Side cutting, dressing leveling & compaction manually. Transported of soil to designated area. Plumb concreting done by Mini batching plant or RD Mixture.
Procedure
De-markation of footing to be excavated.
Proper access making for vehicle movement. Dressing leveling and side cutting using hand tools (Manually). Compaction by using dhurmuz or Compactor. Excavation using mechanical machines poclane, dumpers, & tractors & may be manually. Transportation of soil to designated area using dumpers, Tractor Hywa etc. Area hard barrication around excavated area. Access to be provided for entry exit to pit excavated.
Equipment Used Poclan, JCB, Dumpers, Tractors,Hywa. Safety Measures
PPE’S will be provided to all work men.
Proper access for vehicle movements. Aluminum ladder or MS Ladder for entry & exit into pit & fixed properly. Hard barrication 1.00mtr. Away from excavated pit. Swing area defines & barricaded any one side around excavator. Clear the access before plumb concreting or PCC. Continuous supervision.