SAUDI ARAMCO INSPECTION CHECKLIST
Review of Procedure for Storage, Handling &
SAIC-G-2001 30-Apr-17 MECH-
Preservation of Equipment
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements

The procedure for Storage, Handling and preservation contains Schedule Q,


A1 instructions specified in all applicable specifications, SAUDI Attachment IV,
ARAMCO’s standards and manufacturer recommendations. Para. 6

Schedule Q,
The procedure has listed all inspection schedules for maintaining the
A2 Attachment IV,
quality of the material or equipment.
Para. 6

Procedure specfies responsiblities for "special handling, Schedule Q,


A3 storage and preservation", and supplied with predetermined WORK Attachment IV,
and inspection instructions to the individuals fully qualified to do so Para. 6

Schedule Q,
The procedure provides details for documentation that the required
A4 Attachment IV,
activities have been performed.
Para. 6

The procedure makes provision for Data concerning handling, Schedule Q,


A5 storage and preservation to be included on the Monthly Materials Attachment IV,
Procurement Status Report as specified in Schedule “G”. Para. 6

REMARKS:

REFERENCE DOCUMENTS:

1. Schedule Q, Project Quality Requirements, (Latest Edition)


Ref to SAIC-G-2003

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED