the following temperatures are
longer immersed in oil. measured by means of resistance temperature detectors
for remote indication:
2. Pressure Measuring Devices Seal oil temperature downstream of filter
The following pressure measuring points are Seal oil temperature in hydrogen side seal
provided: oil drain, TE and EE.
2.1 Pressure Downstream of Seal Oil Pump 1 4. Volumetric Flow Rate Measuring Devices
On failure of seal oil pump 1, a pressure transmitter
activates seal oil pump 2. If the latter is not ready for The following volumetric flow rate measuring points
operation, the standby seal oil pump is automatically started. are provided:
Local indication is provided for setting the pressure
regulator and for observation. 4.1 Volumetric Flow Rates for TE and EE Shaft Seals
The volumetric flow rate of the seal oil supplied to
2.2 Pressure Downstream of Seal Oil Pump 2 each shaft seal is indicated by a volumetric flow rate
On failure of seal oil pump 2, a pressure transmitter indicator upstream of the shaft seal.
activates seal oil pump 1. If the latter is not ready for
operation, the standby seal oil pump is automatically started. 4.2 Volumetric Flow Rates for TE and EE
Local indication is provided for setting the pressure
Seal Ring Relief
regulator and for observation.
The volumetric flow rate of the seal ring relief oil
supplied to each shaft seal is indicated by a volumetric
2.3 Pressure Downstream of Standby Seal 011 Pump
flow rate indicator upstream of the shaft sea.
A pressure transmitter signals the takeover of the
seal oil supply by the standby seal oil pump.
The location of the transmitters of the measuring gauge. The electrical signal of the pressure transmitter
and supervisory equipment in the gas system is shown is used for activating an alarm.
in the Gas Diagram. (Refer to 2.1-7211, Gas Diagram)
The essential measuring and supervisory devices 2.3 H2 pressure at pressure reducers
in the gas system are :
Purity meter system For observation of the pressure setting.
Pressure measuring points 2.4 H2 casing pressure
Temperature measuring points The H2 casing pressure is monitored with a local
pressure gauge, the electrical signal of the pressure
1. Gas Purity Meter System transmitter being used for remote control and supervision.
The gas purity meter system measures the purity of 2.5 H2 High Pressure before Central Supply
the hydrogen gas in the generator as well as the The high pressure is monitored with a pressure
composition of the gas mixtures (CO2/air and H2/CO2) transmitter initiating a signal. In addition, a local indicator
during filling of the generator. The gas purity meter system is used to monitor the H2 high pressure.
is also used when removing the hydrogen from the
generator, where the hydrogen is replaced with carbon 2.6 Pressure before purity meter
dioxide and the carbon dioxide in turn with air. The gas The measuring gas pressure can be observed
required for the measurement is taken from the generator before the purity meters at a local pressure gauge.
or from the filling lines, respectively, and, on completion (Also refer to 2.1.4-49220, Pressure Transmitters.)
of the measurement, is discharged to the atmosphere
through a vent line. 3. Temperature Measuring Points
The indicator of the gas purity meter system is
equipped with a limit switch which provides a signal to Within the gas system, temperature detectors are
initiate an alarm when the purity drops below a preset used for supervision of the gas dryer and CO2 flash
value. evaporator.
2. Pressure Measuring Points The temperatures of the gas dryer heater and of the
heat transfer liquid in the CO 2 flash evaporator are
The following measuring points are provided: detected by means of thermostats and used for control
functions. In addition, the temperature of the heat transfer
2.1 CO2 Bottle Pressure liquid in the CO2 flash evaporator is indicated locally by a
The bottle pressure during CO 2 filling can be thermometer.
observed at a local pressure gauge.
A temperature detector installed in the vent line stops
2.2 H2 bottle pressure the precess if a preset temperature value is reached.
The bottle pressure can be read at the pressure (Also refer to 2.1-8440, Temperature Detectors.)
2. Rectifier Wheels
Fig. 1 shows the basic arrangement of the exciter. The main components of the rectifier wheels are
The three-phase pilot exciter has a revolving field with the silicon diodes, which are arranged in the rectifier
permanent-magnet poles. The three-phase ac is fed wheels in a three-phase bridge circuit. The internal
to the field of the revolving-armature main exciter via a arrangement of a diode is illustrated in Fig. 3. The
stationary-regulator and rectifier unit. The three-phase contact pressure for the silicon wafer is produced by a
ac induced in the rotor of the main exciter is rectified plate spring assembly. The arrangement of the diode
by the rotating rectifier bridge and fed to the field is such that this contact pressure in increased by the
winding of the generator rotor through the dc lead in centrifugal force during rotation.
the rotor shaft.
1 2 3 4
1. RC network
2 Fuse
3 Diode
4 Heat sink 1 2 3 4
1. Diode 3. Fuse
Fig. 4 Components for Rectifier Wheels 2. Three-phase lead 4. Diode Rectifier Wheel
For suppression of the momentary voltage peaks
Fig. 6 Rectifier Wheel
arising from commutation, RC networks, consisting of
one capacitor and one damping resistor each are
provided, and combined in a single resin- 3. Three-Phase Pilot Exciter
encapsulated unit. The three-phase pilot exciter is a six-pole revolving-
field unit. The frame accommodates the laminated core
The arrangement of the components in the with the three-phase winding. The rotor consists of a
rectifier wheels is illustrated in Fig. 5. The insulated and shaft with mounted poles. Each pole consists of
shrunken wheels serve as dc buses for the negative separate permanent magnets which are housed in a
and positive side of the rectifier bridge. This non-magnetic metallic enclosure. The magnets are
arrangement ensures good accessibility of all braced between the shaft and the external pole shoe
components and a minimum of circuit connections. with bolts.
2.1-9100-0029/2
1. Stator 1. Rotor 4. Sliprings for ground
2. Permanent magnet rotor 2. Stator fault detection
3. Stator winding 3. Magnetic pole 5. Bearing housing
2.1-9100-0029/3
Turbogenerators Basic Arrangement of Excitation System
Description with Rotating Rectifiers
ELR Series (up to 60 Diodes)
1 Fuse
2 Heat sink
3 Diode
4 Rectifier wheel (negative polarity)
5 Terminal bolt
6 Hot air outlet Current path
7 Rectifier wheel (positive polarity)
8 AC lead
9 DC lead
10 RC-Network
1 Multikontakt connector
2 Coupling
3 Diode
4 Rectifier wheel
5 Fuse
6 AC lead
7 NC network
8 Balancing weights
4 5
1 2 3
The fuses on the rectifier wheels may be checked continuous sequence Of flashes can be interrupted at
during operation with the Stroboscope. A separate any time by actuating the Feed or Return pushbutton.
flash tube is provided for each wheel (A and B). The Following this, a stationary image is obtained which
tubes, which are supplied through a common control ensures accurate checking of a single fuse. After
unit, are permanently installed in the rectifier wheel approximately two minutes, the stroboscope is
enclosure. This permits easy monitoring without any automatically switched off. If this period should not
adjustment outside the exciter enclosure being be sufficient for fuse checking, switching on the
required. stroboscope for another two minutes without delay can
Fig. 1 shows the basic arrangement of a fully be repeated for any desired number of times by
transistorized Stroboscope. The electronics required depressing the On pushbutton.
for control of the light signals are contained in the The stroboscope contains four plug-in printed
control unit and in the tubular lamps. The tubular lamps curcuit boards which can be readily replaced in order
are connected to the control unit by cables. to remedy any faults.
The Stroboscope is located in the rectifier wheel The capacitor and high-voltage transformer
and exciter enclosure so that the fuses may be required to produce the firing pulses for the flash tubes
observed from outside the exciter enclosure while are located on a printed circuit board which is
controlling the stroboscope. accommodated in the handle of the flash lamp.
To synchronize the sequence of flashes with the The operating elements are located on the front
generator rotation, the system frequency is utilized to panel of the control unit for ease of operation. A
activate the flashes. A double synchronous motor, depressed pushbutton is indicated by an illuminated
controlled through two pushbuttons and connected to dot in the pushbutton head.
two potentiometers and IC’s, causes the flash to be The line connector, the two connectors for the
timed so that a slow-motion observation of the fuse flash lamps and the fuse are located on the back of
becomes possible. the control unit.
The observation period for one full revolution of All connectors have a mechanical lock and are
the rectifier wheel (360°) is approximately 25 seconds. protected against dust and splashwater. The cables
At approximately 450°, the flash is reset to its initial are run in flexible metal hoses for protection against
rate, and the observation can be repeated. The mechanical damage.
1. General
The field ground fau!t detection system detects high- fault detection system consists of two stages and
resistance and low-resistance ground faults in the exciter operates continuously.
field circuit. It is very important for safe operation of a If the field ground fault detection system detects a
generator, because a double fault causes magnetic ground fault, an alarm is activated at RE <80 kΩ. (1st
unbalances with very high currents flowing through the stage). If the insulation resistance between the exciter
faulted part, resulting in its destruction within a very short field circuit and ground either suddenly or slowly drops
time. It is therefore an essential requirement that even to RE < 5 kΩ the generator electrical protection is tripped
simple ground faults should activate an alarm and (2nd stage).
protective measures be initiated, if possible, before the The generator is thus automatically disconnected
fault can fully develop. For this reason, the field ground from the system and de-excited.
1. Collection and Discharge System for The labyrinth seal prevents unfiltered power house
Carbon Brush Dust air from entering the exciter unit.
Carbon brush dust contaminates the exciter unit. Air at a slight gauge pressure is admitted into a
The resulting creepage paths can lead to damage due to compartment between the labyrinth seal teeth. The air
flashover. inlet is located at the enclosure of the rectifier wheels.
The labyrinth seal is bolted to and insulated from the
Contamination of the exciter unit is avoided by front- end generator enclosure.
providing for a controlled discharge of the carbon dust to
the atmosphere. For this purpose, the neutral grounding
sliprings are equipped with a protective cover. The fan 3. Makeup Air Filter
pressure chamber is located outside the protective cover.
A larger makeup air filter is required to handle the
larger air flow required for the carbon dust collecting
The air Circulatlng between the cover seal and the
and discharge system.
neutral grounding sliprings is thus discharged to the
atmosphere via a pipe, taking with it any carbon brush
dust. This makeup air filter is located above the exciter
enclosure and ensures that only filtered air is admitted
2. Labyrinth Seal at Exciter End Generator
into the exciter unit.
Enclosure
Strict observance of the operating and setting static head in case of pressure measuring points or
values is a prerequisite for reliable operation of the thermal characteristics in case of temperature
turbogenerator. measuring points. These calculated values are
Separate tables are provided for the various intended as guiding values for making the preliminary
design groups of the generator and its auxiliaries. They settings during initial commissioning of the unit.
show the transmitters activating the controls and These settings require certain corrections to
alarms as well as the transmitters acting on the account for the actual conditions. The final settings
generator protection circuits. obtained after startup and initial load operation are to
The Remark column contains additional be entered in the Operating Value column, and the
information on controls, temperatures and pressures. corrected tables should be promptly submitted to
All operating and setting values refer to rated BHEL for revision.
output of generator and maximum cooling water Revised pages will then be sent to the holder of
temperatures under steady-state conditions. the instruction manual as updates the request to
The operating and setting values initially specified discard all pages that have been replaced by those of
in this manual are based on experience under due a later date.
consideration of the specific site conditions, such as
Recommended
Gas Startup Shutdown Operation
Stock
Replacement of air in Generator Replacement of air in Not permitted Startup :
C02
housing*: Generator housing*: 3. V1
V, = 2.V V1 = 2.V During operation :
2. V1
* It is assumed that generator is at rest during gas filling and removal. Filling during turning gear operation will
result in a higher gas consumption. Due to the whirling motion between the medium to be displaced and medium
admitted, the purity deteriorates so that more gas is required for scavenging.
Parameter Tag Number Minimum Setting Value Maximum Setting Value Unit Remark
Control Generator Alarm Operating Control Generator Alarm
Protection Value Protection
Stator slot
temperature
95 -100 > 105 °C
24 RTDS
MKA 20 CT001
to MKACT 024
Stator Core
Temperature
EE-MKA32 CT001
to MKA32CT012
MKA75CT011
MKA75CT012
AB
Cold gas 25 - 45 > 55 >50 °C
MKA75CT013
temp
after H2
MKA75CT031
coolers
CD
MKA76CT011
MKA76CT011
AB
Hot gas l
MKA76CT012 45 - 70 > 75 °C
temp
before H2
MKA76CT021
coolers CD
MKA76CT022
Cooling water
temp before H2 PGB30CT001
coolers < 38 > 38 °C
PGB30CT501
A PGB32CT001
Cooling
water temp B PGB32CT002
after H2 < 50 > 50 °C
coolers C PGB32CT003
D PGB32CT004
Generator X MKD11CT014
Brg. Temp. < 90 > 90 °C
TE Y MKD11CT018
Parameter Tag Number Minimum Setting Value Operating Minimum Setting Value Unit Remark
Generator value Alarm Generator Control
Control Alarm
Protection Protection
The operating and setting values refers to rated output of generator and maximum cooling water temperatures. All pressure indicated in bar are
guage pressure.
When setting the transmitters, observe static head of oil column. When a seal oil temperature of 55 deg.C is reached, the unit must be shut dowhn
in order to avoid damage
0
Temp. Controller gas MKG 55 CT001 > 150 C
< 150
dryer heater
The operation and setting values refer to rated output of generator and maximum cooling water temperature.
All pressures indicated in bar are gauge pressures.
BHEL, Hardwar
0
MKC61 C
CT004
Operation
MKC65
55 - 70 > 75
CT002 > 80
0
Hot air, main exciter MKC65 C
Turbogenerators
CT002
MKC66
45- 60 > 65
Hot air, rectifier wheels Heater switches on
CT001
0
C
MKC65 Heater switches on
CT004
MKC 71 > 90
Exciter anti-condensation 45-90
CT001
0
heater C
MKC 71
CT002
< 84 > 84 m
Exciter Brg. Vibration
Pk
m
Exciter Shaft Vibration
< 200 > 200 Pk
< 90 > 90 130 0C High – High
Exciter Brg. Temp 0
C Annunciation
The operation and setting values refer to refer to output of generator and maximum cooling water temperature.
Exciter Supervision
Operating and Setting Values
2.3-4090-7500/1
Turbogenerators Operation Log
Operation General
Active power MW
Reactive power Mvar
Stator current kA
Stator Voltage kV
Field current A
Speed S-1
Generator gas pressure bar
MKA20CTOO1
Stator winding slot temperature °C TO
MKA20CT024
MKA31CTOO1
TE °C TO
MKA31CT012
Stator core temperatures MKA32CTOO1
TO
EE °C MKA32CT012
MKA75CT011
A/B °C MKA75CT012
MKA75CT013
Cold gas after coolers MKA75CT031
C/D °C MKA75CT032
MKA75CT033
MKA76CT011
A&B °C MKA76CT012
Hot gas before coolers MKA76CT021
C&D °C MKA76CT022
PGB30CT001
Cooling water temp, before coolers °C PGB30CT501
A PGB32CT001
Cooling water temp after coolers °C PGB32CT002
B
C PGB32CT003
°C PGB32CT004
D
Cooling water outlet temperatures from °C PGB33CT501
H2 coolers
Front MKD11CT014
Bearing Temperature TE
Rear °C MKD11CT018
Bearing Temperature EE Front MKD12CT014
Rear °C MKD12CT018
Bearing Vibration TE X micron MKD11CY021
Y MKD11CY022
X micron MKD11CY041
Bearing Vibration EE
Y MKD11CY042
X micron MKD12CY021
Shaft Vibration EE
Y MKD12CY022
Shaft Vibration EE X micron MKD11CT014
Y MKD11CT018
* Data should be recorded during steady-state conditions after constant operation for several hours
1) Data should be recorded during steady-state conditions after constant operation for several hours.
Date
1)
Operating values Unit Tag Number
(1) Data should be recorded during steady-state conditions after constant operation several hours.
(2) To be recorded only on failure of electrical purity meter system.
MKC61CT001
Cold air temperature to main exciter °C MKC61CT002
MKC61CT003
Cold air temperature to main exciter °C MKC61CT004
MKC65CT001
Hot air temperature after main exciter
°C MKC65CT002
Hot air temperature after main exciter MKC65CT003 .
°C MKC65CT004
MKC66CT002
Hot air temperature after rectifier wheel °C
MKD21CY041
Quadrature Axis Measuring Coil -
MKD21CY041
)
Data should be recorded during steady-state conditions after constant operation for several hours.
It is a prerequisite for startup of the turbine-generator displacement of the air prior to hydrogen filling and for
that continuous contacts be maintained between all plant immediate removal of the hydrogen from the generator.
sections directly or indirectly Involved In the starting
procedure.
Prior to startup, it should be ascertained that the 1.2.2 Hydrogen (H2)
following auxiliaries are in operation and will continue to The hydrogen gas quantity to be provided should
remain in service: suffice for displacing the CO2, for filling the generator to
operating pressure and to compensate for the H2 losses
Seal oil system
during operation [3].
Gas system
Cooling water supply
1.3 Cooling Water Supply
If auxiliaries were taken out of operation, the
The coolers to be placed in operation should be
operating media required to fill the auxiliary systems
filled with water. To do this, the cooler vents should be
should be made available.
opened~ Note: Continuous vents should remain open.
The vents should be kept open unfll the aIr on the water
1. Operating Media
side of the coolers has been completely expelled.
The operating media used, i.e.
Before startup, the operating staff should ensure
Turbine oil
that a sufficient cooling water supply Is available.
Carbon dioxide (CO2)
Hydrogen (H2)
2. Checking the Transmitters
must conform to the specifications [1] and [2].
Prior to startup, all connections should be rechecked.
This applies to piping as well as to cabling. When
1.1 Seal Oil System
checking the cabling, special attention should be paid to
The seal oil circuits should be filled with turbine oil.
testing the metering and signal cables. All alarm systems
The quantity of turbine oil required to fill the seal oil circuits
should be checked.
should be taken Into consideration when filling the turbine
All temperature measuring points should also be
oil tank.
checked. This applies to the local as well as the remote
reading thermometers. Unless temperature rises were
1.2 Gas System brought about by other preparatory work at the measuring
1.2.1 Carbon Dioxide (CO2) points, temperatures of approximately ambient or room
The carbon dioxide quantity to be provided should temperature should be indicated. When doubts exist
suffice for two complete generator fillings [3], i e. for regarding the electrical temperature measurement
calibration and/line compensation should be repeated.
2.3-5003-0001/2
Turbogenerators Filling and Initial Operations
Operation of Seal Oil System
Preparatory Work
2
Preparatory work
2.1
Adjust level detectors in liquid level detec- Carefully drain probe tank and reclose filler connections
tor rack with the probes immersed [3], [4] after completion of the functionaI tset.
2.2
Adjust level detectors for level detection
in seal oil system with the probes im-
mersed [3].
2.3
Check to ensure that regreasing device of axial
Check to ensure that bearing vapor
exhausters are ready for operation shaft seal is filled with a sufflcient quantity of grease.
Fill all existing loop seals in waste gas system with
turbine oil. Close drain valves.
2.4
Check valve positions for agreement Note: Pressure relief valves and seal oil pressure
with valve position list [5]. regulating valves have already been adjusted.
3
Start with filling of seal oil circuits
Note : With normal cooling water conditions, one of the two seal oil cooler is in operation. The second cooler is on standby and
filled with oil on its oil side, but should be empty, clean and dry on its cooling water side to preclude standstill corrosion.
3
Place vacuum pump and bearing Place one exhauster in operation electrically.
vapor exhausters in service Ensure that second exhauster is ready for startup.
4.1
Observe formation of oil foam in seal oil tank When the oil foam rises above the observable
level in the oil sight glass in the seal oil tank, close
shutoff valve
4.3
Fill and vent seal oil filters To do this, first open filler valve at filters and then
open vent valves.
4.4
Change over pumps Stop seal oil pump 1 by manual control. Then-
start seal oil pump 2 and standby seal oil pump. Stop
standby seal oil pump after a few minutes and change
over to seal oil pump 1 or 2.
4.5
Oil from the hydrogen side of the shaft seal will
Observe oil level in intermediate oil tank
continue to flow into intermediate oil tank
MKW06BB001, resulting in a rise of the oil level above
the sight glass. This is caused by the lack of pres-
sure in the generator.
5
Start with venting of seal oil circuit.
Seal oil circuit is filled
2.3-5110-0027/2
Turbogenerators Placing Vacuum Pump in Service
Operation
Start vacuum pump Open gas ballast valve and close shutoff valve
MKW11AA21 to avoid the formation of moisture
condensatation as the pump is in cold condition.
3
Open shutoff valve after the pump has been put in
Open shutoff valve MKW11AA121
operation for approximately 30 minutes. Pump must be
warm to touch.
4
Use control valve MKW10AA011 to adjust vacuum
Adjust control valve MKW10AA011
in seal off tank to approximately-0.6 to -0.8 bar.
Prerequisite:
1 Venting seal oil circuit Seal oil circuit was filled and placed in service.
1.1
Keep venting screws open until the oil emerges
Vent pressure retaining valves downstream
of seal oil pumps without bubbles.
1.2
Fill and vent seal oil coolers Vent seal oil coolers by means of vent valves.
1.3
Keep vent valves MKW21 AA261 and MKW22AA261
Fill and vent seal oil filters
open until the oil emerges without bubbles. Maintain
filler valve in open position.
1.4
Vent all pressure gauges, except for MKW10CP001,
Vent pressure gauges
through the venting screws at the respective pressure
gauge shutoff valves.
1.5
Bypass of volume flow reglators
Briefly open regulating valves MKW35AA011 and
MKW36AA011 to fill pipe with oil and then reclose
regulating valves.
Note: Seal oil units and seal oil valve rack were
subjected to a functional test at manufacturer’s works.
This included setting of seal oil pressures for operating
1 Setting Seal oil pressures
conditions to be expected.
Do not change any setting during commissioning
unless such a change is unavoidable.
2.1
2.2
Set seal oil volumetric flow rate for seal Set seal oil volumetric flow rate for seal ring relief
ring relief by means of volume flow regulators MKW35AA001 and
MKW36AA001
Note: Final adjustment can only be made when the
generator is filled to rated pressure and operated at
rated speed. When making the final volumetric flow
rate setting, also check the turbine-generator vibration
levels, since an incorrectly set seal oil pressure for
seal ring relief may impair smooth running of the
generator.
Setting of the seal oil pressures is Start with setting and checking of alarm and
completed changeover device.
Note: Seal oil units and seal oil valve rack were
subjected to a functIonal test at manufacturer’s works.
1 Setting of operating values This included setting and checkIng of all pressure
transmitters for operatIng conditions to be expected.
2
Alarm contacts at differential pressure indicator is
Differential pressure transmitters at set so that an alarm is activated when a predetermined
seal oil filters degree of fouling is exceeded.
7
Start with measurement of seal oil volumeteric flow
Checking and setting of supervisory rates and setting of flow rates for TE and EE seal ring
equipment are completed relief.
2
Measure oil volume flows for seal ring Note: Regulating valves MKW35AA 001 (TE seal ring
relief relief) and MKW36AA 001 (EE seal ring relief) for setting
the volumetric flow rates were set and checked at
manufacturer’s works. Settings were made under due
consideration of operating conditions to be expected.
Do not change any setting unless such a change is
unavoidable.
3
Measurement of seal oil volume flows is Start with functional testing of pumps and exhausters.
completed
2
Calibration of measuring device Only Barton cells with indicator module can be cali-
brated, since the calibration can only be performed at
the indicator module. Never make any adjustments on
the Barton cell itself.
A calibration will be required to adjust the indicator
module for a torque tube shaft rotation of 8° + 10 %. In
addition, a linearity correction should be made to elimi-
nate any linerarity errors of the cell and indicator mod-
ule.
The calibration should preferably be performed by
comparing the indication with the reading obtained by
means of a U – tube (mercury or water column) con-
nected to the system. The choice of mercury or water
column depends on the measuring range.
When using a mercury column for calibration, make
sure that no mercury will enter the cell.
Exercise utmost care when setting up the instru-
ment on a calibration stand.
Perform the calibration with dry air, making sure
that there is no water in the cell. Remove the bottom
screw plugs before starting with the calibration proce-
dure in order to drain any moisture condensate, etc. from
the cell.
Insert a screw plug on the high-pressure side for
tight sealing. Check to ensure that low-pressure side is
open. Then apply test pressure.
To calibrate measuring transducers with used cells.
Clean the cells before starting with the calibration.
4.1
Connect precision instrument and Connect instrument to a pressure transmitter (see
compressed air feed line Fig.1)
Disconnect pipes between shutoff valve and Barton
cell.
Connect a U-tube pressure gauge or another preci-
sion instrument to the high-pressure side of the
Barton cell.
Remove cover, pull off pointer and remove dial.
Attach calibration dial. It is recommended to use a
standard dial with a 60 mm dia. hole in the center,
affording access to the calibration facilities and en-
abling readings to be taken.
Set pointer to 0 % mark at zero pressure and make
vernier adjustment
2.3-5165-0001/2
Repeat calibration procedure until correct 0%,
50%and 100% indications are obtained.
Remove pointer and replace dial and then set
pointer to zero mark as precisely as possible.
Setting of limit contacts Limit contact settings are not visible from outside.
They should be checked and, if necessary, corrected.
Opening the housing is not required.
The operating points can be adjusted with a
screwdriver at the left-hand and right-hand setting
spindles in the indicator module.
Example: Limit contact C, positive contact; at
connector II, terminals 4,5 and 6, for maximum value
monitoring with rising characteristic, can be adjusted
by turning the upper setting spindle in the left-hand
side wall of the housing (looking on indicator module
from front).
To check the setting, connect a continuity tester,
e.g. ohmmeter. etc., to fixed contact and to one of the
moving contacts (NC or NO contact) and perform
status check. Apply pressure to be monitored to
measuring system. Check limit switch for proper
response and operation.
If the limit switch fails to operate as necessary,
correct setting for the required pressure by turning
the setting spindle. To obtain an optimum setting,
turn setting spindle several times beyond the switch
point in both directions and then approach switch point
position from the higher-pressure side for maximum
contacts and from the lower-pressure side for
minimum contacts.
If the limit switch fails to operate as necessary,
correct setting for the required pressure by turning
the setting spindle. To obtain an optimum setting,
turn setting spindle several times beyond the switch
point in both directions and then approach switch point
from the higher-pressure side for maximum contacts
and from the lower-pressure side for minimum
contacts.
This procedure accounts for the smaller effect of
the switch contact at the switch point. No variation in
the indication occurs before or beyond the switch
point.
2.3-5165-0001/3
Turbogenerators Functional Testing of
Operation Pumps and Exhausters
5
Measure vacuum in bearing compartments with a
Check bearing vapor exhausters for U-tube manometer while the bearing vapor exhauster is
proper operation
in operation. The vacuum should be between
approximately 5 to 10 mbar.
Prerequisite:
1 Startup of seal oil system Seal oil circuits must have been filled with oil.
3
Activate controls of bearing vapor exhausters,
Place bearing vapor exhausters, vacuum
pump and seal oil pump in operation vacuum pump and all seal oil pumps.
Seal oil circuits are new in operation Start will normal running routine.
2
Make adjustment with the probe immersed. Remove
Adjustments
level detectors in seal oil system from their normal
location and place them in a container filled with turbine
oil.
The level detectors in the level detector rack of tne
genrator supervisory system should be adjusted in the
probe tanks. To do this, fill tank with turbine oil via a
separate filler connection until the probe is immersed in
turbine oil. Then adjust level detector.
2.1
3
The level detector system is now adjusted After completion of adjustment, install level
and ready for initiating a level alarm detectors in seal oil system and then perform a functional
test.
Position 1 : H2 from pressure reducer Position 0 : Valve closed Position 2 : H2 from pressure reducer
MKG 15 BY 001 MKG 16 BY001
Position 1 : CO2 filling Position 0 : Valve closed Position 2 : CO2 waste gas
Filling generator with CO2
or H2 and measuring H2 purity
in generator
According to VDE, not more than two valves marked are allowed to be open at the same time when the Hydrogen is
obtained from the H2 bottle supply.
1)
One at a time Also refer to the following Information
[1] 2.3-6107 Position of Multi-way Valves Gas System
1.2
Turn range selector to position I Set range selector switch in CO 2 /H 2 purity
transmitter to position I (0-100% CO2 in air)
2
All lines carrying gas during this procedure are
Fill generator with carbon dioxide (CO2)
represented by yellow lines on the mimic diagram of
the H2 supply unit.
2.1
Switch on heater of CO2 flash evaporator. Observe
Switch on heater of CO2 flash evaporator temperature rise of heat transfer liquid at temperature
gauge. Wait until thermostat switches off the heater at
the preset temperature.
2.3
Terminate filling with carbon dioxide (CO2) Filling with CO2 may be terminated when a purity in
excess of 95% CO2 in air has been reached.
Switch off heater of CO2 flash evaporator. Close
shutoff valves MKG70 AA111 to 118 after CO2 bottles and
shutoff valve MKG71AA131 for high-pressure CO2.
2.4
Prior to starting with H2 filling, check to ensure that a
Check if sufficient CO2 is available for next
sufficient amount of CO2 is available for the next generator
generator filling operation
filling procedure.
3
The generator is filled with carbon dioxide Start with H2 filling.
1.1
Set shutoff and multi-way valves according
Adjust shutoff and multi-way valves as specified in
to valve position list [1] column H2 Filling.
1.2
Set pressure reducers MKG15 BY001 and Check to ensure that H2 pressure reducers adjust
MKG16BY001 to operating pressure and the required pressures.
pressure reducers MKG11 BY001 and MKG12 Note: Pressure after pressure reducers in H2 bottle
BY 001 to intermediate pressure rack must be approximately 8 bar. Pressure after
pressure reducers in H2 supply unit must be set to gas
pressure.
H2 filling should be performed by opening the H2
bottles separately.
2
Set range selector switch in CO 2 /H 2 purtiy
Set range selector switch to position II and
transmitter to position II (0 to 100% CO2). The increase
measure H2 purity
in H2 purity can be seen at the indicator, since the purity
meter system continues to measure the waste gas purity.
2.1
2.2
Contrary to the valve position list (1) the shutoff valve
Close shutoff valve MKG19 AA155 in waste
should be closed.
gast line
5
The generator is filled with H2 ; start with
normal running routine
Hydrogen Coolers in service with reduced flow (approx 10% of nominal flow)
Exciter cooler
filled with water and vented, control valves closed
Exciter cold air temperature cold air temperature >=40 0C, adjust cooling water
flow required for removal of loss heat [1]
Speed n = appox. 90 %
Bearing vibration set seal ring relief oil pressure for shaft seals
Synchronizing
Paralleling
De
1234
1234Cooler Out Of Service
Cooler In Service
** Operation with less coolers or higher output than shown above is not allowed.
260
250
240
Generator output in MVA
230
220
210
200
190
180
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
Time t in sec
1. General 2. Coolers
During shutdown of the generator the shaft lift oil Before the unit reaches turning gear speed, the cool-
pump must be started as soon as the unit reaches the ing gas temperature control system (if provided) should
speed specified in the Turbine Instruction Manual. be changed over from the automatic to the manual mode.
Use manual control to adjust a cooling water volume flow
2. Turning Gear Operation of approximately 5 to 10 % of the nominal flow rate. This
To prevent any difficulties during a subsequent runup results in a lower dew point temperature in the generator
due to thermal unbalances and resulting rotor distortion, interior due to the condensation of moisture contained in
the turning gear must be started as soon as the turbine- the gas on the cooler tubes and fins. The coolers should
generator coasts down to the speed (turning gear speed) be operated with this cooling water volume flow for ap-
specified for the turbine (normally automatic) and proximately 15 hours.
maintained in operation without interruption until the rotor
has cooled down to nearly room temperature.
1. Generator at Standstill With the Seal The scope of the preservation work required
Oil and Gas System in Operation depends on the duration of the shutdown, on the
overall conditions in the vicinity of the unit and on the
Due to operational conditions, it may become extent to which checks and inspections are possible
necessary to shut down the generator for a short during such period.
period. When the unit is at standstill, the bearing oil After removal of the hydrogen from the generator,
system can be taken out of service. In the absence of it is recommended to open the generator by removing
any operational needs, e.g. inspection or faults on two manhole covers and to connect a dryer or hot air
generator, the hydrogen should remain in the generator blower for continuous drying or circulation of the air in
in order to retain the most favorable prerequisites for the generator. Care should be taken to ensure that
a dry condition. All observations required for a this equipment is connected in such a way that a
generator partly taken into service should be circulation through the entire generator interior will be
performed, such observations being essentially accomplished.
limited to seal oil and gas systems. The hydrogen, exciter and seal oil coolers should
Normally it can be assumed that the generator be drained on their water sides and dried in a suitable
was operated with the gas dryer during the preceding manner.
service period. In the absence of any special fault These measure are intended to prevent any
(e.g. leak) requiring special measures, the generator condensation in the generator interior even under
interior will thus be in a dry condition. different environmental conditions, including the risk
Care should be taken to ensure that no standstill of stress corrosion cracking of the austenrtic rotor
corrosion damage will occur in the tubes of the retaining rings.
hydrogen and exciter coolers. During a brief outage It will be necessary to request the services of
the coolers should be supplied with a small water trained BHEL personnel for the preservation of a
flow. In addition, the coolers should be flushed with turbogenerator. If it is intended to shut down the
full water flow twice weekly. generator for a longer period, the competent BHEL
In the case of prolonged outages, the coolers should Office should be informed, when requesting the
be drained on the water side and dried. services of BHEL personnels, how long the units is to
be shutdown, on the conditions prevailing in the vicinity
2 Generator at Standstill With the Seal Oil of the unit during the outage and whether customer’s
personnel will be available for any required checks.
and Gas System Out of Operation
The necessary preparations for the preservation will
Preservation measures will have to taken when
then be made in all details by the competent BHEL
the generator is to be shut down for a period
Office. The services of BHEL personnel should again
exceeding two months with the seal and gas systems
be requested if a preserved unit is to be
to be taken out of operation.
recommissioned. The preservation measures will
then be abolished by the BHEL personnel. For
recommissioning, the same procedure should be
followed as during initial startup.
Suitable measures will have to be taken on all coolers to supply the coolers with a small water flow and to
taken out of service to prevent standstill corrosion in the flush them with the full water flow twice weekly.
cooler tubes [1]. In the case of a prolonged outage, the coolers should,
In the case of a brief outage, it will mostly be sufficient however be drained on their cooling water sides & dried.
After gas removal from the generator, the seal oil monitoring of the generator must be continued. All seal
system can be taken out of operation, and monitoring of oil pressures and temperatures should be recorded at
the generator is no longer required. the previous intervals, and attention should be given to
However, if the seal oil system remains activated, all special occurences.
2
Shutdown turbine-generator
3
Remove H2 gas from generator After lowering of the H2 gauge pressure in the generator
remove hydrogen from generator by admitting CO2.Then
purge CO2 by means of compressed air.
4
Stop seal oil pumps, vacuum pump and
bearing vapor exhausters
5
Terminate normal running routine
6
Partial or complete draining of the seal oil system
Seal oil system is out of service; start with will only be necessary for work requiring an empty
corrective actions, e.g. replacing defective system. Refill piping or branch circuits with oil prior to
valves and fittings restarting the seal oil system.
If the cooling water supply is stopped for more
than three days, the seal oil coolers should be drained
and dried on their cooling water sides.
If operation can be expected to be resumed after
three days, the coolers may remain filled with cooling
water provided that the cooler tubes are free of deposits
If deposits are detected, the cooling water should be
drained and the tubes cleaned and flushed with clean
water. Water channels should remain open until the
system is restarted.
During brief outages (< three days), it is permissible
to maintain the system in operation at low cooling water
velocities (slow-motion flow) in order to avoid deposits
in the tubes.
2
Drain seal oil tank
2.1
Close shutoff valves MKW21AA151 (Three-way valve at the inlet of coolers)
2.2 .
Open shutoff valves MKW06AA008 (after intermediate oil tank)
MKW11AA185 (after seal oil pumps)
2.3
Start seal oil pump MKW11AP001 and
Deactivate level detector MKW10CL002.Start
vacuum pump MKW11AN001
pumps. The pumps should be kept in operation only
until the seal oil has been removed from seal oil tank
MKW10BB001. Stop the pumps immediately afterwards.
Close shutoff valve MKW11AA185.
The remaining seal oil can be drained through the
drain plug in bottom of seal oil tank
3
Drain intermediate oil tank The remaining oil can be drained through drain plug
MKW06BB001 of intermediale oil tank.
4
Drain seal oil coolers and piping
4.2
Close cooling water inlet valves.
Open cooler drain and vent valves on water After draining on their water sides, the coolers
side
should dried to prevent standstill corrosion of the cooler
tubes.
5
Draining of seal oil circuit is complete Start with draining of signal line.
It is recommended to leave the hydrogen in the The gas must, however, be removed from the generator
generator and to reduce the hydrogen pressure if the if the seal oil system is taken out of service or for carrying
generator is to be shut down for a period up to two months. out welding work within the range of the gas supply system
It should, however, be observed that all alarm devices or work on the generator. If the generator is filled with air,
must be set to the new operating values. Monitoring of the seal oil system can be taken out of service.
the gas system must be continued as during normal
operation.
1.1
Check zero setting of CO2/H2 purity trans- mitter
1.2
Set shutoff valves and three-way valves ac- Set valves as specified in column Lowering H2
cording to valve position list [1] Pressure.
1.3
Lower the gas pressure in the generator to
Lower gas pressure in generator
approximately 0.1 bar when shutoff valve MKG19 AA155
is open and when multi-way valve MKG18AA101 is in
position 2 (H2 waste gas).
2
Generator is ready for filling with CO2
1 Filling generatorwith carbon dioxide All lines carrying gas during this procedure are
represented by yellow lines on the mimic diagram on
the H2 supply unit
1.1
Set range selector switch to position II Set range selector switch in CO 2 /H 2 purity
transmitter to position II (0 to 100% CO2 in H2).
1.2
Switch on heater of CO2 flash evaporator Switch on heater of CO2 flash evaporator. Observe
temperature rise of heat transfer liquid at the temperature
gauge. Wait until the thermostat switches off the heater.
1.3
Set shutoff and multi-way valves according Set valves as specified in column Air Filling.
to valve position list (1)
1.4
CO2 filling can be terminated when the indicator
Terminate filling with CO2
shows a purity reading in excess of 95% CO2 in air.
Switch off heater of CO2 flash evaporator and close
shutoff valves MKG70AA111 to MKG70AA118 after CO2
bottles and shutoff valve MKG71AA131 for high-pressure
CO2.
2
Generator is filled with CO2 Start with air filling.
1 Filling generator with air All lines carrying gas during this procedure are
represented by blue lines on the mimic diagram of the
H2 supply unit.
1.1
Set range selector switch in C0 2 /H 2 purity
Set range selector switch to position I
transmitter to position I(0 to 100% CO2 in air)
1.2
Establish hose connection between compressed
Establish hose connection
air filter MKG91BT101 and regulating valve MKG91
AA101.
1.3
Set shutoff and multi-way valves according Set valves as specified in column Air Filling.
to valve position list [1] Ensure that compressed air is clean and dry. ie.
neither oil nor water should be entrained in the air. Adjust
the compressed air pressure by means of regulating
valve MKG91 AA101 so that the pressure in the generator
will not exceed 1 bar.
1.4
Terminate filling with air When the indicator gives a readlng of 0% CO2 in
air, the carbon dioxide has been driven out of the
generator.
Open shutoff valves downstream of the liquId Ievel
detectors and close multi-way valve MKG78AA111 for
purging the main lead range and the pipes to the level
detectors. After purging, switch multi-way valve MKG78AA
111 to position II (CO2 Waste Gas) and close shutoff
valves downstream of liquid level detectors
Close shutoff valves MKG91AA101 and MKG91
AA105 afler purging.
1.5
Remove hose connection
Remove hose connection between compressed
air title MKG91BT101 and regulating valve MKG91 AA101.
2
Stop normal running routine of gas system
2.3-8630-0015/2
Turbogenerators Supervision of Generator During
Description Standstill
Exciter
With the unit on turning gear or at standstill, the Slightly contaminated filters should be blown out
exciter dryer and the anticondensation heating system with clean compressed air from the air inlet side or
must be in operation and absorb the moisture’ from washed in water of approximately 30°C, adding Prilor
the air inside the exciter enclosure. another neutral expansion agent.
Air drawn from the power house via an air filter is Depending on the operating conditions, the ball
dehumidified in the dryer and then delivered into the bearings of the fan and gear motor should be packed
exciter enclosure. with new grease at intervals of two to three years.
The filters should be checked for contamination The brushes of the ground fault detection system
at regular intervals and cleaned or replaced as should be removed to prevent the formation of rust on
necessary [1]. the sliprings. In the case of a prolonged outage, a
Caution: Never place exciter dryer into service protective coating should be applied to the measuring
without makeup air filters. sliprings.
The details given herein on faults, their possible corrective measures can be taken in accordance with
causes and the corrective measures cannot be the following instruction, the turbine-generator should
considered complete in every respect, since all be shut down and the services of the manufacturer
possible troubles cannot be covered in advance. In should be requested. In most cases, however,
most cases, the operator will have to decide on the sufficient details will be found in the Turbogenerator
measures to be taken. The individual measures Manual.
required depend on the mode of operation. Unless
Fault/Cause Remedy
Differences in slot temperatures of stator winding The embedded RTD’s should be checked when
different slot temperatures are indicated while stator
currents are of equal magnitude in the three phases. Such
check should only be made with the generator at rest
and in non-excited condition. The check should include
resistance measurements as well as testing of the
detector leads, the measuring point selector switches and
the indicators. Care should be taken during resistance
measurements of the embedded RTD’s to ensure that
they are not heated as this will falsify the results. In many
cases, a fault can be cleared by recalibration of the RTD’s.
Loss of cooling water flow. Restore cooling water flow immediately. If this should
not be possible, the generator should be unloaded and
shut down.
Liquid in generator
Due to a leaking or defective H2 cooler tube. The liquid in the generator casing should be
inspected to determine its origin, i.e. defective cooler
section, bearing oil or moisture condensate.
Very small water quantities are indicative of moisture
condensate. The gas dryer should then be placed in
operation. The hydrogen gas should be examined in a
laboratory to determine its moisture content.
Larger amounts of water points to a leakage cooler
section, in which case the measures outlined in [2] will
have to be taken.
Unbalanced load due to unequal phase loading of If the generator is operated with unbalanced load
the system connected to generator due to particular system conditions, care must be taken
that the continuously permissible unbalanced load is not
exceeded [3]. The unbalanced load is defined as the ratio
of negative sequence current to rated current. The
permissible rated stator current should not be exceeded
in any stator phase. When the unbalanced load is higher
than the continuously permissible unbalanced load, steps
should be taken for bringing about a uniform system load.
The generator should be shutdown if it is impossible to
distribute the system load more uniformly over the three
phases.
Fault/Cause Remedy
Sudden deterioration of rotor running condition Check whether the deteriorated running condition
originated due to the turbine or whether the rotor bearings
are damaged. A deterioration of the running condition
may be caused by a change in the balancing condition
or by a rotor wiinding short. Unload and shotdown turbine
generator as soon as feasible if cause cannot be located
and corrected for severe condition. Since it is very difficult
in most cases to find a definite cause, it is advisable to
obtain the help of manufacturer's product service
personnel.
Fault/Cause Remedy
Liquid In Generator
This fault is due to a leaking or defective H2 cooler Identify the defective cooler section. First, close
tube. cooling water outlet of this cooler section and then the
cooling water inlet.
Close shutoff valve before the level detectors that have
initiated the alarm. Drain the liquid by means of shutoff
valves after the level detectors. Repeat this procedure
until no liquid is drained through the shutoff valves. This
procedure ensures that no hydrogen can escape from
the generator through the shutoff valves.
Fault/Cause Remedy
Bearing oil pressure indicated in the shaft lift Oil pressure depends in part on the bearing oil inlet
oil pipe drops temperature. Check first to determine whether the
pressure drop was caused by an oil temperature
variation. If not, the shaft lift oil system should be
checked for leakages. The fault may be due to a leak at
the check valve in the lift oil pipe. To determine if the
check valve is leaking, close globe valve in the lift oil
line. Prior to closing valve, check and record the setting
(throttling valve as set for operation). This check is
performed by counting the number of turns or by
measuring the travel.
If, on closing the globe valve, the pressure gauge
shows an increase over the previous operating value,
the check valve is leaking. Replace or repair the check
valve at the next shutdown or inspection. A precise
adjustment of the throttling element will again be
necessary during recommissioning.
Fault/Cause Remedy
Fault/Cause Remedy
Level detector for low oil level in seal oil tank has See under Low oil level in seal oil tank in [1].
stopped seal oil pump 1.
Level detector for low oil level in seal oil tank has See under Low oil level in seal oil tank [1].
stopped seal oil pump 2. .
Fault/Cause Remedy
Pressure collapses during pump changeover. Trace and correct cause of pump changeover.
Seal oil filter in service is contaminated. For remedial measures, see below.
Seal oil filter MKW21AT001 or MKW22AT001 is con- Change over to standby filter with changeover valve
taminated assembly. Deactivate contaminated filter by means of
the other changeover valve assembly.
Vacuum bypass valve MKW10AA011 is open. Remove contaminated filter and clean filter. Fill filter
housing with turbine oil prior to reassembly. Prepare filter
for operation.
Screw caps on relief valves M KW11AA031 and For remedial measures, see [1 ]
MKW12AA031 are missing.
Fault/Cause Remedy
Shutoff valve MKW06AA151, which must always be Open shutoff valve MKW06AA 151.
open and secured against closing, was opened
without authorization after removal of lock. (Shutoff
valve MKW06AA151 should only be opened for
setting of level detectors MKA06CL001 and MKW07
CL001 in generator prechambers.)
Float-operated valve MKA06AA001 does no longer If the fault is due to failure of float-operated valve
operate properly. The valve remains fully closed or MKW06AA001, the fault cannot be cleared without
opens insufficiently. removing the float-operated valve.
The indication is given when the oil level in the seal
all drain Iines has risen to such a height that level
detectors MKA06CL001 and MKA07CL001 in the
generator prechambers are immersed in seal oil. Open
regulating valve MKW06 AA008 so that the oil level will
drop. When the oil level in intermediate oil tank MKW06
BB001 has fallen to such an extent that level detector
MKW06CL001 is no longer immersed in seal oil, the
indication Low oil Ievel in Intermediate oil tank is given.
Then close regulating valve MKW06AA008.
Caution: if the regulating valve Is open, the complete
oil volume contained In the intermediate oil tank is
forced Into the seal oil storage tank and hydrogen
flows Into the seal oil storage tank.
If the cause of the trouble is not removed, the oil
level In the seal oil drains lines starts to rise again and
the procedure described above is repeated. Removal of
fault is only practicable following shutdown and emptying
of generator and lowering of oil level in intermediate oil
tank.
Emergency operatlon for brief periods is possible
with manual control of regulating valve MKW06AA008.
Make sure that oil level remains visible in oil sight glass.
Oil level In Intermediate oil tank MKW06 BB001 has For remedial measures, see: High oil level in TE/EE
dropped to such an extent that level detector MKW06 prechambers
CL001 is no longer immersed In oil.
Make sure that regulating valve MKW06AA008 is
closed.
vacuum pump MKW11 AN001 so that it can draw no Operation of the generator can be continued without
seal oil. Level detector MKW10 CL001 automatically removing the fault. The fault should, however, be cleared
restarts the vacuum pump when the level detector Is no during the next outage.
longer immersed in oil.
Float- operated valve MKW10AA001 does not close
even if the oil level in seal oil vacuum tank MKW10 BB001
continues to rise above its normal level.
Float-operated valve MKW10AA001 in binding. If the fault is due to a failure of float-operated valve
MKW10AA001 set control switch for standby seal oil
pump MKW12AP001 to off position. Seal oil pump
MKW11AP001 automatically switched off by level detector
MKW10CL002. The pump is automatically restarted
when the level detector is immersed in seal oil.
After stopping of the seal oil pump, B valve MKW13
AA001 takes over the seal all supply to the shaft seals
without any interruption. Stop the vacuum pump and open
vacuum bypass valve MKW10AA01 to break the vacuum.
Level detector does no longer function properly. Check level detector and probe.
Leak in seal oil storage tank. In the event of a leak In the seal oii storage tank,
the seal oil pump can no longer draw oil for supply to the
shaft seals. Shutdown generator and remove gas
immediately.
Fault/Cause Remedy
Fault/Cause Remedy
H2 bottle connected and open is empty. Close valves as necessary to isolate the empty H2
bottle from the gas system. Then connect a new H2 bottle
ready for operation.
Note: Record connection of a new bottle and
analyze gas consumption for continuous assessment
of tightness of entire system. If a major gas loss due
to leakage is suspeced, identify leaks immediatel [1].
H2 supply is distrubed Check hydrogen flow path and correct cause of fault.
Setting of H2 operating pressure reducer in H2 supply Check setting of H2 operating pressure reducer MKG16
unit incorrect. BY001.
In the event of a failure of the H2 operating pressure
reducer, perform changeover to H2 filling pressure reducer
MKG 15 BY001. To do this, set multi-way valve MKG15
AA151 to position 1 [2] and then open valve MKG15
AA121. Set filling pressure reducer to operating value.
Close shutoff valve MKG16 AA121 to check or replace
the defective pressure reducer.
Fault/Cause Remedy
Low H2 Purity
Seal oil system was in operation without vacuum Corrective action as described in [1].
treatment of the seal oil for a longer period time, i.e.
the air entrained in the seal oil will escape into the
generator, resuling in a deterioration of the H2 purity.
The supply of measuring gas to CO 2/H 2 purity Check the complete meter system for CO2/H2 purity
transmitter MKW31CQ001 has been interrupted, transmitter MKW31 CQ001 as per instructions manual
resulting in faulty indication of the instrument or for H2/CO2 gas Analyser.
malfunction.
Remedy
Fault I Cause
Note: After operation of one or several fuses, it may
Fuse indicator operated be necessary to observe the respective operatlng
limitations [1], [2].
Failure of one or several diodes. If the number of blown fuses per bridge arm and
rectifier wheel has reached the maximum admisslble
value, it is no longer permissible to continue on-load
operation of the generator. The number of blown fuses
indicates a severe fault in the excitation system, the cause
of which must be identified and removed. To do this. the
turbine-generator must be shut down immediately.
Work on the exciter should be performed with the
field ground fault detection system shut down and the
measuring brushes lifted off the sliprings. Remove the
exciter enclosure and half of the enclosure over the
rotating rectifier wheels. Rotate entire shaft assembly of
turbine-generator until defective fuse is brought to an
accessible position. While rotating the shaft. visually
check all fuses in both wheels. To remove defective fuse,
detach contact splice strap of the heat sink by unscrewing
lock nut. Unlock and unscrew the screw attaching the
fuse to the wheel on front side. A continuity test of the
fuse will indicate whether fuse failed due to an electrical
or mechanical fault. A mechanical fault is unlikely.
If fuse failed electrically, the cause of the fault
(defective diode) should be located by megger test. To
do this disconnect flexible lead from the three-phase
power lead. In cases where two diodes are mounted in
each heat sink, both flexible leads must be
disconnected. A controlled DC voltage source of not less
than 1000 V with constant output voltage must be
available for the measurements. Apply DC voltage to
diode in reverse direction. Use another connection to tie
the rectifier wheel to the voltage potential. Connect a
micro-ammeter for determination of reverse current in
circuit between the voltage source and the diode
connection.
To obtain the blocking characteristIc of a diode,
increase applied voltage in steps up to e maximum level
of 1000 V and determine the reverse current for each
step. At least three measurements are necessary for
pIotting the characteristic, the recommended voltage
steps being 500 V, 750 V and 1000 V. The maximum
permissible reverse current at 1000 V amounts to 500
μA. If this limit is exceeded, the diode must be repIaced.
If the shaft assembly cannot be shut down for
several hours, e.g. because cooldown of turbine is still
in progress, the measuring setup described above can
probably not be implemented. ln such a case, the shaft
should be stopped for brief period only to enable a
replacement of the diode(s) in the respective branch
circuit. Plotting the blocking characteristic and assessing
the reusabilily of the diode(s) can then be done while
the unit is running. The defetive diode(s) should be
cautiously unscrewed from the heat sink using the special
diode wrench.
Before installing new diodes and fuses, the
following checks must be made:
After cleaning the heat sink, the insulation
resistance
Trapped air has accumulated in cooler. Vent cooler by means of vent screws.
Cooler is fouled on water side. If the cold air temperature continues to rise above the
permissible level, the generator should be operated at a
reduced load.
Unload & shutdown the generator at the next possible
occasion.
Remove the exciter enclosur, isolate the cooling
water supply and detach return water channel for cooler
cleaning.
Thoroughly clean individual cooler tubes with a tube
cleaning brush. If this should not lead to the desired result,
the coolers should be disassembled and cleaned by
hydraulic or chemical means [1].
Use new gaskets for refitting water channels.
We recommend cleaning the exciter coolers on the
air side as well.
For this purpose, cover main exciter, rectifier wheels
and ploit exciter with a tarpaulin. Blow out coolers with
clean and dry compressed air. After careful cleaning, the
tarpaulins should be removed and the exciter enclosure
placed in position over the exciter. Check to make sure
the seals are tight around the exciter enclosure to prevent
the exciter from drawing unfitered air into the enclosure.
Liquid in exciter
The cause is a leak or a tube rupture at the cooler Unload and shutdown turbine-generator.
tube bundle. Identify the defective cooler section. Close cooling
water inlet and outlet of this cooler section.
Drain the water from the cooler. If the defective cooler
tube cannot be identified by a simple visual examination,
disassemble the cooler section, remove water inlet/outlet
and return water channels. All cooler tubes must be
separately subjected to a leakage test.
1. Plug
2. EE Tubesheet
3. Cooler tube
4. TE Tubesheet
Stroboscope defective
Check to ensure that supply voltage is available at
Pins 2 and 9 on plug board 2 are interconnected for a pins 1 and 9 on plug board 2. If no voltage is available,
supply voltage of 220 V. check cable and fuse.
Note: Voltages specified below may vary within a
tolerance range of + 15%.
1 2 3 4 5 6 7
Relay d1 must pick up on depressing the on
0 0 0 0 0 0 0
pushbutton. If the relay drops out again on releasing the
pushbutton, the pushbutton should be pressed again and
0 0 0 0 0 0 held in position. Measure voltage at pins 11 and 5 with
8 9 10 11 12 13 respect to ground (15 V DC). If no voltage is available,
replace printed circuit board 3. If voltage is available,
replace printed circuit board 2.
Plug board 3, printed circuit board viewed from below Ground/pin 13 abt. 23 V DC
Ground/pin 7 abt. 15 V DC
1 2 3 4 5 6 7 Ground/pin 11 abt. 5 V DC
0 0 0 0 0 0 0 Ground/pin 9 abt. 6-9 V DC
0 0 0 0 0 0
8 9 10 11 12 13 If no voltage is available at pin 7 or with 15 V or 0 V
at pin 9, replace printed circuit board provided that voltage
is available at pins 13 + 11.
Overheat protection has switched off the exciter Open door in exciter enclosure behind which the
dryer. In most cases, the cause is no or an insufficient dryer is located from the operating floor. Following a short
air flow. cooldown period, the overheat protection automatically
returns the dryer to service.
Check whether air is drawn in via the intake parts
on both side of the air diyer.
If yes, the air flow passage is obstucted. Inspect
prefilter in door for contamination.
If air is drawn only, via one intake part, the free flow
of dry air or regeneration air is obstructed. Restore free
flow conditions.
If no air is drawn in via both intake parts, the ventilator
motor in the dryer has failed. The exciter dryer should be
deenergized, disassembled and returned to the
manufacture’s work for repair. A 2 kW heater-blower
should be used inside the exciter enclosure for dehumidifi-
cation as long as the dryer is not available due to repair.
High-resistance groundfault in exciter circuit Immediately investigate cause of ground fault alarm.
Ω)
(RE <80 kΩ Measure insulation resistance in exciter circuit if the
generator can be disconnected from the system and de-
excited [2].
If an insufficient insulation resistance is measured,
operation of the generator should be continued only after
consultation with the manufacturer to avoid possible
major damage.
Low-resistance ground fault in exciter circuit
Ω)
(RE <5 kΩ At RE <5 kΩ, a TUSA trip is activated by the electrical
generator protection, and the generator is disconnected
from the system and de-excited.
If the insulation resistance measurement confirms
the ground fault, the generator must be removed from
service. The manufacturer should be notified and
entrusted with the fault removal.
If no ground fault can be identified by the insulation
resistance measurement, check system once more for
ground faults and rated speed before exciting the
generator again.
Maintenance Intervals
Every 3 months
Every 6 months
See
Work Required
Instruction
Annually
Monthly
Weekly
Daily
Check sight glasses after level detectors for liquid level x 2.4–4210–......
Check gas consumption x 2.4–4610–......
Check hydrogen cooler vents x 2.4–4240–......
Check shaft grounding brushes x 2.4–4210–......
Check seal oil cooler in operation for proper venting x 2.4–4540–......
Check seal oil supply lines and shutoff valves for leakages x 2.4–4540–......
Check degree of contamination of seal oil filters x 2.4–4550–......
Change over seal oil pumps 1 and 2 x 2.4–4520–......
Perform functional check of standby seal oil pump x 2.4–4520–......
Change over vapor exhausters 1 and 2 x 2.4–4520–......
Check EE generator bearing insulation x 2.4–4250–......
Check EE shaft seal insulation x 2.4–4250–......
Measure insulation resistance x 2.4–4310–......
Check shutoff valves for free movement x 2.4–4610–......
Check shutoff valves with magnetic drive for function and gastight x 2.4–4610–......
Check gas supply lines and shutoff valves for leaks x 2.4–4610–......
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check shaft grounding brushes x
1 Brush holder
2 Grounding brush (Design A)
3 Grounding brush (Design B)
4 Brush spindle
5 Insulation
6 Rotor shaft
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check cooler vents x
1. General 2. Coolers
Special measures should be taken to prevent During normal operation, the cooling water flows
corrosion damage to the cooler [1]. Cooler sections through all cooler sections. Since the coolers are designed
having no cooling water flows for some time may be for 100 % capacity at maximum cooling water
subject to standstill corrosion. In addition to many other temperature, the condition may arise that the coolers are
corrosive influences, such as the different elements of supplied with smaller cooling water flows for long periods.
the cooling water, locally differing deposits, raw materials, Depending on the purity of the cooling water, this may
etc., there exists the danger that micro-organisms on the result in deposits due to the lower water velocity in the
tube walls may die and decay due to a loss of fresh water cooler. To prevent cooler damage, it is therefore
supply (lack of oxygen). Ammonia is formed from such recommended to rinse the coolers with the full water flow
decay which may lead to stress corrosion cracking. during short outages. In addition, the coolers should be
Corrosion damage can only be properly prevented if the frequently cleaned with brushes. For heavy cooler
cooler is drained on the water side, cleaned, completely contamination and if operational restrictions and
dried and maintained in a dry condition. With the generator shutdowns are undesirable, it is recommended to install
in commercial operation, such measures are often a continuous cooler water purification system.
unfeasible, particularly in cases of short outages. In such
cases, the measures outlined below should be taken.
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check EE genertor bearing insulation x
Fig. 1 Generator Bearing and Seal Insulation Also refer to the following information
[11 2.5-0300 Checking the Bearing and Seal Insula-
tion
Maintenance Intervals
Work required
Every 3 months
Every 6 months
Annually
Monthly
Weekly
Daily
Check zero x
Normally the Barton cell-requires no maintenance. With contaminated working fluids, it may become
In the event of a disturbance, first inspect the pres- necessary to remove the pressure caps on the high-
sure transmission lines and the other fittings for pressure and low-pressure sides for inspection and
possible faults. cleaning of the diaphragm bodies. To do this, loosen
If unauthorized opening of the center plate unit or and remove clamping bolts Cautiously lift off pres-
damage to the diaphragm bodies has resulted in sure caps to avoid damaging the diaphragm bodies
draining of the liquid, the -system must be returned if a large amount of dirt has accumulated. Dirt. tar or
to the manufacturer’s works for refilling under other foreign matter deposited on the diaphragms
vacuum. should be removed by means of a soft brush, using
suitable solvents.
Note: Barton cells with incompletely filled dia-
phragm bodies are not capable of withstanding high Note: Never use a wire brush, knife or other
static pressures.
tools which are likely to damage or perforate
Inspect lower parts of pressure caps for deposits
the diaphragm bodies.
of solids, crystals, high-viscosity condensate (e.g.
tar) at regular intervals. To do this, disconnect Barton Remounting the pressure caps:
cell from measuring point and remove bottom screw
plugs. • If necessary, replace gaskets prior to remounting
the pressure, caps.
Note that over-range protection of Barton cell is
only designed for short-lived operational troubles as • Remount pressure caps.
these can normally be corrected within a short time.
Note: Do not damage diaphragm bodies.
Relieve damping valve at regular intervals to avoid
sticking of the O-ring seal due to prolonged over- • Lubricate screw and nut threads and nut contact
loading To do this, close shutoff valves and open faces with Molykote paste
equalizing valve assembly until system is restored
to zero. It is recommended to perform this Zero check • Fit screws and torque to 8 kpm (torque wrench)
at intervals of three months.
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Measure insulation resistance x
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check over seal oil pumps 1 and 2 x
Perform functional check of standby seal oil pump x
Change over bearing vapor exhausters x
Repack regreasing devices of bearing vapor exhauster shaft seals with gease x
1. Seal Oil Pumps showing that the standby seal oil pump is in operation
To prevent dry running of the pump and to ensure are displayed during the short running period.
proper lubrication of the shaft seal, each new or Perform changeover to standby pump once per
overhauled seal oil pump should be filled with turbine oil month. Check pump delivery pressure and then change
via the oil filling plug, unless this has already been over to normal-service pump.
accomplished through the oil supplied to the oil inlet of
the pump. In addition, the oil ensures proper seallng of 2. Bearing Vapor Exhausters
the shafts for pump priming. The bearing vapor exhausters are provided with a
Change over seal oil pumps 1 and 2 at monthly regreasing device for the axial shaft seal. Repack
intervals. To do this start standby pump by manual regreasing devices with grease every six months.
control. Then stop pump so far in service by manual The exhausters should be changed over once per
control. month. To do this follow the same procedure as for the
Perform functional check of standby seal oil pump seal oil pumps.
3 once per month. To do this. start standby pump by
manual control. After a short running period, this pump
will then be automatically stopped again after elapse of
a preset time delay. Check to ensure that the indications
1. Venting Screw/ Oil filling Plug 3. Pressure Relief Valve 1. Regreasing device
2. Discharge Flange 4. Drive Shaft 2. Drive Motor
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Perform cooler changeover x
Check seal oil supply lines and shutoff valves for leakages x
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check degree of contamination of seal oil filters x
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check gas consumption x
Check shutoff valves for free movement x
Check gas supply lines and shutoff valves for leaks x
2. Gas Consumption
Every 6 months
Every 3 months
Annually
Monthly
Weekly
Daily
Check fuses X
1. Fuse Monitoring
With the aid of the stroboscope whose light The operating limitations [1] must be
frequency is automatically controlled, it is possible to (observed if several fuses have blown.
observe each separate fuse on both wheels. To activate
the stroboscope press the On pushbutton. It is then In normal operation, the fuses should be
possible to select either flash tube 1 or flash tube 2 by monitored at least once each day. A check is required
pressing the corresponding pushbutton Lamp 1 or at once following abnormal operating conditions, e.g.
Lamp 2 to observe each successive fuse on the rectifier short-circuit on the system close to the power
plants,asynchronous running, etc. If the exciter is
wheel. By pressing the feed or return pushbutton, the
operated with defective fuses, monitoring should be
flashes can be timed so that a continuous slow-motion
done on an-hourly basis. If no additional fuses have
observation of each fuse is possible.
blown after two further shifts, normal running routine
may be continued.
The position of the fuse indicator shows whether
a fuse is intact or has blown due to diode failure. If the
color-coded fuse indicator has taken a radial position,
the fuse has blown. To determine the condition of the 2. Measuring the Insulation Resistances
entire rectifier wheel, it is necessary to know in which
arm of the bridge each blown fuse belongs. The bridge Check the insulation resistances of the windings to
arm can be determined from the color marking above ground and the insulation resistances between the
the fuse on the edge of the rectifier wheel. diode heat sinks and the rectifier wheel [2].
Maintenance Intervals
Every 3 months
Every 6 months
Work required
Annually
Monthly
Weekly
Daily
Check make-up air filters x
1. Cleaning Air Filters agent to drain. Air filters are now ready for operation and
The air filters should be cleaned with Purinol air filter can be reinstalled.
cleaning fluid available from DELBAG-Luftfilter GmbH. The cleaning and wetting fluids are available from
The air filters should be removed and slightly beaten
to remove loose dust. For cleaning in a Purinol bath,
pour Purinol into the cleaning tank and add water about DELBAG-Luftfilter GmbH
as thick as a finger to prevent the cleaning fluid from Schweidnitzer Str. 11-15
evaporating. Depending on the degree of contamination, D-1000 Berlin 31
the air filters should be vigorously rinsed out in the or
cleaning fluid several times until the dirt layer has been DELBAG-Luftfilter GmbH
removed. Heerdterbuschstr. 9
Then set up filter pads for drying. Immerse clean air D-4000 Dusseldorf-Heerdt
filters in Viscinol air filter wetting agent and allow wetting West Germany
Maintenance Intervals
Work required
Every 6 months
Every 3 months
Annually
Monthly
Weekly
Daily
Check exciter cooler vents X
Reliable operation of the turbine generator will be restarted in the same way as during initial startup.
ensured only if inspections and overhauls are carried out The assignment and number of BHEL product
at regular intervals so that any faults can be detected service personnel required for an inspection should be
and corrected before they result in costly failures. planned well in advance to enable BHEL to make the
Following each inspection, the next inspection should be necessary arrangements. In addition, the period available
scheduled. for execution of the inspection should be indicated.
Provided that commercial tools can be used and The spare parts stored for repairs and overhauls
that no special skills are required for the dismantling and should be checked at regular intervals. Components
erection work, the inspections can be performed by skilled packed in plastic sheeting mostly contain a desiccant
power station personnel. In all other cases, however, such which must be replaced of reactivated from time to time.
as for the inspection of the shaft seals and their auxiliaries,
the services of experienced BHEL product service Danger:
personnel will be required. Rotating components. These may cause
The shutdown of a turbine generator for inspection injury to persons. When working on generator
should be made in exactly the reverse order of startup. It or auxiliary equipment ensure that this is elect-
should be noted in particular that the hydrogen must be rically isolated and cannot accidentally be reconnected.
removed from the generator housing with carbon dioxide In single shaft configurations, do not open the
only. Should opening of the gas system or of the generator generator frame and do not start any work on the rotor
proper be required during an inspection, it is necessary or the bearings until the gas turbine and the steam turbine
to replace the carbon dioxide with air. as well as the generator have come to a complete
Following an inspection, the generator should be standstill.
The moisture absorption capacity of the desiccant 5.2 Land Transport or Sea Transport of Longer Duration
must be checked after arrival at site, after interruptions For land transport exceeding one month and for sea
in transit involving a storage period of more than one transport, the rotor should be packed in a closed, self-
month and during normal storage at the site (see Item supporting container. The setup for two-pole rotors
7.2). corresponds to Fig. 4.
The container bottom should have openings with
Make sure that sufficient replacement desiccant or
perforated-plate covers for ventilation and to prevent the
the necessary drying facility for reactiv:p.tion is available.
accumulation of water. In addition, inspection openings
After opening, the plastic sheeting cover should be
with covers should be provided on the long sides for
provisionally resealed, but must not be left In this
access to the desiccant pouches via the plastic sheeting
condition for more than 20 hours. hoses. An inspection opening at the exciter end should
For reactivation, the pouches should be dried in provide access to the contact pins on the exciter-end
a drying oven at a temperature of 110°C (230°F) end cover of the rotor for measurement of the insulation
for 12hours. If a drying oven is not available, the resistance of the rotor winding.
desiccant should be removed from the pouch spread out Prior to closing the container, the rotor should be
in a thin layer on a metal plate and dried at 110-130°C covered with 3mm (0.12 in.) thick pressboard panels and
(230-266°F) for several hours until the weight of the polythene sheeting, taking care to avoid the formation of
desiccant remains constant. The desiccant should then troughs in which water might accumulate. The container
be filled back into the pouches which are to be closed lid should be covered with tar board sanded on one side
and reinserted into the plastic sheeting covers as quickly and folding down over the edges not less than 200mm
as possible. Care should be taken to ensure that the (7.87 in.).
The total weight and the dimensions of the cargo
All circles pink: danger of corrosion 50 should be marked on the container. In addition the
hitching range should be color-marked. The complete
cargo should be covered with a tarpaulin for protection
Two circles pink: replace desiccant 40
against the elements.
Four-pole rotors requiring prolonged land transport
One circle pink: warning 30 or shipment by sea should be set up on a skid as
illustrated in Fig. 5. In contrast to the example shown in
Fig. 4. the hitch should be taken at a steel sleeve at mid-
Fig.3 Moisture Indicator length of the rotor. The lower half of the steel sleeve
(Exact Location Identification to be Entered in Handwriting)
should be connected to the skid.
Preventive Measures
Protective Materials and Setup
Purpose/
Phase Component
Land Transport Sea Transport
Short Distance, Shipment by Sea or
Transport Period Less Than One Month Transport Period More Than One Month
A
Corrosin Shaft Hard wax coating (e.g. Tecty1506) of sufficient thickness (dark-brown color). Additionally
protection of journals (1) protect areas of support in skid with two layers of wax-coated bindings and one layer of
shaft ends Couplings 3mm (0.12in.) canvas-reinforced rubber mat.
C Place wax-coated aluminium foil over entire range of rotor body (only for rotor body diameters
Rotor body (2) < 300 mm < 11.8 in.), due to difficult handling).
First pack-
ing of rotor Piace 3mm (0.12 in.) canvas-reinforced rubber mat, 2500 -3600 mm (98 -141 in.) wide
retaining (3) (dependent on length of rotor) around center of gravity; seal overlap seams with wax-
rings and coated bindings and steel bands; secure axial overlap seam with wooden lath.
rotor body Place lath grid on fabric mat, about 300mm (11.8 in.) narrower than (4), around two-thirds
(4)
in plastic of rotor circumference and secure at top.
sheeting
Retaining, (5) Place 0.2 mm (0.08 in.) polythene sheeting between shaft ends (1) and body ends (3) and
cover rubber mat (4), respectively; seal joints with wax-coated brindings at both ends; heat-seal
rings
(sufficient Fans seams.
for short- (waterboxes) Check plastic sheeting cover for tight sealing by inflation with air and recheck after two
(6)
distance hours.
transport up
to 20 hours Add desiccant per m2 (1 m2=1.2sq.yd.) of sheeting surface: shipping time up to 1 month:
500g (1.1 lb.); up to 3 months: 1000 g (2.2 lb.); up to 6 months: 1500 g (3.3Ib.). Plus 280g
and imme-
(7) (0.62Ib.) for each kg of wood and 35g (1.230z.) for each kg of foam material within plastic
diate instal- cover. Moisture indicators for relative humidity> 30 %, > 40 %, > 50 %.
lation)
(8) Place 0.2mm (0.008in.) polythene sheeting between shaft ends (1) and rubber mat (4)
D Rotor body over a 5.10 mm (0.2-0.4 in.) foam mat around top half circumference of rotor retaining
Protection and rings and rotor body.
of first pack- retaining
(9) Check heat-sealed and tightly wrapped plastic cover (9) for tight sealing as under (7).
ing C by rings
second
(10) Add desiccant as under (8).
plastic sheet-
ing cover
(11) Not required for land transport Place 0.2 mm (0.008 in) ploythene sheeting
E over a foam mat and cover entire rotor bet-
Rotor body
Protection ween shaft ends as under (9). With four-
and
of packings pole rotors, foam mat is split within range of
retaining
C and D by lath grid; insert plastic sheeting between
rings 3 mm (0.008 in) rubber boards. Check for
third plastic
sheeting tight sealing as under (7). Add desiccant as
under (8).
cover
F (12) Tightly sealed rotor (1) to (11) on skid with Tightly sealed rotor (1) to (12) in closed
Tightly
closed bottom under enclosure and self-supporting shipping container under
Transit sealed rotor tarpaulin. tarpaulin.
protection
Hitch point on rotor at lath grid in center of Hitch point on shipping container, in the case
G Complete (13) gravity after removal of enclosure. of four-pole rotors on steel sleeve at
Loading cargo midlength of skid.
H Complete Check outer packing. Replace desiccant, if necessary. Return check list with details
(15) on condition of packing and insulation resistance of rotor winding to consignor.
Receiving packing
of Cargo and rotor Prior to unpacking the rotor in a weather-protected location, a cold rotor must have
winding (16) ambient or dewpoint temperature plus 5 K safety margin to prevent moisture
condensation.
J Storage With packing for land transport, only in a hall kept at a moderate temperature. For
Storage area (17) outdoor storage, seaworthy packing plus additional precautions are required: storage
on well tamped and suitable reinforced ground and set on blocks for protection
against moisture, case under protective roof.
Complete During storage (including interruptions in transit), check outer packing for damage
packing (18) and tight sealing, insulation resistance of rotor winding.
and rotor
winding
K Rotor Maintain tight sealing of packing as long as possible until rotor is installed. Protection
(19)
Removal against condensation hazard by preventive measure (16).
from
storage
Desiccant Checking Requirements The results should be recorded in the table below. The
The absorbent capacity of the desiccant must be desiccant must be removed and replaced or reactived
checked after shipment has been completed and at inter- by drying, if necessary.
vals of one month during any subsequent storage period.
Moisture Indicator
outer packing
Shipping Replacement
component
identification Desiccant
Company
or of
storage of moisture in packing reactivation
Bottom Bottom Bottom
Name
(1 kg=2.2 ib.)
(30%) (30%) (30%)
Prior to TE 1
shipment
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
TE 1
TE 2
TE 3
2.3 Shaft Seals 3.1 Checking the Insulation with the Generator
Both shaft seals are mounted such that they are insulated. in an Excited Condition
To check the insulation resistance, follow the same
procedure as outlined for the labyrinth rings. It is to be
the two readings are not identical, the rotor grounding system
should be rectified first before taking any further readings to
check the insulation for shaft currents.
1. Bridge Instrument
If the shaft voltage can be exactly measured according
Fig.4 Measurement of Insulation Resistance With
to Fig. 2, the measuring brush on the shaft
the Generator In Non-Excited Condition
1. Leak Tightness Test of the H2 System with Air are to be thoroughly investigated. In such a case the
Having sealed the generator and having taken the usage of Diprol or any other foaming agent which is to
seal oil supply into operation, the generator, including be applied to the leak location assumed is recommended.
the connected gas supply system has to be leak tested Bubbles will indicate the relevant leak.
with compressed air. Provide the compressed air supply If sufficient leak tightness is established when testing
via the appropriate compressed air connection. with air, the generator can be filled with CO2 and
The test pressure should be equivalent to the subsequently with H2.
generator operating pressure. Use a precision gauge of If in exceptional cases, leak tests are performed with
class 0.6. The leak test should last for at least 48 hours. hydrogen, due to the reduced density of hydrogen, the
The vacuum pump is out of operation during the leak test. allowable leak rate may be about four times as high as
The H2 system is to be regarded sufficiently tight, if with air. Leakages are determined in such a case with
the air loss is below 1.5 m3/24 h = 62.5 dm3/h (n.s.) by the gas leak detector.
this test.
Determine the air losses as follows: 2. Leak Tightness Monitoring of the H2 System
with Hydrogen
0.2694*24 (p1 + pB1 p2 + pB2 In operation. the gas loss has to be checked
V= .VG. - continuously with respect to the appropriate hydrogen
Z 273 +T1 273 + T2 consumption. The uncontrolled escaping hydrogen
Where: volume may amount to 12 m3 (n.s.)*/24 h. In such a
V = air loss in m3 (n.s.)*/24 h case, it has to be noted that only the uncontrolled
273K escaping gas volume should be taken as reference for
0.2694 = tightness considerations. Continuous controlled gas
1013.25 mbar losses, e.g. will escape the electrical purity measuring
unit. Losses will also occur due to gas being discharged
z = duration of leak tightness test in h via the seal oil.
VG = generator volume in m3
(see information at Mechanical Data) 3. Leak Tests by the Gas leak Detector
Leak tests have to be performed, if the gas loss of
p1 = overpressure in mbar within the system when the unit is unallowably high. Use the gas leak detector
starting the leak tightness test [1].
p2 = overpressure in mbar within the system when 4. Controlled H2 Losses in the Seal Oil Tank
finishing the test Deduct the controlled losses from the total amount
pB1 = barometric pressure in mbar when starting of losses to determine the uncontrolled ones. Quite large
the test controlled H2 losses come up due to degassing of the
seal oil in the seal oil tank.
pB2 = barometric pressure in mbar when finishing Determining the losses across the seal oil tank may
the test take place by air (pressure increase measurement) at
generator standstill or with hydrogen (delta p
T1 = intermediate temperature of the gas measurement) in operation. Close the shut off valve
atmosphere in the generator in °C ahead of the vacuum pump for measuring.
when starting the test Pressure increase measurements start at an initial
T2 = intermediate temperature of the gas pressure of 0 bar (relative). The air escaping the seal oil
atmosphere in the generator in °C results in a pressure increase. Measurements should only
when finishing the test take place up to an over pressure of about 0.1 bar, as
the oil level decreases in case of higher pressures. Any
lower oil level falsifies the measurements due to the
In case of air losses exceeding 1.5 m3 (n.s.)*/24 h, enlarged free volume in the seal oil tank; furthermore,
the leaks are to be determined. the lower level detector is activated in case of decreasing
oil levels. resulting in switching off the seal oil pump.
* n.s.=in normal State at 00C and 0.013 bar acc : to DIN 1343
1. Measures to be Taken at Inspections, oil samples should be taken and analyzed to decide
Repairs or Checks whether the flushing oil charge can be used as ser-
When opening parts of the oil systems for inspection, vice oil change after treatment by the oil supplier.
repair or checking, make sure that no dirt is introduced Use of an oil grade intended for use as flushing oil
into the oil circuits. In the event of a contamination being only. Its properties, particularly its viscosity, are
unavoidable due to the work to be performed, take care matched to the special application. This oil charge
to reduce such contamination to a minimum and perform is completely drained on completion of the flushing
a thorough cleaning afterwards. procedure and replaced by a new service oil charge.
In case of more extensive inspections, it is The properties of the service oil and flushing oil must
recommended to drain the oil, to clean the oil coolers, be suitably matched.
the oil tank and the bearing compartments in the same
way as for initial operation of new plant, and refill the oil
via filters. After each inspection, the oil system should
be subjected to a short flush. It is recommended to install
screens in the throttle valves and to perform flushing for
12 hours. On completion of this flushing procedure, all
filters and screens should be cleaned again.
If the oil piping must be flushed the following
procedure should be used.
During an inspection, the Individual components of The air dryer or fan-forced heater should be arranged so
the generator are exposed to the ambient conditions that the air will circulate through the stator interior in a
which may result in hazards to these components. It is closed circuit for ventilation of the entire internal space.
therefore strongly recommended to take suitable The rotor should be protected in such a manner that
measures for preventing any exposure to moisture, especially the retaining ring area can be kept dry and
especially rain, snow, liquids of any kind and above ambient temperature level. The air dryer or fan-
condensation. Covering the components will not afford forced heater should be arranged so that the air will
sufficient protection. circulate in a closed circuit.
To avoid the above-mentioned hazards, the The cooling water should be drained from the
assembly work during an inspection should be coolers. The coolers should be cleaned, dried and
accomplished under protection from weather conditions. maintained in dry condition by suitable measures.
The generator should only be opened if an uninterrupted Normally, a condensation hazard can be recognized
execution of the work will be ensured and provided that with the help of a dewpoint measuring device. In case of
the necessary protective measures can be taken. After doubt, however, it is recommended to dry the components
opening of the unit and withdrawal of the rotor, the stator on a continuous basis in order to achieve a markedly
openings should be promptly reclosed. The stator should low dew-point temperature on these components, i.e. to
be dried by means of a portable air dryer or fan-forced maintain their temperature above ambient temperature
heater and kept above ambient temperature level. level.
Accompanying 2 Reference to special packing and request for restoration after opening
documents: due to customs or in-transit damage.
Damage to 3 Restore proper condition of dry packing immediately. For details, see
packing: description accompanying the cargo.
Storage area: 7 Indoor storage in dry building; outdoor storage in seaworthy packing,
under shelter, protected against precipitation/ground moisture.
Open generator 10 With danger of condensation (outdoor installations and open power
rotor Installed house) blow dry air from portable air dryers into rotor end windings
and slipring assembly.
Outdoor 16 Set down rotor under shelter and provide rotor areas between bearing
installatlon: journals with dry packing.
Preventive maintenance of generators serves to consideration of changes that are likely to occur after a
avoid major problems or damage while the unit is in relatively short service period.
service. The time periods given are guiding values.
Apart from its scope, the timing of an inspection is Depending on the scope of the planned work or inspection
important. To account for the deterioration and stresses findings, the inspection period is either shortened or
due to different modes of operation, the number of lengthened.
operating hours, the number of starts and the tuming
times are used as criteria in determining the intervals Influences
between the inspections. Scheduling of the Initial Inspection and of the
The intervals recommended in the following are the subsequent inspections mainly depends on the number
same as those indicated in the VDEW Recommendations of operating hours, the number of starts and the turning
for Intervals Between Generator Inspections [1] which times. The influences are considered according to VDEW
are based on the accumulated experience. This Foreword Recommendation for an equivalent operation time under
contains a large number of extracts from the VDE consideration of the machine output in four performance
Recommendations. groups.
The guiding values given in the VDEW Recommen-
dations are to assist the power plant owners/operators Tequlv = K1 .T1 + K2 .T2 + n.T3
in scheduling inspections, taking into account also own Tequiv t, Tequivr = Equivalent operating hours Subscript t
experience on the performance of their generators and K1 = Weighting factor for stress refers to total
that of sister machines. impact during normal operat. hours
operation since initial
Types of Inspection T1t,T1r = Operating time in hours commissioning
Depending on the scope, date and duration of the K2 = Weighting factor for
inspections, a differentiation is made between turning gear operation
T2t , T2r = Tuming gear operation Subscript r
Initial Inspection (II) time in hours refers to
Short Inspection (SI) (or Minor Inspection) nt, nr = Number of starts operat. hours
Intermediate Inspection (Inl) (or Medium Inspection) T3 = Weighted time equivalent belween two
Main Inspection (MI) (or Major Inspection) in hours per start main inspect.
Table 1: Types of Inspection, Features and Duration Table 2: Weighting Factors for the Different Power
Type Features Duration Output Ranges
II Maximal as Up to several
Main Inspection weeks Power
Rating K1 K2 K3
Output Range
SI Checks and measures required Days
based on observations during 1 SN> 600 MVA 1.0 0.5 20
operation and checks 2 250 < SN < 600 MVA 0.9 0.3 10
INI Like Short Inspections including A few weeks 3 50 < SN < 250 MVA 0.8 0.1 10
partial disassembly but without
4 SN < 50 MVA 0.7 0.1 5
removal of rotor
MI Like Intermediate Inspection but Several weeks
The recommendations given in the following apply
with removal of rotor
to normal operation without major disturbances.
The Initial Inspection is the first major inspection of Abnormal disturbances, such as close-in system faults,
the generator normally involving the removal of the rotor faulty synchronizing, asynchronous running and
and is an essential prerequisite for assuring high reliability inadmissibly high unbalanced load, may necessitate
on a long-term basis. shortening of the respective inspection interval or an
The removal of the rotor at the Initial Inspection immediate check.
Is not necessary for post-impregnated generator When scheduling inspections, also consider the
stators. An extensive visual Inspection through the following factors:
man holes Is urgently required. With these generators, Wear and deterioration of components
the extent of the Initial Inspection corresponds to the Deterioration of running behaviour
Intermediate Inspection. Frequency of load rejections associated with overspeed
The scope of work and checks to be performed should Earth faults or intertum faults in generator field circuit
be agreed upon with the manufacturer in good time. The Hydrogen, water or cooler leaks
date of the Initial Inspection should be determined under due Change in coolant flow rates .
Fouling of air-cooled generators
BHEL, Haridwar 2.5-1010-0004/1
Deterioration of shaft insulation 50 hours per shutdown, but subject to an annual
Type specific experience. maximum of the difference between 8 500 h/year and
the operating time, In some circumstances this may result
With proper performance of the generator and In shutdown times of 1 000 hours per year for operating
provided that the inspection findings obtained by the modes A, B and E.
preceding inspections (s) have been favourable, the The recommendation of a generally binding
intervals between inspections may be lengthened within inspection interval of 40 000 to 60 000 equivalent
reasonable limits. operating hours between Main Inspections for a medium-
sized turbogenerator (power output range 2) at peak load
Recommendation for Inspection Intervals (operating mode D) will result in an interval of 6 to 10
The Initial Inspection (II) after an equivalent operation time years.
10000 h < Tequlv t < 20 000 h
Table 4: Determination of the Equivalent Operating
The Main Inspection (MI) after an equivalent operating time
Hours for One Calendar Year with Differing
40 000 h < Tequlv r < 60 000 h
Operating Modes and Ratings
It is recommended that one or more Short and
Intermediate Inspections are performed between Main Power Output 1 SN > 600 MVA
Inspections. This result in a sequence of Short, Operat.
Intermediate and Main Inspections which can be selected mode T1 T2 n T1XK1 T2XK2 noXT3 Tequtv
flexibly at different intervals.
A + E 7000 500 10 7000 250 200 7450
This point of time is not dependance to the technical
requirements of the generator, but also to the most B 5000 2500 50 5000 1250 1000 7250
generator dependent moments of shut down periods of C 3000 5500 150 3000 2750 3000 8750
the machine set. D 1000 7500 300 1000 3750 6000 10750
Recommendatlons
By the mathematical calculation of inspection Power Output 2 250 MVA < SN < 600 MVA
intervals based on the equivalent operating time Operat.
Tequiv = K1 .T1 + K2. T2 + n.T3 (from Table 2) will be included mode T1 T2 n T1XK1 T2XK2 noXT3 Tequtv
the turning gear operation hours in addition to the number
A + E 7000 500 10 6300 150 100 6550
of starts and by classifying four groups of power output
ranges with different weighting factors. B 5000 2500 50 4500 750 500 5250
In this way an equivalent operating time is C 3000 5500 150 2700 1650 1500 5850
determined for the various operating modes. It reflects D 1000 7500 300 900 2250 3000 6150
the diverse operating influence and corresponds well with
experience. The equivalent operating times are
determined and compared for one calendar year Power Output 3 50 MVA < SN < 250 MVA
considering different operational modes in the four power Operat.
output ranges. mode T1 T2 n T1XK1 T2XK2 noXT3 Tequtv
Regardless of the four power output ranges, in
A + E 7000 500 10 5600 50 100 5750
principle five operating modes can typify turbogenerators
(Table 3). For each operating mode typical values are B 5000 2500 50 4000 250 500 4750
given for the load ranges, the annual operating time, load C 3000 5500 150 2400 550 1500 4450
variations and the annual number of starts providing such D 1000 7500 300 800 750 3000 4550
a characteristic order.
Table 3: Typical Operating Modes
Power Output 4 SN < 50 MVA
Annual
Oper- Annual
Operating Load Operat.
ating Load Ranges No. T1 T2 n T1XK1 T2XK2 noXT3 Tequtv
time Variation mode
Mode of Starts
in h A + E 7000 500 10 4900 50 50 5000
A base load > 7000 small 10 B 5000 2500 50 3500 250 250 4000
B lower 4000-6000 large 50
C 3000 5500 150 2100 550 750 3400
medium load
C upper medium 2000-4000 large 100-200 D 1000 7500 300 700 750 1500 2950
load
D peak load < 2000 small 300
Regardless of the above recommendations to perform
E operation in
the Initial and the Main Inspections after having reached
industrial > 7000 large 10
equivalent operating hours totals of Tequiv t or Tequiv r , the
power plants
maximum time (operating time + turning gear time +
Examples of the equivalent operating hours in a standstill time) between two Main Inspections, and also
calendar year for each of the five typical operating modes between Short and Intermediate Inspections, should not
are shown in Table 4 for the four power output ranges. exceed the period specified in Table 5 because of harmful
The turning gear time in the Table has been taken as long-term factors.
0 10 20 30 40 50 60 70 80
Fig.1 Typical Equivalating Hours of Turbogenerators Actual Operating Hours Tact ( 103 h )
Initial Inspection")
Minor Inspection
Major Inspection
Work required
") Deleted, unless a main inspection has to be performed at an earlier time than scheduled due to findings of visual checks of the generator
interior of special occurrences in operation (system fauft, terminal fault, faulty synchronization etc.).
The scope of inspection will depend on the appropriate findings.
1) Dissipation factor measurement, charging and leakage current measurement, and, in particular cases, high-potential test.
2) Normally required only at every second major inspection.
Initial Inspection")
Minor Inspection
Major Inspection
Work required
") Deleted, unless a main inspection has to be performed at an earlier time than scheduled due to findings of visual checks of the generator
interior of special occurrences in operation (system fauft, terminal fault, faulty synchronization etc.).
The scope of inspection will depend on the appropriate findings.
Minor Inspection
Major Inspection
Initial Inspection
Work required
General
Check cooling water inlet and outlet pipes, vent pipes, drain pipes and mountings of all coolers x x x
Check condition and performance of temperature and pressure measuring devices at all coolers x x x
Hydrogen Cooler
Clean H2 cooler on water side x x x
Check condition and, if required, recondition H2 cooler water channels x x x
Dismantle H2 cooler, check on water and gas sides, clean, if required, replace gaskets x
and perform pressure tests
Exciter Cooler
Clean exciterl cooler on water side x x x
Check condition and, if required, recondition exciterl cooler water channels x x x
Dismantle exciterl cooler, check on water and oil sides, clean, if required, replace gaskets x
and perform pressure tests
Minor Inspection
Major Inspection
Initial Inspection
Work required
Minor Inspection
Major Inspection
Initial Inspection
Work required
Minor Inspection
Major Inspection
Initial Inspection
Work required
Minor inspecttion
Major inspecttion
Initial inspecttion
Work required
Initial Inspec-
Minor Inspec-
Major Inspec-
Work required
tion
tion
tion
Check condition and performance of temperature gauges and alarms x x x
Replace gaskets at temperature measuring points x x x*
Check condition and performances of level meter system (liquid level alarm switches) x x x
Check condition and performance of grounding brush x x x
Major Inspection
Minor Inspection
Initial Inspection
Work required
Preservation measures will have to be taken when placed into operation once a week and the entire system
a adequately flushed with water-free oil. After activation of
hydrogen-cooled generator is to be shut down for a period the oil system, the shaft should be operated on the
exceeding two months. turning gear for approximately three to four hours.
The scope of the preservation work required
depends on the duration of the shutdown, on the overall The supply of water to the bending oil and seal oil
conditions in the vicinity of the unit and on the extent to coolers is not required during this period.
which checks and maintenance are possible during
such period. 3. Coolers
The preservation measures recommended in the All coolers should be drained on their cooling water
following are sufficient under normal conditions. High sides and dried by suitable measures. During the
relative humidity in combination with severe temperature outage, the drains and vents should be kept open.
changes involves the risk that the temperature of certain Caution: Never leave water-filled coolers standing idle
surfaces in the generator may drop below the dew point, for several weeks.
resulting in the possible formation of a moisture film For cooler drying, hot air or dry ambient air may be
due to condensation on these generator components. used which should be admitted by means of blowers
In such a case, special measures may be required for via the cooling water inlet/outlet flanges. A fan-forced
preservation of the rotor retaining rings [1] heater with a rating of 1 to 2 KW has proved satisfactory
for this purpose.
1. Generator Interior
The hydrogen gas should be removed from the 4. Bright Components
generator. The stator and rotor windings should then be All accessible bright components, e.g. exposed
protected against moisture by maintaining the generator shaft portions, should be protected with a suitable
interior at a moderate temperature or in dry condition by corrosion inhibiting oil or grease. e.g. Tectyl.
suitable means. This may, for instance, be achieved by
the provision of a hot air blower or dryer. The air should 5. Seal Oil and Gas Systems
be admitted and discharged via branches at the exciter Except for the work already mentioned, no
end and turbine end manhole covers. preservation measures are required on the coolers of
Prior to recommissioning the generator, the the seal oil system.
insulation resistances of the stator and rotor windings During the weekly activation of the seal oil system
should be measured and the windings dried, if required. for turning the shaft, the system should be inspected for
proper functioning by checking all operation values.
2. Bearings and Shaft Seals All valves in the gas system should be closed. No
No preservation measures are required on the additional measures are required.
bearings of the turbogenerator and on the H2 shaft seals.
However, the bearing and seal oil systems should be
1. Sicomet 50 Adhesive cutting take care that the profile does not suffer any visible
distortion and that the pressure applied after pulling
Profiled gaskets should preferably be cemented together the parts to be mounted is exerted on the area
together by means of Sicomet one-component adhesive. of cut (see arrow in Fig. 1). The faces to be cemented
This adhesive meets all requirements, its only together should be well roughened.
disadvantage being the difficulties encountered in storage.
Sicomet should be protected from moisture, heat 2.2 Cementing the Joint
and sunlight and should therefore be stored in a dry, cool The adhesive should be applied in drops on the joint
and dark place. To prevent an increase in viscosity and areas to be cemented together, using a plastic or metal
discoloring of the adhesive Sicomet is best stored at a spreader for obtaining a thin film. Immediately afterwards
temperature of -10°C. If stored under these Conditions, the joint faces should be assembled and located in
Sicomet has an unlimited working life. Defrost Sicomet position. Because of the short curing time of 10 to 30 s
prior to use and bring to room temperature. any readjustment will be almost impossible. After curing,
Repeated freezing and defrosting does not affect the any cement residue should be removed from the outer
bonding properties. The maximum storage time at room surface of the bonded joint by means of emery paper.
temperature is six months. The adhesive not used up Warning: Sicomet should only be used In well
must be stored at a temperature of -10 0C immediately. ventilated work areas. Care must be taken to avoid
body contact. In the event of contact with the eye,
rinse immediately with ample amounts of distilled or
2. Preparatory Work and Application of Adhesive drinking water to dilute the adhesive. The eye should
then be treated to soothe any inflammation and a
2.1 Preparatory Work physician immediately consulted.
The exact length of the profiled gasket is determined
by inserting it in the center of the sealing groove, allowing 2.3 Breaking the Cemented Joints
30 to 40 mm in length for overlapping at the joint. The Cemented joints which are to be broken should be placed
joint faces could be cut so that the overlapping portion to in a bath of either dimethyl-formamide for a brief period
be cemented is approximately 30 to 40 mm long. When or of ethylacetate for a longer time, resulting in swelling.
1. Labyrinth ring
2. Oil baffle
The labyrinth rings must be mounted after insertion 1. Lower half labyrinth ring
of the generator rotor and installation of the lower half 2. Bolted Joint
bearings, but before to installing the upper half end shields 3. Finning device
and baffle ring carrier. At first, the ring should be attached
to the lower half end shield only. After complete assembly Fig.2 Shifting Lower Half Labyrinth Ring in Position
of the upper half end shield, the inner labyrinth ring should
be bolted in position. Shift the lower half labyrinth ring in axial direction
At this stage, the generator rotor is not yet coupled against the flange of the end shield. Attach it provisionally
to the turbine rotor, and the hydrogen cooler sections by means of the two bolts at joint level, permitting the
are not yet installed. fitting device to be detatched afterwards.
When placing the upper half labyrinth ring in position,
To avoid contact with the shaft and the resulting flow make sure that the joints are not displaced and the taper
of shaft current the labyrinth rings must be insulated from pins can be easily inserted.
the end shields at the flanged points. Attention should The joint bolts, nuts and lock washers should then
be given to careful fitting of the insulation. After be inserted and uniformly tightened.
completion of the assembly work, the insulation of the Remove the two bolts provisionally inserted at the
labyrinth rings should be checked [2]. labyrinth ring end shield joint and shift labyrinth ring in
axial direction away from the flange up to the collar. With
2. Preparatory Work the labyrinth ring in position, insert the gasket and the
The labyrinth rings should be cleaned with a suitable insulation.
solvent. Clean the groove for the gasket and all fixing 4. Mounting Gaskets and Insulation
holes and oil drain holes in the lower .half labyrinth rings Prior to connecting the labyrinth ring to the end
with compressed air. shield, the insulation and gasket should be checked,
The mating upper and lower half labyrinth rings are marked replaced (if necessary), and placed in the proper position
TE and EE close to the joints and should be mounted [3].
accordingly. 5. Assembling Labyrinth Rings
The labyrinth rings should be provisionally assembled Shift labyrinth rings upto the flange of the end
and the length of the gasket determined and prepared[3]. shield. provide mounting bolts with insulating sleeves,
1. General
During initial installation or inspection of the unit the
radial clearances between the caulked-in seal strips of
the labyrinth rings and the shaft should be measured.
For required labyrinth ring clearances, see the binding
drawing Erection and Setting Clearances. If the actual
clearances are excessive, new seal strips should be
fitted to the labyrinth rings. To do this, the old seal strips
should be removed and replaced by new ones. New
seal strips are available from stock at BHEL Works.
2. Tools
The tools shown below are required for removal and
fitting of seal strips.
1. Scraper
2. Sharpening tool
3. Smooth file
Fig.3 Pulling Out Seal Strip
4. Caulking tool
5. Pincers
6. Turn-out tool
7. Drift key
8. Hammer
Fig. 9 Rescraping Joint Surface. Turning the inside diameter of the labyrinth rings
results in blunt seal strips The seal strips must therefore
be sharpened by means of a special sharpening tool prior
7. Turning Inside Diameter of labyrinth Ring to assembly. After completion of this work, the half
After color print control. the half labyrinth rings labyrinth rings should be bolted together again.
should be assembled according to the marks and then
turned on a lathe to suit the shaft dimensions and
Caution: Wear leather gloves while sharpening the
clearances specified on the drawing Erection and
Setting Clearances. strip to prevent injuries.
During manufacture and transport, the insulation of correction to an agreed reference temperature (formerly
the stator winding may have been exposed to moisture 75 °C) must be made.
which would reduce the insulation resistance of the An insulation resistance of 1 megohm per each
windings. The insulation resistance should therefore be kilovolt of rated voltage at 75 °C is normally attainable
measured prior to initial start-up. after prolonged without any difficulties.
shutdowns and after work on the windings. If required, New international standards specify an insulation
the generator should be dried until a sufficient insulation resistance of not less than 1 megohm per each kilovolt
resistance is obtained. of rated generator voltage at 40 0C.
A correction of the insulation resistance measured
1. Required Insulation Resistance of Stator at the winding temperature prevailing during the
Winding measurement to the above reference temperature can
be made using the diagram in Fig. 1.
If the insulation resistance measured is lower than
the specified minimum value, the neutral connections
must be separated and the insulation resistances of the
individual winding phases measured. During the test, the
other two phases which are not involved should be
grounded. If the insulation resistances of the individual
phases are likewise lower than the required limit value,
drying of the windings will be indispensable. Great
differences in the insulation resistance values are
indicative of local contaminations, e.g. insulators in bus
duct or terminal bushings. If practicable additional
connections should be separated.
If this measure does not result in an improvement, it
is recommended to obtain the services of a specialist
from the manufacturer’s works.
The epoxy resin insulation used for the stator wind- Should this not be the case, the generator will have to be
ing absorbs practically no moisture. Any reduction of the de-excited and the cause of the non-uniformity (e.g. poor
insulation resistance during transport, erection or a pro- contact of buses) removed.
longed shutdown is mostly caused by a moisture film on
the surface of the insulation. To prevent damage to the The stator winding temperature and the hot and cold
insulation, it will be necessary to check the insulation gas temperatures should be brought to the maximum
resistance of the stator and rotor windings prior to run- operating values by slowly raising the field current.
ning up the unit to full voltage. In case of an insufficient
insulation resistance being detected, a drying procedure During drying, the absorbent materia! in the gas
should be performed first. dryer should be carefully observed. When the gas dryer
Drying should preferably be carried out with the gen- filling is no lorger active, reactivation should be carried
erator filled with hydrogen, making sure that the gas dryer out.
is in operation and that the absorbent material is suffi- During drying, the generator should be occasionally
ciently active. de-excited and run down for measurement of the
The stator winding should be short-circuited at the insulation resistances. In the event of sufficient insulation
bushings by means of buses. The buses should be fitted resistances being obtained, short-circuit drying may be
so as to permit a measurement of the short-circuit cur- stopped.
rent by means of current transformers. Remove the short-circuit at the bushings. Following
Run up the turbine-generator to rated speed and this, the generator may be run up to full voltage.
excite generator. As a result of this, a current in accor- In the event of a prolonged shutdown of the
dance with the short-circuit characteristic will flow in the generator, it is preferred that the hydrogen filling be
stator winding. The currents in the three phases should retained in the generator, thereby eliminating surface
be of identical magnitude. moisture on the windings.
1. Leakage Test of Field Current Lead contamination. Careful cleaning is important so as not
Before starting overhaul work and H2 purging, check to damage any of the numerous insulated parts. It is,
H2 seals at the field current lead for leakage. To do this, therefore, recommended to make use of the services of
use a leak detector and check coupling flange between our experienced product service personnel who will
generator and exciter rotors and field studs at rectifier carefully remove any dirt accumulations below the
wheels for gas leakage. retaining rings and within the range of the end windings
If no H2 gas leak is detected, the exciter should be by means of a special vacuum cleaner. Any inexpert use
dismantled. The exciter rotor should be uncoupled from of compressed air involves the risk of cooling duct
the generator and a new leakage test of the central field clogging and of damage to insulated parts.
connection performed.
If a leak is detected during this leakage test, the
5. Contact Pins and Plug-in Socket Strips
manufacturer must be notified. The hydrogen should be
The contact pins and plug-in socket strips should
purged from the generator only after completion of the
be checked for arc erosion and proper contact
leakage test.
resistances. Proper seating of the contact pins on the
plug-in socket strips can be verified by visual examination.
2. Rotor Wedges and Retaining Rings
If the rotor is removed, examine it carefully. The
wedges and retaining rings should be inspected for proper 6. Coupling
condition. The coupling flange at the rotor should be checked
both at the guide flanges and at the fitting bolt holes.
3. Shaft Journals and Shaft Seal Contact Faces The coupling bolts should be inspected for proper
The shaft journals and shaft seal contact faces condition.
should be checked for grooves. If any irregularities are
detected, reconditioning should be carried out according
to instructions from our service personnel. 7. Insulation Resistance Measurement
Prior to recommissioning, the insulation resistance
4. Cleaning the Rotor of the rotor winding should be measured and, if necessary,
After each withdrawal, the rotor should be cleaned improved. Details are given elsewhere in this manual [1],
thoroughly, even if the visual inspection did not reveal any [2].
During manufacture and transport, the insulation of Note: When the generator Is filled with hydrogen,
the rotor winding may have been exposed to moisture make sure that the rotor shaft ends are properly
which would reduce the insulation resistance of the grounded during measurement and discharging.
winding. The insulation resistance should therefore be
measured prior to initial startup, after prolonged
shutdowns and after work on the winding. If required.
the generator should be dried until a sufficient insulation
resistance is obtained.
2. Flaw Detection
Ultrasonic examination of the shrink-fitted retaining
rings inevitably also involves the generation of spurious
echoes, resulting in difficulties in the interpretation of
the ultrasonic indications, particularly within the range
of the shrink fits and on shapes deviating from the
smooth cylindrical outline. Based on previous
experience and using special probe heads and.
reference blocks, the BHEL specialists are in a position fig. I Ultrasonic Examination of Rotor Retaining Ring
to determine with a high degree of probability the flaw
size from the indications obtained. According to
experience so far available, the detectable flaw size is
far below the critical flaw size that may result in a sudden
forced rupture. If the echoes reflected by a flaw are
markedly above the spurious echo level of the inner
periphery and can be interpreted as incipient cracks
with a high degree of probability, it is recommended to
pull off the respective retaining ring for further
examination.
The insulation resistance of insulated bearings resistance has been previously measured, the respective
should be measured prior to each inspection. The bearing should be inspected thoroughly for any damage
bearings should then be dismantled and cleaned by cathodic action. Clean the insulation at the bearing
thoroughly. Bearing sleeves and shaft journals should saddle, as otherwise the insulation properties are
be checked for proper condition. If grooves are detected affected. The inspection procedure described above
the manufacturer should be asked for advice whether should be performed at all sleeve bearings of the turbine
the bearings may be used further. If a low insulation generator.
The inspection of shaft seal rings and seal ring displaying signs of wear shall be replaced or
carriers is performed as follows: reworked.
If the components are not dismantled for the In addition, the contact surfaces shall be examined
inspection, the insulating effect of the shaft seal with for fractures and scoring marks. This is particularly
regard to the generator casing can only be measured required if parameters such as seal oil pressure, seal
via the shaft current. oil volume, H 2 side seal oil temperature, etc.
If the seal ring is removed, the clearances between displayed fluctuations in the operating period prior
seal strips of the labyrinth rings and the shaft must to the inspection. Liquid penetrant testing may be
be recorded prior to removing the seal ring. During performed to obtain more accurate results.
the removal, the condition of all shaft seal
components and particularly that of insulating Reassembly of the shaft seals should be performed
elements such as flange insulation and insulation with utmost care.
barriers shall be checked. During each inspection. a check should be made to
Following removal of the shaft seal, all components ensure that the seal rings are still sufficiently insulated
shall be cleaned thoroughly. Any components from the stator frame.
1. Draining 011 From Vacuum Pump Open exhaust filter and clean or replace the filter
Remove the oil drain plug to drain the oil from the element. Clean interior of filter housing and inspect float
pump. When the oil flow decreases, start and immediately valve for free movement. Clean oil filter in vacuum pump
stop the pump to drain the residual oil. after removal of the oil reservoir.
Push the two spring clips in outward direction each
and lift off the holding frame. Then carefully lift off the
2. Draining Oil from Drain Trap and Exhaust Filter filter. Clean filter or replace it with a new filter. Reassemble
Open drain cock at drain trap to drain the liquid from pump.
the trap [1]. Remove the oil drain plug from the exhaust
filter to drain the oil. 4. Filling Vacuum Pump With Oil
After the pump has been completely reassembled,
fill pump with oil via the intake port. Keep the pump
3 Cleaning Pump Components and Replacing Filters
running for not less than 10 minutes and then drain the
A wire mesh strainer placed In the intake port of the
oil. If the oil drained is clean, fill the vacuum pump and
vacuum pump serves to arrest coarse matter. This wire
the exhaust filter with grade N62 special oil or an
mesh strainer should be removed and cleaned.
equivalent mineral oil up to the maximum oil level marks.
After isolation of the cooling water inlet and outlet, and checked for proper operation.
the upper water channels should be removed and their If cleaning of the tube exterior should be required.
position marked. Use tube cleaning brushes to clean the tube bundle should be placed into a bath with a
the tube interior. suitable cleaning fluid. Cleaning by means of steam
Make sure that all deposits in the tubes and water using solvents is also possible. After each cleaning
channels are fully removed. Take care that the procedure, the tube bundle should be well rinsed with
protective coating on the tube surfaces is not damaged turbine oil inside and around the tubes to remove the
during cleaning, as this would promote corrosion. The last traces of the solvent. Use only new gaskets when
drain and vent holes in the water channels should be reassembling the seai oil coolers.
checked for freedom from deposits and dirt. The vent For additional details. see separate instructions
and drain cocks should be thoroughly cleaned [1].
4. Dismantling and Cleaning the Exciter 10. Checking the Contact Pins and Plug in Socket
Remove exciter rotor. The coupling flange at the rotor Strips
should be checked both at the guide flange and at the The contact pins and plug-in socket strips should
coupling bolt holes. Check coupling bolts for proper be checked for proper mechanical condition. If the silver
condition and take dimensions. plating of the contact pins shows signs of are erosion,
Any accumulations of dirt in the ventilating air ducts the contact pins require reconditioning and replating. A
of the rotor, at the diodes, fuses and heat sinks must be check should be made to ensure that the projecting
removed. Cleaning should be done very carefully to avoid contacts of the plug in socket strips are spuatly distributed
damage to the numerous insulated parts. If is therefore on the entire circumference of the contact sleeve.
recommended to remove these contaminations with a 1 2
brush cloth (non-lining) and a vacuum cleaner. Particular
care should be exercised when cleaning the porcelain
bodies of the diodes.
1. Insulation
2. Contact sleeve
3. Plug-in contact strip
Regular inspection work should include checking the would then no longer the ensured, resulting in a phase-
insulating sections between the diode heat sinks and to-phase fault in the main exciter circuit.
rectifier wheels [1]. Leakage paths may be formed at After removal of the fuses, the insulation resistance
these points as a result of dirt deposits, rendering the between points a and b or a1 and b1 respectively, can be
fuses connected after the diodes ineffective in the event measured by means of a megger, applying a voltage of
of a failure. 500 to 1000 V. The insulation resistance between the
In the event of a diode losing its blocking capability, heat sink and rectifier wheel should not be less than 10
an interruption of the respective bridge arm by the fuse MΩ.
1. Fuse
2. Heat sink
3. Diode
4. Rectifier wheel (negative polarity) Current path
5. Tension bolt
6. Terminal bolt
3 1 4
7. Hot air outlet
8. Rectifier wheel (positive polarity)
9. Insulation
10. AC lead
11. DC lead
Detail X
General Information
This includes information required in all parts
of the Manual,
Symbols
Abbreviations
Units
Bibliography
This includes the most important papers in
the field of turbogenerators.
Piping
Air
Shutoff valve, solenoid operation
Combustible gas
Control valve, piston operated
Non – combustible gas
Control valve, hydraulically or pneumatically operated
Lines, crossing
Level control valve
Lines, joining
Restricting orifice
Tee branch
Sight glass
Drain funnel
Heat Exchager and Tanks
Drain trough
Generator cooler (hydrogen / air)
Exhaust to atmosphere above roof
Electric heater, CO2 – flash evaporator
Shutoff valve
Liquid tank
Control valve
Gas bottle
Multi-way valve
Machines
Coupling, general
Electrical
Separator, general
Flow rate
Filter, general
Level
Air or gas filter, general
Moisture
Liquid filter, general
Pressure
Tubular element filter
Quality variables (e.g. O2 or conductivity)
Mixed – bed filter
Temperature
Ion exchange filter
Vibration
Gas dryer
Framing for valve and fitting identification
Measurement and Control
Limit of Supply
Component Limit
2.9-0210-0004/2
2.9-0210-0004/2
Turbogenerators Electrical Test on Stator Winding
With Vacuum Impregnated Micalastic
High-Voltage Insulation
1. The Insulation System of the Stator There are several methods of electrical testing. All of
Winding these are indicated below for the sake of completeness.
The Insulation system serves to insulate the However, for reasons to be explained in the following
generator stator bars, whcih are subjected to a high- sections, not all of these tests are suitable for checking
voltage potential of upto 30 KV, from each other and the insulation of large turbogenerators, especially those
from the grounded stator iron parts for reliable with water-cooled windings.
protection against the additional thermal and z Insulation resistance measurement (meggar)
mechanical stresses arising during operation.
For decades, Insulation system with a high mica z Recharging and leakage current measurment for
content of up to 65% have been and are still being exact determination of insulation resistance
used most successfully. Up to the mid-fifties. mica z Dissipation factor measurement
was predominantly bonded with shellac or asphalt. z Partial discharge measurements
Insulation systems of this type are greatly affected by
moisture and develop low Insulation resistances z High-potential proof tests
especially after a prolonged outage of the generator AC voltage
in a humid atmosphere. DC voltage
The present day system uses epoxy resin 0.1-Hz voltage
featuring a high resistance to mechanical, thermal
and electric stresses. 3. Insulation Resistance Measurement
The MIcalastic insulation consists of mica tapes Insulation resistance measurement is by far the
applied continuously from end to end on the bars, simplest and easiest of the available tests to perform to
including the end winding portions. Vacuum determine the integrity of the insulation. It is made with an
impregnation with epoxy resin provides an insulation instrument commonly known as meggar and supplying
system which is highly resistant to mechanical, a variable DC voltage between 100 V and 5000 V. The
thermal and electric stresses and also impervious to instrument is cailbrated for direct reading of the insulation
moisture. Drying the insulation prior to startup of the resistance in mega-ohms. The DC voltage for
generator will thus only be required to remove any measurement is generated by a hand-operated or motor-
moisture film on the surface. operated generator or by electronic means. This voltage
should be applied for not less than one minute prior to
2. Purpose and Kind of Electrical Tests reading the insulation resistance value to allow for the
The mechanical, thermal and electric strength of decay of the absorption current component with time
the insulation system is assured by numerous due to a polarization of the dielectric in the electric field.
laboratory tests performed prior to using the insulation This process, which follows an exponential function, is
in actual service on the generators and by the results
reflected at the instrument by a pointer deflection which
of service on the generators and by the results of
is initially fast and then gradually slows down. The
service experince.
results of this reading indicate only the presence or
During the manufacturing process until delivery
absence of a winding short to ground and that insulation
of the generator, a comprehensive quality verification
resistance is at a level above the accepted minimum
program is performed by subjecting the insulation to
limit. This test is performed prior to each startup of the
electrical tests. Unless the insulated parts in the
generator are stressed due to abnormal conditions unit and prior the each high-potential test on a winding.
during transport or during the installation and assembly On water-cooled generators with water filled winding
at the power plant, no electrical testing would be the relatively low resistance of the water in the hoses
required prior to placing a new generator into between the winding and ground potential is connected
operation. For safety considerations, the insulation in parallel to the true insulation resistance. A megger
resistance should, however, be checked by means reading would indicacate the resistance value of the water
of a meggar prior to each startup. in the hoses. Depending on the conductivity of the water and
It is a known fact that even the best insulaion the number of parallel connected hoses, this value may be
system is subject to aging during service, especially far below 1 mega-ohm and does not provide any
as a result of operational disturbances, such as voltage information of the magnitude of insulation resistance of
surges due to sudden short-circuits, etc. the winding. It merely serves to determine that there exists
During overhauls, the degradation of the insulation no direct short to ground.
and any damage due to accidental disturbances To determine the insulation resistance of water-filled
should therefore be asceratained by a visual windings by means of megger reading in the usual way,
inspection and by means of suitable electrical tests to
give assurance of trouble free operation for further
years.
BHEL, Haridwar 2.9-2300-0001/1
the water must be drained from the windings, and the factor measurement, partial discharges will occur
surface of the supply hoses requires thorough drying. which increase with rising voltage and result in a
4. Recharging and Leakage Current dissipation factor tip–up.
Measurement Mlcalastlc insultion is impregnated with epoxy
To determine the true insulation resistance of an resin under vacuum to be essentially void-free. In
insulation, some what larger and more complicated new condition, this insulation thus exhibits a
equipment is required, permitting also a determination dissipation factor tip-up of less than 0.001 for each
of the polarization index. For this test, a stabilized DC measuring interval of 20% of rated voltage.
power source and a micro ammeter are required, Prolonged exposure to thermal and mechanical
stresses and last but not least, the effect of partial
enabling the current to be measured as a function of
discharges may result in new separations and thus in
the test period under otherwise constant conditions
additional discharges. Measurement of the dissipation
and allowing the influence of temperature, moisture
factor as a function of the test voltage can therefore
and dirt to be determined and considered.
provide information on the aging of an insulation by a
In hydrogen-cooled generators, the ambient is quite
relatively simple method.
clean, and the winding is protected against moisture
Measuring the dissipation factor on individual
absorption, because, in contrast to air-cooled units,
winding components, such as bars, is mostly performed
these machines have a closed cooling circuit.
by means of a guarded electrode to eliminate the effect
In addition the insulation of Mlcalastlc -insulated
of leakage currents across the coil end. Such a guarded
generators is not subject to moisture absorption.
electrode system cannot be provided for complete
Recharging and leakage current behavior and the
winding which are mostly equipped with an end corona
insulation resistance, repectively, may merely be affected
protection. This effect must therefore be taken into
by dirt or moisture on the surface of the end winding.
consideration when evaluating the variation of the
On winding without water conductor cooling, this
dissipation factor with voltage.
test is just easy to perform as the megger reading.
The dielectric constant and the dissipation factor
However, to permit the use of this test also on water-
are measured with a Schering bridge.
cooled windings with water circulating in the windings
without affecting the recharging current or the
insulation resistance through the water in the multiple
parallel hoses from the winding to the ground, 500
MW generators are equipped with special device in
the water circuit, enabling the water manifolde to be
disconnected from the ground in a simple way. The
bushing hoses are equipped with contact sleeves to
compensate for the leakage current through the water
in the hoses.
Since, in addition to the leakage current, the
stabilized DC power source is also required to supply
the partial currents via the water in the hoses, i. e. up
to 40 mA dependent on the conductivity of the water,
the micro ammeter is inserted in the circuit through
which only this recharging current and the leakage
current of the winding insulation are flowing.
Fig. Schering Bridge
5. Dissipation Factor Measurement At balance, zero current flows through the bridge
The winding insulation system is primarily a
branch. The capacitance of the winding is then:
capacitive setup, with the winding copper costituting
one electrod, and the grounded frame the other
electrode. Such circuit is accessible for bridge method
of resistance measurement to determine the dielectric Cx = R4 . CN / R3
loss factor. Dielectric loss is defined as the ratio of
active power to reactive power. Inconnection with
insulation testing the dielectric loss indicate the
amount of electrical energy converted into heat in the and the dissipation factor:
insulation. tan delta = R4 . w. C4
The dissipation factor and capacitance of a solid To perform dissipation factor measurement on
insulating material are not dependent on the test voltage generator winding, disturbing error capacitances can
applied as long as there is no change in the conduction be eliminated with a universal capacitance/dissipation
mechanism. A change in the conduction mechanism of factor bridge using ancillary equipment for the initial
insulation materials occurs due to loss of bond between balancing adjustment. This scheme offers an effective
layers of insulation, with voids being formed in minute method for measurements on winding in a directly
cracks. As the voltage is increased above a certain level grounded stator.
(partial discharge start voltage) during the dissipation
2.9-2300-0001/2
6. Partial Discharge Measurements also on the aging of the insulation . They are indicative
The dissipation factor measurement described of the dielectric strength of the insulation with certain
in the preceding section covers the sum of the losses probability only.
occurring in the insulation voids due to partial A high-voltage test is an indispensible last
dichrages. Since partial discharge is a radio-frequency criterion for determining with assurance whether or not
phenomenon, this open up the possibility of using the insulation on a winding is suitable for continued
operation with sufficient reliability. The application of a
radio-frequency methods for detection.
high test voltage is especially recommended in all
Partial discharge measurements provide useful
cases where it is to be expected that the insulation
information for the detection of localized defects in may have suffered localized damages as a result of
winding components, such as the phase connector extremely high mechanical stresses due to a sudden
insulation system. This method is also used for short circuit or extremely high electric stresses due to
quality assurance during manufacturing. transients. A high-pontential proof test is also applied
in the case of serious aging as identified by a
dissipation factor measurement and if localized weak
points in the insulation cannot be ruled out.
Any breakdown occurring during a proof test indicate
that the winding is approaching the end of its service
ability. After removal of bars on which a breakdown has
occurred, the areas of the insulation most severely
affected by degradation can be assessed, permitting
scheduling of a suitable date for rewinding. If no breakdown
occurs during the proof test or following the removal of
already failed bars, this means that after completion of
the test even the weakest area of the insulation still has
a certain life expectancy which will be longer at the field
intensity arising during normal operation troublefree
operation at least for a certain service period following
the test and avoids the risk of a breakdown occurring
during operation together with the consequential damage
resulting from the high currents arising.
2.9-2300-0001/3
For this reason, it is necessary to use a multiplication has been specified.
factor to obtain nearly, equivalent searching ability as
an AC test. It is recommended that 1.7 times the AC Laboratory tests on new and aged insulation
RMS test voltage be used. systems have rendered greatly differing values of the
multiplication factor to be used both for DC testing
7. 30.1-Hz Voltage Test and 0.1 Hz testing to obtain equivalent results as a
test at power frequency alternating voltage. These
An AC high-potential test requires a large and multiplication factors are mostly considerably higher
heavy testing transformer which is capable of for new insulation system than for aged insulation.
providing also the reative power of the winding
capacitance, whereas for DC over-voltage testing From this, it may be concluded that the stress
smaller and lighter test equipment is mostly sufficient. mechanism during both DC testing and 0.1 Hz testing
To make use of the lower weight, while retaining the differs from that obtained by the use of an alternating
advantage of a field distribution corresponding to that voltage. Accordingly, the multiplication factor should
obtained with a power frequency test equipment, tests be selected under due consideration of ageing of
are also performed at a reduced frequency of 0.1 Hz. the winding insulation. However since the high-
Tests conducted at Swedish and American potential test serves to establish the life of the
laboratories have shown that the 0.1 Hz test voltage insultion, it appears more appropriate to use a power-
to be applied must be higher than the 50 Hz or 60 Hz frequency alternating voltage for the high-potential
test voltage to obtain equivalent test conditions as an test, if it is practicable to obtain and transport the heavy
AC test. For such tests, a multiplication factor of 1.25 test equipment.
Note : While carrying out tests like DLA, PD, Tan delta, HV on Stator winding, it is to be ensured that the external
vibration leads are isolated from the vibration lead-in plate provided in the stator casing.
2.9-2300-0001/4