7 QAC RT V V V
Drawing, code
NDT of longitudinal seam QAC UT W/V RW/V RW/V
NDT Procedure
QAC MPT&LPT RW/V V V
8 Fit-up of shell to head, shell to shell and shell Drawing, code
Prod H - H
to cone circumferential seams WPS
9 Drawing, code
Welding of circumferential seams Prod H RW H
WPS
10 QAC RT V V V
Drawing, code
NDT of circumferential seams QAC UT W/V RW/V W/V
NDT Procedure
QAC MPT&LPT RW/V V RW/V
11 Marking of Nozzle orientation/location and Drawing, code
Prod H RW H
those of other attachments
12 Opening the shell plate for nozzles and Drawing, code
Prod H RW H
Manholes
13 Manufacture of subassemblies like manholes Drawing, code
Prod H RW H
and nozzles
14 Fit-up of manholes and nozzles on the Drawing, code
Prod H W H
shell/head/cone
15 Drawing, code
Welding manholes and nozzles Prod H RW H
WPS
Document N° :01
SARL ADNANE Inspection And Test Plan Rev ° :00
Note:
1) The heads, shell plates, nozzles, flanges, gaskets, etc. are considered to be bought out items as per the customer specifications reproduced in the
purchase order;
2) Considered that the client inspector is permanently posted at the shop.
3) Third party/ statutory inspection are envisaged only at certain important stages and may be modified based on specific requirements.
4) If needed by client, even more specific ITP can be prepared for each vessel by listing each and every seam, nozzle, etc. Which will be essential in
the case of very critical and, especially, very high-pressure vessels.