PROJECT: CONTRACTOR
TRANSMITTAL NO. &
DATE:
PROPOSED CCU1
E-Mail Dated 26.12.19
Warehouse at Kolkata.
M/S FLUIDLINE ENGINEERS &
FAB. PVT. LTD.
We are herein conveying our approval/ comments on the documents listed below. Approval/ comments conveyed herein neither
relieves the vendor/ contractor of his contractor of his contractual obligations and his responsibilities for correctness of
dimensions, materials of construction, weights, quantities, design details, assembly fits, performance requirements and conformity
of the supplies with the Local statutory Laws as may be applicable, nor does it limit the purchaser's rights under the contract.
Yours faithfully
R.Palaniappan
Associate Vice President - Mechancal
CODE
A. Document approved as submitted; proceed with fabrication/ F. Correct original of the document to reflect our
construction. comments and resubmit for records.
B. Document approved subject to comments noted proceed G. Documents of this category are for information
with fabrication/ construction considering our comments. only and not for approval information furnished on
the document is noted.
C. Our comments are noted on the enclosed marked-up print. H. Document reviewed only against our previous
comments and other revisions highlighted and
identified by the vendor.
D. Our comments are noted in the enclosure/ attached to this transmittal. I. Document returned without review.
E. Correct original of the document to reflect our comments J. Print not enclosed.
and resubmit for approval.
SHOP DRAWINGS
FIRE SPRINKLER & WATER CURTAIN
1 ESR-WH-08-SPK-02 RO E
SYSTEM LAYOUT FOR PHASE-2
WATER CURTAIN SYSTEM LAYOUT
2 ESR-WH-08-CUR-04 RO E
FOR PHASE-2
FIRE SPRINKLER SYSTEM LAYOUT
3 ESR-WH-08-SPK-03 RO E
FOR MEZZANINE FLOOR PHASE-2
FIRE HYDRANT SYSTEM LAYOUT
4 ESR-WH-08-HYD-01 RO E
FOR PHASE-2
FIRE WATER CURTAIN SYSTEM
5 ESR-WH-08-CUR-05 LAYOUT FOR MEZZANINE FOR RO E
PHASE-2
FIRE SPRINKLER DROPPER LAYOUT
6 ESR-WH-08-SPK-06 RO B
FOR PHASE-2
(Please tick the relevant column)
M/s.Amazon seller
services Private Limited
COMMENTS
1 FLEPL/BOM07/DS/15 / Rev 0 / FIRE SPRINKLER & WATER CURTAIN SYSTEM LAYOUT FOR PHASE-2
a Sprinkler locations shall be coordinated with rafters,cross bracings and it shall shown in the drawing.
b Additional Support for Branchlines,Mains Shall be provided as per FMDS - 2-0 Clause 2.5.4.5.2.2 & 2.5.4.5.2.3
c Provide at least one pipe support every 12 ft (3.6 m) for vertical run as per FMDS 2-0.
d Pipe support load calculations shall be submitted as per FMDS 2-0.
e Hydraulic calculations for water curtian system shall be subnitted for our review.
5 ESR-WH-08-CUR-05 / FIRE WATER CURTAIN SYSTEM LAYOUT FOR MEZZANINE FOR PHASE-2 / R0
a Hydraulic calculations for water curtian system shall be submitted for our review.
b Operaion logic and integration with Fire alarm for activation of deluge valve shall be submitted.
c Deluge valve control panel locations shall be shown in the drawing.