You are on page 1of 7

DPR-BRIDGE

ESTIMATING STEEL QUANTITY OF ABUTMENT

Span Arrangement : 2 x 18.75


Bar Total Total
Mark as Dia. Total wt wt of Total wt
per of bar Spacing Length Width No. of Length Wt. of bar Total Wt. single both with
Sr.No. Particulars Drawing (mm) (mm) (m) (m) bar (m) (kg/m) (t) abut. abut. wastage

RCC PILES
1
Abutment A1-A2

7 25 20 132 2640.0 3.86 10.19


8 10 250 3.8 20 486 1832.2 0.62 1.13 11.32 22.63 24.89555

PILE CAP
2
Abutment A1-A2
1 20 125 7.1 8.7 71 504.1 2.47 1.24
2 20 125 10.7 5.1 42 449.4 2.47 1.11
3 16 125 7.1 8.7 71 504.1 1.58 0.80
4 16 125 10.7 5.1 42 449.4 1.58 0.71
5 16 250 28.2 1.7 8 225.6 1.58 0.36
6 10 150 32 5.1 35 1120.0 0.62 0.69 4.91 9.82 10.79969
3 Abutment Shaft
9 12 150 7.05 2.05 15 105.8 0.89 0.09
10 12 150 7.05 2.05 15 105.8 0.89 0.09
11 20 150 4.80 6.45 44 211.2 2.47 0.52
12 25 150 4.80 6.45 44 211.2 3.86 0.81
13 12 4.80 6 28.8 0.89 0.03 1.55 3.10 3.409772
4 Abutment Cap
15 20 6.65 16 106.4 2.47 0.26
16 12 6.65 6 39.9 0.89 0.04
17 10 150 6.4 6.45 44 281.6 0.62 0.17 0.47 0.94 1.038422
Dirt Wall with
5
Bracket
18 10 150 3.25 6.45 44 143.0 0.62 0.09
19 16 150 3.95 6.45 44 173.8 1.58 0.27
20 10 150 6.75 2.25 16 108.0 0.62 0.07
21 10 150 6.75 2.25 16 108.0 0.62 0.07
33 12 6.45 7 45.2 0.89 0.04
34 10 150 0.8 0.6 10 8.0 0.62 0.005
35 12 150 2.1 6.45 44 92.4 0.89 0.08
36 12 6.75 3 20.3 0.89 0.02 0.64 1.28 1.411205
6 Seismic Block
41 12 150 2.4 0.9 14 33.6 0.89 0.03
38 16 150 2.3 0.75 12 27.6 1.58 0.04 0.07 0.15 0.161659
Return Wall
7
22 10 150 6.00 2.25 32 192.0 0.62 0.12
23 12 150 6.00 2.25 32 192.0 0.89 0.17
24 12 150 3.05 2.05 30 91.5 0.89 0.08
25 10 150 3.05 2.05 30 91.5 0.62 0.06
26 10 150 3 5.00 70 210.0 0.62 0.13
27 12 5.00 6 30.0 0.89 0.03
28 12 150 2.15 2.95 42 90.3 0.89 0.08
29 10 150 2.15 2.95 42 90.3 0.62 0.06
30 10 150 1.16 1.25 20 23.2 0.62 0.01
31 12 150 1.16 1.25 20 23.2 0.89 0.02
32 16 3.9 6 23.4 1.58 0.04
37 12 3.85 6 23.1 0.89 0.02
39 10 150 1.41 1.72 26 36.6 0.62 0.02
40 12 150 1.41 1.72 26 36.6 0.89 0.03 0.87 1.73 1.907171

Total wt. = 19.83 39.66 43.62

Formation level 104.5


Abutment pile cap top level 100

Ht. of dirt wall 2.45


Ht. of shaft = 2.05
thickness of pile cap= 1.8
Pile cap= 8.7 x 5.1
DPR -BRIDGE
ESTIMATING CONCRETE QUANTITY OF ABUTMENT
Span Arrangement : 2 x 18.75

Length Height Quantity


Sr.No. Description No. Width (m)
(m) (m) (m3)
1 Pile Column 12 3.77 0.3 20 271.43

2 Pile Cap 2 8.7 5.1 1.8 159.73

3 Abutment Shaft 2 6.45 0.8 2.05 21.16

4 Abutment Cap 2 6.45 1.4 0.5 9.03

5 Pedestal 6 0.8 0.6 0.3 0.86

6 Dirt Wall 2 6.45 0.3 2.45 9.48

7 Bracket 2 6.45 0.3 0.45 1.74

8 Straight portion of Return Wall 4 0.4 3.5 4.50 25.20

9 Cantilever portion of Return Wall 4 0.4 0 0 0.00

10 Seismic Block 4 0.75 0.45 0.9 1.22

11 Haunch b/w return wall & abut. Shaft 4 0.3 0.15 4.50 0.81

12 Approach Slab 2 5.65 3.5 0.30 11.87

13 Crash Barrier 0 38.72 0.00

Quantity of shaft = = 21.16 m3


Quantity of return wall = 26.01 m3
3
Quantity of shaft with wastage = 22.2138 m
3
Quantity of cap = 4+5+6+7+10 = 22.33 m
3
Quantity of cap with wastage = 23.4486 m
3
Qt. of app. Sl. & cr. ba. =12+13 = 11.87 m
3
Qt. of app. Sl. & cr. ba. With wa. = 12.45825 m

Ht. of dirt wall 2.45 m


Pile cap= 8.7 x 5.1 m
thickness of pile cap= 1.8 m
DPR-BRIDGE
ESTIMATING STEEL QUANTITY OF PIER

Span Arrangement : 2 x 18.75

Total
Bar Mark Total Wt. of wt Total wt Total wt
as per Dia. of bar Spacing Length Width No. of Length bar Total Wt. single of all with
Drawing (mm) (mm) (m) (m) bar (m) (kg/m) (t) pier piers wastage
PILE CAP

1 20 125 10.7 5.1 42 449.4 2.47 1.11


2 20 125 7.1 8.7 71 504.1 2.47 1.24
3 16 125 10.7 5.1 42 449.4 1.58 0.71
4 16 125 7.1 8.7 71 504.1 1.58 0.80
5 16 28.2 7 197.4 1.58 0.31
6 10 150 21 5.1 35 735.0 0.62 0.45 4.63 4.63 5.089404
RCC
PILES
7 20 20 150 3000.0 2.47 7.41
8 10 250 3.7699 20 486 1832.2 0.62 1.13 8.54 8.54 9.392219
Pier Shaft

9 12 100 10.51 4.05 42 441.5 0.89 0.39


10 20 6.95 32 222.4 2.47 0.55
11 20 6.95 32 222.4 2.47 0.55
12 20 6.95 14 97.3 2.47 0.24 1.73 1.73 1.904063
Pier Cap

13 16 6.25 6 37.5 1.58 0.06


14 16 7.50 6 45.0 1.58 0.07
15 12 150 5.40 2.5 18 97.2 0.89 0.09
16 12 250 10.80 3 13 140.4 0.89 0.12
16a 12 150 10.80 2 15 162.0 0.89 0.14
17 25 8 22 176.0 3.86 0.68
20 16 8.3 9 74.7 1.58 0.12
22 16 2.00 6 12.0 1.58 0.02 1.30 1.30 1.431749
Seismic Block transverse
18 20 100 1.7 1.9 20 34.0 2.47 0.08
19 16 100 1.8 1.9 16 28.8 1.58 0.05
21 12 150 1.55 0.9 14 21.7 0.89 0.02 0.15 0.15 0.163626
Seismic Block longitudinal
18 20 100 1.7 1.2 13 22.1 2.47 0.05
19 16 100 1.8 1.2 16 28.8 1.58 0.05
21 12 150 1.55 0.9 14 21.7 0.89 0.02 0.12 0.12 0.131305

Total wt. = 16.47 16.47 18.11

Formation level 104.5


Pier pile cap top level 98

Ht. of pier wall 4.05 m


Pile cap= 8.7 x 5.1 m
thickness of pile cap= 1.8 m
thickness of pile cap= 1.8 m
DPR -BRIDGE
ESTIMATING CONCRETE QUANTITY OF PIER
Span Arrangement : 2 x 18.75

Length Height Quantity


Sr.No. Description No. Width (m)
(m) (m) (m3)
1 Pile Column 6 3.77 0.3 20 135.72

2 Pile Cap 1 8.7 5.1 1.8 79.87

3 circular sides of pier column 1 2.51 0.2 4.05 2.04

4 Straight portion of Pier Wall 1 0.80 4 4.05 12.96

5 Square portion of Pier Cap 1 2.1 7.5 0.5 7.88

6 Trapezoidal portion of Pier Cap 1 1.55 7.5 0.5 5.81

7 Pedestal 6 0.6 0.8 0.3 0.86

8 Long. Seismic Block 2 0.5 1.2 0.9 1.08

9 Trans. Seismic Block 4 1.9 0.45 0.90 3.08

TOTAL = 249

Quantity of shaft = 3+4 = 15.00 m3

Quantity of cap = 5+6+7+8+9 = 18.71 m3

thickness of pier wall 0.8 m


Ht. of Pier wall 4.05 m
Pile cap= 8.7 x 5.1 m
thickness of pile cap= 1.8 m
Calculation of Quantities for Protection work :
Span Arrangement : 2 x 18.75

1. Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification
(Granular material) :

= (8.7-2*0.4)x3.5x6x2 = 331.8 cum

2. Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall
and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification
:

= (8.7-2*0.4)x6x0.6x2 = 56.9 cum

3. Providing and laying Pitching on slopes laid over prepared filter media including boulder apron laid dry in front of
toe of embankment complete as per drawing and Technical specifications :

= 4 x 10 x 6.75 x 0.6 = 162.0 cum


4 x 3.5 x 4.5 x 0.6 = 37.8 cum
2 x 6.4 x 4.5 x 0.6 = 34.6 cum
Total 234.4 cum

4. Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical
specification :

4 x 10 x 6.75 x 0.3 = 81.0 cum


Total 81.0 cum