MAIN CONTRACTOR ROHAN BUILDERS (INDIA) PVT LTD.

CLIENT JABIL CIRCUIT (INDIA) PVT LTD.

CONSULTANT DANDEKAR ASSOCIATES

LOCAL CONSULTANT PRIDE PROJECT CONSULTANTS

COMPRESSED AIR P. VENDER ELIXIR ENGG PVT LTD

TASK (Work Method Statement) Vacuum Piping

LOCATION SMT PRODUCTION AREA.

METHOD STATEMENT FOR


Vacuum Piping

 Purpose : Vacuum Piping-- Work

 Scope of Work: Shifting Of Pipe, Fabrication , Erection ,


Painting

 Procedure :Unloading of SS 304 Pipes


Stacking of Pipes.
Shifting to Material (manually) to work place.
Fabrication Of Pipe Support.
Erection Of Pipe Support.
Pipe Installation on Support.
Welding of Pipes. (Fusion.) Height 3.5 Mtr.
Testing of pipes.
Valves Fittings.
Painting of Pipes.

 Possible Hazard: - Cut Injury.


Fall of Material / Person
Hot Injury/ Fire Hazard
Electrical Hazard
Pressure Bust
 Use of Equipment :- 1) Rectifiers ( Welding Machine)
2) Hand Tools
3) Spirit Levels
4) Mechanical tool Box
5) Guide Ropes
6) Wire-Brush
7) Painting Brush
8) Spanner

 Use of PPE’S :-
 Safety Helmet, Shoe, Reflective Jacket
 Hand gloves
 Nose mask.
 Full body safety harness
 Goggles ( White)
 Ear plug.
 Safety shoes

 Responsible Person --

Raut D.A. – 9970534358

Prepared By--- Raut. D.A.