FY 2018 DPWH Infrastructure Program, Organizational Outcome 1: Ensure Safe and Reliable

National Road System, Network Development Program, Construction of By-Pass and Diversion
Roads, TAYABAS BYPASS ROAD, PACKAGE A INCLUDING BRIDGE, QUEZON PROVINCE

18-DO-0046
APRIL 23, 2018
(NOTICE TO PROCEED) APRIL 24, 2018 APRIL 27, 2018 APRIL 30, 2018 MAY 17, 2018

SUSPENSION ORDER NO. 1 RESUME ORDER NO. 1 SUSPENSION ORDER NO. 2 RESUME ORDER NO. 2

SUSPENSION DUE TO SUSPENSION DUE TO


DAYS USED TO DATE BAD WEATHER CONDITION DAYS USED TO DATE BAD WEATHER CONDITION DAYS USED TO DATE
1 CALENDAR DAYS 3 CALENDAR DAYS 4 CALENDAR DAYS 13 CALENDAR DAYS 9 CALENDAR DAYS
TO BE APPROVED BY TO BE APPROVED BY
REGIONAL DIRECTOR REGIONAL DIRECTOR

MAY 21, 2018 MAY 25, 2018 MAY 26, 2018 JUNE 17, 2018 JUNE 20, 2018

SUSPENSION ORDER NO. 3 RESUME ORDER NO. 3 SUSPENSION ORDER NO. 4 RESUME ORDER NO. 4 SUSPENSION ORDER NO. 5

SUSPENSION DUE TO
SUSPENSION DUE TO SUSPENSION DUE TO
BAD WEATHER CONDITION
BAD WEATHER CONDITION DAYS USED TO DATE BAD WEATHER CONDITION DAYS USED TO DATE 8 CALENDAR DAYS
3 CALENDAR DAYS 33 CALENDAR DAYS 22 CALENDAR DAYS 55 CALENDAR DAYS
TO BE APPROVED BY
TO BE APPROVED BY TO BE APPROVED BY
REGIONAL DIRECTOR
REGIONAL DIRECTOR REGIONAL DIRECTOR

JUNE 29, 2018 JULY 6, 2018 JULY 11, 2018 JULY 13, 2018 JULY 20, 2018

RESUME ORDER NO. 5 SUSPENSION ORDER NO. 6 RESUME ORDER NO. 6 SUSPENSION ORDER NO. 7 RESUME ORDER NO. 7

SUSPENSION DUE TO
SUSPENSION DUE TO
BAD WEATHER CONDITION DAYS USED TO DATE
DAYS USED TO DATE BAD WEATHER CONDITION DAYS USED TO DATE 6 CALENDAR DAYS 89 CALENDAR DAYS
68 CALENDAR DAYS 4 CALENDAR DAYS 80 CALENDAR DAYS TO BE APPROVED BY
TO BE APPROVED BY
REGIONAL DIRECTOR
REGIONAL DIRECTOR

JULY 25, 2018 AUGUST 1, 2018 DECEMBER 10, 2018 JANUARY 9, 2018 JUNE 10, 2019
SUSPENSION ORDER NO.10
SUSPENSION ORDER NO. 8 RESUME ORDER NO. 8 SUSPENSION ORDER NO. 9 RESUME ORDER NO. 9

SUSPENSION DUE TO SUSPENSION DUE TO


BAD WEATHER CONDITION NON-AVAILABILITY OF
DAYS USED TO DATE DAYS USED TO DATE
8 CALENDAR DAYS CONSTRUCTION MATERIALS
109 CALENDAR DAYS 177 CALENDAR DAYS
TO BE APPROVED BY 30 CALENDAR DAYS TO BE
REGIONAL DIRECTOR APPROVED BY ASSISTANTSECRETARY

JUNE 10, 2019


SUSPENSION ORDER NO.10a

NOTE:
PREPARED BY:
THE PROJECT EXPIRY DATE SHALL BE ADJUSTED ROMEL S. PUCHERO
ACCORDINGLY BY THE PERIOD OF TIME THAT THE WORK
WERE SUSPENDED
Project Engineer