Professional Documents
Culture Documents
APPD.
IPA
IPA
IPA
CERT.
RNB
RNB
RNB
CHKD.
ALP
ALP
ALP
ISSUED FOR CONSTRUCTION Vendor’s Name : AL RUSHAID CONSTRUCTION CO LTD
COMPANY Name : Al-Khafji Joint Operations
ISSUED FOR APPROVAL
HQ824PC09
HQ824PC09
JO/EWO
CAA
CAA
BY
RESULT CODE : A B C D E
22-DEC-2018
24-FEB-2018
FI FA FC AB NA
28-Jan-2018
NEXT STATUS :
DATE
RESUBMISSION DATE :
RESP. DEPT./PERSON :
REVIEW DATE :
NO
DATE……………..... A: Approved without Comment; B: Approved with Minor comment ; C: Revise & Resubmit
; D: Not Approved ; E: No Subject to Review
CHKD BY…………….
BY……………………
DATE……………......
APPD. FOR. CONSTR
BY……………………
DATE……………......
CERTIFIED
BY……………………
DATE……………......
TABLE OF CONTENTS
Page
1. PURPOSE 3
2. SCOPE 3
3. DEFINITIONS 3
4. REFERENCE DOCUMENTS 3
5. RESPONSIBILITIES 3-4
ARCC Page 2 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
1.0 PURPOSE
1.1 This method statement shall provide ARCC of minimum guidelines to carry out
Scaffolding works required to allow safe means of access to work and accident free
environment for KJO Global Gas & NGL Recovery & Handling Project, to ensure
that the work is carried out safely and in accordance with IFC drawings and
JGC/KJO Project Specifications.
2.0 SCOPE
2.1 This method statement cover the following:
2.1.1 Installation of required safety working platform.
2.1.2 Proper control and utilization of scaffolding materials to avoid dismantling and
re-installation.
2.1.3 All system scaffolding erected, pipe and coupler scaffolding dismantling and
any alteration/modification on project as required.
3.0 DEFINITIONS
5.0 RESPOSIBILITIES
5.1 Project Manager shall be responsible for the implementation of this method
statement.
5.2 Safety Supervisor shall be fully responsible to ensure that the all works carried out at
the site meet the JGC/KJO and those of the local Health, Safety, Environment (HSE)
and Security Standard
5.3 Scaffolding Supervisor shall be in accordance with G.I. 008_001, responsible for the
supervision and implementation at site. Scaffolding Supervisor; to ensure of the
following:
5.3.1 All workers and foreman are conforming to project safety procedures
/regulations.
5.3.2 There is a safe access provided for scaffolders to work.
5.3.3 All scaffolds are erected in accordance with project scaffolding procedure.
5.3.4 Materials and workers are sufficient to meet site scaffolding requirements.
ARCC Page 3 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
5.3.6 All documents needed was discussed and disseminate to pre-talk (PPE’s
inspection, scaffold tagging system, work request, safety report, etc)
5.4 Scaffolding Foreman; to ensure of the following: Supervision of any scaffold
erection, dismantling
Supervision of any scaffold erection, dismantling, alteration or modification
must be supervised by a SA Certified Scaffolding Supervisor.
5.4.1 To oversee scaffolding activities under his area of responsibility.
5.4.2 Scaffolding crews can meet production target.
5.4.3 Scaffolders are trained for their assigned task.
5.4.4 Identify scaffold materials needed for the job.
5.4.5 Erected scaffolds are complete and in safe manner.
5.4.6 Correct tag is attached and signed off to each scaffold.
5.5 Certified scaffolding inspector qualification shall be submitted to JGC/KJO
5.5.1 Inspection of scaffolding at all working level upon notification from
supervisor that scaffold is complete.
5.5.2 Issuance of scaffolding tag in full compliance with the procedure.
5.5.3 Update as required, modification work or adverse weather conditions.
5.5.4 Erected scaffold structures shall be inspected daily prior to use for stability
and safety by competent scaffolder.
5.5.5 Certified scaffolding supervisor shall inspect and revalidate the scaffold tag
every seven days.
5.5.6 Ensure scaffold materials are of the standards for their purpose.
ARCC Page 4 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
ARCC Page 5 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
7.2.4.4 Scaffolding pipes, boards, and coupler shall be lifted using ¾”Ø rope
and bolt bag during installation.
7.2.4.5 Each platform on all working level shall be fully planked and
provided with guardrails (mid and top rails).
7.2.4.6 Platform`s toe board shall be secured with single clamp. Secure all
scaffold board and lapped boards down with tie-wire.
7.2.4.7 Access ladder shall be provided in every platform. Ladder shall be
positioned in either vertical straight or slope with 1:4 angle ratio
depends on situation. Aluminum ladder shall be fixed by rope
lashing on top and single clips on middle and bottom whereas wood
ladder shall be fixed/secure with at least ⅜”Ø nylon rope or tie-wire.
7.2.4.8 In every platform with a ladder, a self closing gate on top of it shall
be installed with drop bar attached to the railing.
7.2.4.9 Housekeeping at worksite must maintain as installation progresses.
Excess material shall be removed from the platform.
7.2.4.10 Scaffolds shall be inspected by certified Scaffolding Inspector and
provided with green tag upon acceptance.
7.3 Types of Scaffolding to be installed applicable for the Project. Refer to G.I. 0008_001
for General Requirements prior to Scaffolding erection.
7.3.1 Cantilever Scaffolding
7.3.1.1 Install transom using beam clamp tightly and properly attach to
flange of the beam/column.
7.3.1.2 Install ledger as a main load bearer of the platform.
7.3.1.3 Diagonal support of the bracing shall be installed, attach to the
ledger and fix with double coupler.
7.3.1.4 Install wood plank and provide toe boards whereas fixed with single
clip.
7.3.1.5 Install railing along the perimeter of the working platform.
7.3.1.6 Access ladder will be attached to the scaffold tube, secure with at
least ⅜”Ø nylon rope or tie-wire at the top, fix with single coupler
with drop bar or swing bar.
7.3.2 Independent Scaffolding on Foundation Pedestal Works
ARCC Page 6 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
ARCC Page 7 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
7.3.5.7 Ladders will be set at a working angle of 75º, 1:4 ratio to horizontal
and extent of 1 meter, 5 rungs above the platform to provide
adequate step off point.
7.3.6 Drop bar at the access landing platform entrance of the scaffold shall be
provided.
7.4 Dismantling
7.4.1 Upon completion of works on scaffolds and request for removal, scaffolds
shall be dismantled in opposite of scaffolding erection procedures. The last
piece of scaffold materials that has been installed will be the first to be
removed. Refer to G.I. 008_001 for Dismantling requirements
7.4.2 Alterations Modification as per G.I 008_001
8.5 Certified permit receiver and work-in-charge shall be at work site during the
execution of work.
8.6 Full body harness shall be worn at all times when working at elevated platforms 1.8
meters and above with double lanyards and shock absorbers, 100% tie-off to be
maintained.
8.7 A ½” Ø wire rope must be provided for safety lifeline.
8.8 Safe access and required safe guard are in place.
8.9 Scaffolding bags shall be used to lift all scaffold couplers while in erection.
8.10 Scaffold tag system will be in place to indicate the scaffold condition and scaffolding
supervisor shall maintain the tag. “RED TAG” will be displayed during scaffolding
erection indicating that the scaffold is unsafe and not to be use. “GREEN TAG’ will
be displayed if the scaffolding is safe for use. “YELLOW TAG’ will be displayed if
the scaffolding is incomplete and unsafe for use.
8.11 For confined space work, these must be considered:
ARCC Page 8 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
ARCC Page 9 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
ARCC Page 10 of 11
Originator: Approved By:
SCAFFOLDING INSTALLATION
CA Andal IPA
Doc Rev
3040-MS-SCAF-001 No. B Date: 21-12-18 Date: 21-12-18
No.
ARCC Page 11 of 11
INITIAL RISK RESIDUAL
ACTION
Sl. No.
3 Installation, modification, Unsecured scaffold tubes, 4 3 12 Secure appropriate work permit 4 1 4 Job
dismantling of scaffolding accessories and other prior to start of work. Supervisor
platforms / structures. materials. Ensure STARRT are properly
accomplished and supervisor to
discuss on the group all the
possible hazards indicated with all PTW
the control measures. Receiver
Provide appropriate visible danger
signages during erection,
modification and dismantling of
scaffolding platforms / structures to
warn other personnel nearby.
Refrain storing materials that could
slip from the top of scaffold
platform to the ground.
Use pulley and erection / bolt bag
in hauling materials at the top of
scaffold. Throwing scaffold
accessories are not allowed when
erecting nor dismantling.
Scaffolder’s hand tools should
have retaining string / rope to
prevent from falling.
Scaffold shall have a toe board
installed in standard heights.
In case of special scaffold, an
engineered design shall be secured
and analyzed prior to erection.
INITIAL RISK RESIDUAL
ACTION
Sl. No.
7 Reinstatement of Works / Tripping Hazards 2 2 4 Tidy up area at each end of work 2 1 1 Job
Housekeeping. shift. Maintain good housekeeping. Supervisor
Remove all debris from site before
and after activity as minimum and
maintain.
Arrange all materials in its PTW
designated location only, grouped Receiver
into types, uses, and neatly stocked
pile.
Designate housekeeping crew and
equipment for collecting and
removing waste and segregating
different materials
INITIAL RISK RESIDUAL
ACTION
Sl. No.
1 2 3 4 5
Scale No.
Severity
Environment (E)
Unlikel
Reputation (R)
Personnel (P)
Asset (A)
Unlikely (Could e (Probably Likely
(Only in occur at (Might occur in (Expected
exceptional some occur at normal in normal
circumstance future some time circumstance circumstan
s-0.01%) time – – 1%) s – 10%) ces-100%)
0.1%)
Insignificant
Slight
injury or health Slight Slight
1 (less than 1 2 3 4 5
effect(First Aid (<5K) (local)
10barrels)
Case)
Minor
Minor injury or
Minor (< $5K
health effect Limited
2 (10 to 25 but less 2 4 6 8 10
(Medical Treatment (provincial)
barrels) than
Case)
$100K)
Medium
Moderate injury or Medium
(<$100K
health (Localized)(>2 Considerabl
3 but less 3 6 9 12 15
effect(Restricted 5 but<2,500 e (Regional)
than
Duty Case) barrels)
$1M)
Major
Major
Major injury or ($1M or
(2,500 barrels
4 health effect(Lost more but National 4 8 12 16 20
but <5,000
Time Incident) less than
barrels)
$10M)
Catastrophic
Massive Extensiv
injury or health Internationa
5 (>5,000 e 5 10 15 20 25
effect(Single/Multip l
barrels) (>$10M)
le Fatality)
Comment Resolution Sheet
Contract No. : HQ824PC09 COMPANY Document No.: Vendor Document No.: 3040-MS-SCAF-001_B
GK0920-0142-JGL-
JGC Job Code: G-K092-00-0000 COMPANY Transmittal No.
Contractor Document No. V-3100-001-A-112_B ARC0008-RTN
Project Name: Globar Gas & NGL Recovery and Handling Project Rev. No. : B Date: 24-Feb-18
CONTRACTOR Contractor /
Sl. CONTRACTOR COMPANY Closure Remark JGC / Vendor Response
Page. No. Contractor Comments Commented Vendor JGC / Vendor Response
No. Reviewer (If any) (If any)
Date Response Date
KJO Proj. Engr.
5.5 Certified scaffolding inspector qualification
1 4 Ahmed M. Al- 6-Feb-18 12-Feb-18 Client Comments Incorporated
shall be submitted to JGC/KJO
Ghamdi
7.3 Types of Scaffolding to be installed applicable
KJO Proj. Engr.
for the Project. Refer to G.I. 0008_001 for
2 4 Ahmed M. Al- 6-Feb-18 12-Feb-18 Client Comments Incorporated
General Requirements prior to Scaffolding
Ghamdi
erection.
KJO Proj. Engr.
3 4 Item no. 8.16 Deleted Ahmed M. Al- 6-Feb-18 12-Feb-18 Client Comments Incorporated
Ghamdi
JGC CNS M.
3 4 4.1 Saudi ARAMCO Scaffold Safety Handbook 6-Feb-18 12-Feb-18 Client Comments Incorporated
Guinita
Page 1 of 2
Document Title: METHOD STATEMENT FOR SCAFFOLDING WORKS
CONTRACTOR Contractor /
Sl. CONTRACTOR COMPANY Closure Remark JGC / Vendor Response
Page. No. Contractor Comments Commented Vendor JGC / Vendor Response
No. Reviewer (If any) (If any)
Date Response Date
7.1.1 Scaffolding materials shall already been
inspected prior to delivery at site. All scaffolding
materials should be examined by scaffolding
supervisor and be fit to use. Any material found JGC CNS M.
3 4 6-Feb-18 12-Feb-18 Client Comments Incorporated
to be in bad condition will be remove from site. Guinita
Refer to G.I. 0008_001 for General Requirements
prior to Scaffolding erection.
Page 2 of 2