D ependable N A ffordable Remodeling

Dan Trevino (210) 902-7372

February 19, 2019

Mrs. Rosie Cruz


9707 Fortune Ridge
Converse, TX 78109
(210) 508-4308

PROPOSAL

WATER AND MOLD DAMAGE


Removal*
Description of Work

Kitchen Area
1. Install 6 mil plastic sheeting secured with tape in two sections of the kitchen from ceiling to
floor, to closing it off from the rest of the house. One section behind the sink area and another
section in front of the sink area, extending to the adjacent walls. There will be a centralized
neutral zone between the above described sections for decontamination use by employees to
ensure proper mold removal techniques are adhered to.
2. Tightly cover all appliances and cabinets with 6 mil plastic and tape.
3. Cover and seal all flooring in kitchen with hardboard paper and plastic, secured with tape.
4. Cut out sections of sheetrock on ceiling and walls where necessary to determine the amount of
water and mold damage. This will expose the upstairs master bath subfloor as well.
5. Remove light fixtures and upper cabinets where necessary to determine decontamination and
reinstallation versus replacement.
6. Remove all contaminated and damaged areas; this includes sheetrock, studs, joists, etc.
Note: Any contaminated materials that we are unable to remove will be treated with an
antimicrobial agent then will be left to dry. Once dry they will be coated with a sealer.

Upstairs Master Bath


1. Install 6 mil plastic sheeting secured with tape from ceiling to floor, closing off the bath area
from the closet and bedroom.
2. Tightly cover tub and all cabinets with 6 mil plastic and tape.

Choose DNA Remodeling because your satisfaction is in our blood!


Page 1 of 5

Initials _______
D ependable N A ffordable Remodeling
Dan Trevino (210) 902-7372

3. Remove all tile and walls where needed in shower area including sheetrock on toilet side of
shower.
4. Remove bench and glass on tub side of shower.
5. Remove glass door and shower pan.
6. Remove tile on floor all around shower.
7. Remove toilet and tile under toilet.
8. Remove all contaminated and damaged subflooring.
9. Remove all contaminated and damaged studs, floor joists, baseboards and sheetrock.

*Note: Any unforeseen issues that arise during demo will be discussed
with the homeowner. An example would be the discovery of
additional wood rot and/or mold . These issues would require
more time and materials, therefore, a change order would be issued
for additional work upon agreement with the homeowner.

Repair and Replace


Description of Work

Kitchen Area
1. Replace all sheetrock and treat for mold as needed.
2. Tape, float, texture and paint where needed.
3. Install new light fixture.

Upstairs Master Bath


1. Install new floor joists where needed.
2. Treat all floor joists, studs, subfloors and sheetrock for mold as needed.
3. Install new subfloor where needed including backer board.
4. Install new studs in shower area where needed.
5. Install new plumbing fixtures in tub, shower and toilet areas including toilet flange.
6. Install new tile on floors where needed.

Choose DNA Remodeling because your satisfaction is in our blood!


Page 2 of 5

Initials _______
D ependable N A ffordable Remodeling
Dan Trevino (210) 902-7372

7. Rebuild shower area.


 Install new shower pan and drain
 Install new shower bench
 Install backer board
 Install tile
 Install glass
 Install new shower door
8. Install new sheetrock behind shower on newly built wall.
9. Tape, float, texture and paint where needed.
10. Install new baseboard where needed.

Choose DNA Remodeling because your satisfaction is in our blood!


Page 3 of 5

Initials _______
D ependable N A ffordable Remodeling
Dan Trevino (210) 902-7372

Cost Breakdown

Labor Costs

Demo and Mold Control and Disposal $3,000.00+


Repair and Replace $4,500.00
Misc. $225.00
TOTAL: $7,725.00
Note: 25% of the labor cost, $1,931.25, is required to begin work.
Payment schedule: Weekly
End of Week 1 – prepaid as 25% labor
End of Week 2 - $1,931.25
End of Week 3 - $1,931.25
Final payment due at completion of project. Total project estimated to be completed within 4 to
5 weeks from start.

Material Costs
Homeowner is responsible for all material costs. A proposed materials list has been included (Page 5)
for your reference. Materials and material pricing may change if job specifications change.

Please initial each page and sign below to accept the proposed work and associated labor costs.

X________________________________ Date ____________________

Sincerely,

Dan Trevino
DNA Remodeling

Choose DNA Remodeling because your satisfaction is in our blood!


Page 4 of 5

Initials _______
D ependable N A ffordable Remodeling
Dan Trevino (210) 902-7372

Proposed Materials List


# of Est. Actual
Items Material Description Cost Cost
1 Shower Pan
1 Shower door
Tile
Bathroom fixtures
2x12x10
2x4x8
3/4" 4x8 subfloor
1/2" or 1/4" 5x3 greenboard
1/2" 4x8 sheetrock
1 Shower drain
Waterproofing membrane
Plumbing hardware Pipe, adapters, connectors, toilet flange, wax ring, etc.
Tile supplies Mortar, spacers, grout and grout sealer
Painting supplies Paint, brushes, pans, brush cleaner, caulk and silicone
Base boards
Mold remover
Tape and mud
1 roll X Board surface protector
Fasteners
2
packs Painters Tape Value Pack
2
rolls Duct Tape
150
ct Contractor Bags
150
ct Trash bags
Safety Equipment Goggles, disposable gloves, shoe covers, coveralls, etc.
Notes: