You are on page 1of 104

Adani Brahma Synergy Pvt. Ltd.

Belevedere Club VRV/Ventilation works

Section 1 System Design Data

1. General

1.1 The system design, basis of design, estimated requirements and other relevant data are
outlined in this section. The detailed specifications and specific requirements are out lined
in the subsequent sections.

2. Location

2.1 The proposed HVAC System (VRV/VRF/ERV ) is to be installed at the Belvedere Club at Sector
-60, Gurgaon ( Haryana).

3. Scope of work

3.1 The work proposed under this tender includes providing and fixing Air Cooled Variable
Refrigerant Volume air conditioning system, Refrigerant piping, drain piping, insulation,
Ventilation System, electrical wiring etc. for HVAC System of, the above project.

3.2 The work shall also include chasing of walls for piping, rough plaster to seal the chases,
embedding of drain piping under floor, wiring from electrical point upto unit etc.

3.3 All necessary provisions for connecting the HVAC system with the BMS system (Shall be
provided by 3rd party vendor) shall be done by the HVAC contractor.

4. Design Consideration

4.1 The Belvedere Club has various areas like Restaurant, SPA, Admin Office, multipurpose hall,
Indoor Games room etc. which are air conditioned by 16 Nos. of VRF outdoor units
connected to ceiling suspended units (ductable type) and floor Mounted DX type AHU.

4.2 Selected VRV Outdoor Units

The following capacity VRV outdoor unit has been selected.

(1) 16HP
(2) 18 HP
(3) 24 HP
(4) 28 HP
(5) 36 HP
(6) 48 HP
(7) 50 HP
(8) 52 HP
(9) 54 HP
(10) 58 HP

4.3 The outdoor units shall be located on the Terrace of the building as per the drawings.
Technical specifications Page -1
Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

4.4 The outdoor & indoor units shall be interconnected with insulated copper refrigerant
piping.
5. Basis of Design

5.1 Outside Conditions Summer : 43.3C DB ; 23.8C WB


Monsoon : 33.3C DB ; 28.4C WB
Winter : 06.0C DB ; 05.2C WB

5.2 Inside Conditions For all area to be : Summer: 23.0 ± 1 deg C DB


Air- conditioned
: RH not exceeding 60% in all areas.

5.3 Lighting Load : See attached table (Table – 1)( based on


ECBC and similar Previous project
experience )

5.4 Equipment Load General : 0.5 w/sq. ft.

5.5 Fresh Air : As per ASHRAE 62.1


See attached table (Table – 1)

5.6 Air Circulation Rate : Living Areas > 5 Air Changes/Hr


Bath/Kitchen/Utility > 15 ACH
Toilets > 8 ACH

5.7 Occupancy : See attached table (Table – 1 )

5.8 Roof Insulation : All the exposed roof shall be insulated


with 50mm thick expanded polystyrene
or equivalent insulation with U Value of
0.68 W/m2k.

5.9 Exterior Wall : Insulating Building Block with U Value of


2.15 W/m2k.

5.10 Glazing : All windows will have heat reflecting


double glass with air gap frame U Value
of 3.1 W/m2k.
5.11 Standard & Codes

The proposed system must be designed in accordance with following standards/codes.

5.11.1 ASHRAE 55-2010 Thermal Environmental Conditions for Human Occupancy


5.11.2 ASHRAE 62.2-2013 Ventilation and Indoor Air Quality in Low Rise Residential Buildings.
5.11.3 ASHRAE 90.2-2007 Energy-Efficient Design of Low-Rise Residential Buildings.

5.12 Energy Conservation Building Code (ECBC). 2017

Technical specifications Page -2


Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

5.13 India National Building Code (NBC 2017), Part-VIII: Building Services.

Technical specifications Page -3


Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

6. System Requirement
6.1 Based on the above the requirements of A.C. are as follows:

Table – 1 HEAT LOAD CALCULATION SHEET FOR BELVEDERE CLUB, GURGAON

Lighting Air Qty.


S. Floor Area Occupancy Equipment Fresh Air Load
Name of Area/ Room Floor Level Load D. Humid
No. (Sq. Ft.) ( persons ) Load (KW) (CFM) (Tons)
(W/Sq. ft.) (CFM)
BASEMENT
1 Purchase office BASEMENT 180 4 1.1 0.5 48 1.64 744
2 Electric office BASEMENT 102 2 1.1 0.5 28 0.9 407
SUB TOTAL 282 6 76 2.54 1151
GROUND FLOOR
3 Sitting Area GROUND 829 83 0.9 0.5 772 12.17 4184
4 Change Room Men GROUND 537 16 0.5 0 113 2.91 1174
5 Change Room Women GROUND 307 9 0.5 0 64 2.13 923
Corridor connecting change 245 3 96 1.23 449
6 room GROUND 0.5 0
7 Play Area GROUND 948 38 1.1 0.5 372 6.44 2348
8 Entrance Lobby GROUND 2888 29 1.1 0.5 1132 19.27 7943
9 Lobby(in front of kitchen) GROUND 399 4 0.5 0 84 2.34 1058
10 Admin GROUND 214 4 1.1 0.5 45 1.65 756
11 Hall4 GROUND 976 147 1.2 0.5 794 12.7 3703
12 lobby near luggage room GROUND 987 10 0.5 0 387 12.62 5939
13 Hall1 GROUND 1637 246 1.2 0.5 1329 20.32 4916
14 Hall2 GROUND 1541 231 1.2 0.5 1248 18.72 4322
15 Hall3 GROUND 1505 226 1.2 0.5 1221 18.78 4565
16 Foyer below hall4 GROUND 1077 11 0.5 0 422 13.3 6226
17 Foyer left to halls GROUND 1607 16 0.5 0 630 10.11 4092
18 Reception and corridor GROUND 1457 15 0.5 0 571 6.92 2507

Technical specifications Page -3


Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

Lighting Air Qty.


S. Floor Area Occupancy Equipment Fresh Air Load
Name of Area/ Room Floor Level Load D. Humid
No. (Sq. Ft.) ( persons ) Load (KW) (CFM) (Tons)
(W/Sq. ft.) (CFM)

19 Business centre/reading room GROUND 566 17 1.2 0.5 222 7.6 3471
20 Conference GROUND 438 14 1.2 0.5 172 4.1 1724
21 Meeting room GROUND 516 16 1.2 0.5 203 5.58 2438
SUBTOTAL 18674 1135 9877 178.89 62738
FIRST FLOOR
22 Staff Cafeteria and Training FIRST 923 57 1.2 0.5 483 6.34 1878
23 Pantry FIRST 192 4 1.2 0.5 32 0.82 335
24 CCTV Room FIRST 276 6 1.2 0.5 47 1.79 806
25 Corridor FIRST 870 9 0.5 0 131 3.32 1441
26 Doctor_Room FIRST 129 2 1.1 0.5 20 0.38 146
SUBTOTAL 2390 78 713 12.65 4606
SECOND FLOOR
27 Restaurant SECOND 2131 149 1.2 0.5 1502 21.29 7004
BOH Office SECOND 502 11 122 3.52 1541
28 1.2 0.5
29 Wifi/reading lounge SECOND 4265 128 1.2 0.5 1152 26.3 10544
30 President SECOND 197 4 1.2 0.5 48 1.36 595
31 Secretary SECOND 117 3 1.2 0.5 29 1.36 642
32 PA SECOND 140 3 1.2 0.5 34 1.13 512
33 Workstation/Copy/record SECOND 274 6 1.2 0.5 66 1.93 843
34 Club mgmt office corridor SECOND 242 2 1.2 0.5 59 0.88 341
35 Restaurant near main kitchen SECOND 1832 128 1.2 0.5 1290 19.23 6519
36 Guest room1 SECOND 256 2 1.2 0.5 50 1.72 811

Technical specifications Page -4


Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

Lighting Air Qty.


S. Floor Area Occupancy Equipment Fresh Air Load
Name of Area/ Room Floor Level Load D. Humid
No. (Sq. Ft.) ( persons ) Load (KW) (CFM) (Tons)
(W/Sq. ft.) (CFM)

37 Guest room2 SECOND 256 2 1.2 0.5 50 1.49 684


38 Guest room3 SECOND 256 2 1.2 0.5 50 1.49 684
39 Guest room4 SECOND 256 2 1.2 0.5 50 1.49 684
40 Guest room5 SECOND 256 2 1.2 0.5 50 1.49 684
41 Guest room6 SECOND 256 2 1.2 0.5 50 1.49 684
42 Foyer SECOND 146 1 0.5 0 36 1.01 465
43 Guest corridor SECOND 1031 10 0.5 0 198 7.4 3486
44 Junior suite/Bridal Room SECOND 378 2 1.2 0.5 73 2.25 1048
45 Pantry SECOND 593 12 1.2 0.5 114 3.7 1638
46 foyer and guest lift lobby SECOND 551 6 0.5 0 106 2.93 1309
SUB TOTAL 13935 477 5129 103.46 40718
THIRD FLOOR
47 Gymnasium THIRD 2241 67 2 0 673 14.86 5979
48 Squash(above) THIRD 646 2 2 0 246 2.91 1091
49 Squash(below) THIRD 756 2 2 0 288 5.29 2288
50 Juice_lounge THIRD 3312 331 1.2 0.5 3079 37.92 11007
51 Indoor games THIRD 1460 29 2 0.5 481 7.12 2618
52 Indoor/interactive games THIRD 998 20 2 0.5 330 6.49 2653
53 Change room(W) THIRD 257 8 0.5 0 56 1.79 766
54 Change room(M) THIRD 308 9 0.5 0 64 1.54 609
55 Sitting Area THIRD 448 11 1 0.5 86 1.72 642
56 Carrom room1 THIRD 184 6 1 0.5 79 1.07 363
57 Carrom room2 THIRD 155 6 1 0.5 73 0.8 227
58 Carrom room3 THIRD 192 6 1 0.5 80 0.88 261

Technical specifications Page -5


Adani Brahma Synergy Pvt. Ltd. Belevedere Club VRV/Ventilation works

Lighting Air Qty.


S. Floor Area Occupancy Equipment Fresh Air Load
Name of Area/ Room Floor Level Load D. Humid
No. (Sq. Ft.) ( persons ) Load (KW) (CFM) (Tons)
(W/Sq. ft.) (CFM)

59 Carrom Corridor THIRD 873 9 1 0.5 168 6.6 3126


60 simulated cricket golf THIRD 622 12 1 0.5 202 3.65 1453
61 Foyer THIRD 160 2 0.5 0 31 0.93 420
62 Guest corridor THIRD 1263 13 0.5 0 253 9.38 4415
63 Guest room1 THIRD 256 2 1.2 0.5 52 1.68 783
64 Guest room2 THIRD 256 2 1.2 0.5 52 1.43 650
65 Guest room3 THIRD 256 2 1.2 0.5 52 1.43 650
66 Guest room4 THIRD 256 2 1.2 0.5 52 1.43 650
67 Guest room5 THIRD 256 2 1.2 0.5 52 1.43 650
68 Guest room6 THIRD 256 2 1.2 0.5 52 1.43 650
69 Junior suite/bridal room THIRD 378 2 1.2 0.5 76 2.17 1003
70 Indoor bandminton/basektball THIRD 1842 37 2 0 860 17.09 7173
court
SUB TOTAL 17631 584 7437 131 50127
FOURTH FLOOR
71 Hall(30 persons) FOURTH 1034 30 1.2 0.5 311 6.59 2626
72 AV Room FOURTH 89 2 1.4 0.5 31 0.41 142
73 Function Room FOURTH 703 14 1.2 0.5 176 3.95 1640
74 Card room FOURTH 1374 52 2 0.5 638 9.62 3412
75 Corridor FOURTH 2159 22 0.5 0 540 14.03 6282
76 BOH/Pantry FOURTH 231 5 1.2 0.5 58 2.02 918
SUB TOTAL 5590 125 1754 36.62 15020
GRAND TOTAL 58502 2405 24986 465.16 174360

Technical specifications Page -6


Belvedere Club, Gurgaon

7 System Design

7.1 It is proposed to provide Air cooled variable refrigerant volume system (VRV/VRF).

7.2 All VRV/VRF system will be Micro Processor based with all inverter type scroll compressors.

7.3 It is proposed to use different types of Indoor units to suit the requirement. Ductable Units
types are proposed for all area with false ceiling or boxing.

7.4 Each type of Indoor unit will have individual temperature controller.

7.5 The air from ductable units will be distributed through Pre-insulated ducts and extruded
aluminum powder coated grilles along with a temperature adjuster to control the room
temperature.

8. Ventilation System

8.1 All the toilets will be ventilated through In-Line /Propeller fans/ axial fans of required
capacity as mentioned below.

S.No. Room Name Floor Area ACPH Height Exhaust Air Type of
Level (in Sq.m) (in m) Qty.(CMH) Fan
1 Toilet near Conference Ground 11 12 4 528 Inline
2 Gents toilet near Club Mgmt. Second 10 12 4 480
3 Ladies toilet near Club Mgmt. Second 16 12 4 768 Inline
4 Toilet in terrace Second 44 12 4 2112 Inline
5 Gents toilet near Indoor Games Third 10 12 4 480
6 Ladies toilet near Indoor Games Third 16 12 4 768 Inline
7 Toilet Fourth 15 12 4 720 Inline
8 Gents toilet near Hall4 Ground 26 12 4 1248
9 Ladies toilet near Hall5 Ground 26 12 4 1248
10 change room women toilet Third 20 12 4 960
11 change room men toilet Third 15 12 4 720
12 Toilet near Carrom Room Third 7 12 4 336
13 Ladies toilet Fourth 32 12 4 1536
14 Gents toilet Fourth 32 12 4 1536 Axial
15 change room women toilet Ground 17 12 4 816
16 change room men toilet Ground 17 12 4 816
17 Toilet near BOH Office Second 62 12 4 2976 Axial
18 Child toilet Ground 12 12 4 576
19 Ladies toilet Ground 16 12 4 768
20 Gents toilet Ground 16 12 4 768
21 Male Toilet First 54 12 4 2592
22 Female Toilet First 32 12 4 1536
23 Toilet1 First 12 12 4 576
24 Toilet2 First 12 12 4 576 Axial
25 Room1 Toilet Second 4 12 4 192
26 Room2 Toilet Second 4 12 4 192
Technical specifications Page -7
Belvedere Club, Gurgaon

27 Room3 Toilet Second 4 12 4 192


28 Room4 Toilet Second 4 12 4 192
29 Room5 Toilet Second 4 12 4 192
30 Room6 Toilet Second 4 12 4 192
31 Room7 Toilet Second 4 12 4 192
32 Room1 Toilet Third 4 12 4 192
33 Room2 Toilet Third 4 12 4 192 Axial
34 Room3 Toilet Third 4 12 4 192
35 Room4 Toilet Third 4 12 4 192
36 Room5 Toilet Third 4 12 4 192
37 Room6 Toilet Third 4 12 4 192
38 Room7 Toilet Third 4 12 4 192

8.2 The kitchen would be supplied with exhaust system consisting of ducting and exhaust
scrubber. The make-up air would be supplied through air washers.

9. Basement Ventilation System

9.1 Fire protection systems for basements are provided to minimize the risk from smoke, to
assist occupants to egress the danger area.

9.2 Based on NBC 2017, the basement fire compartment / zone have been designed at max.
3000 Sq.mt. area as per enclosed tender drawings.

9.3 It is proposed to provide a mechanical ventilation system.

9.4 Provision has also been made for Smoke Exhaust in basement @ 12 air changes per hour and
normal exhaust @ 6 air changes per hour.

9.5 It is proposed to use a separate set of Axial Flow Fan for normal exhaust as well as smoke
exhaust in each zone / compartment.

9.6 An additional set of Axial Flow fans are proposed for supply of Fresh air to the Basement.

9.7 There will be 2 nos. axial flow fans (1 no. for Normal Exhaust & 1 no. for Smoke Exhaust) in
Exhaust Fan Room & 2 nos. axial flow fans (1 no. for Normal fresh air & 1 no. for Smoke
make-up air) in Fan Room of each zone in the basement.

9.8 There will be total 2 nos. of zones in the basement.

9.9 The smoke exhaust & fresh air make-up will be automatically energized by the activation of
any fire alarm signal within the particular fire zone.

Technical specifications Page -8


Belvedere Club, Gurgaon

9.10 Each Staircase & Lift well will be provided with pressurization system to minimize the risk of
ingress of smoke. Each system for lift well pressurization will consist of axial flow fans. The
staircase having atleast one external wall will be naturally ventilated or pressurized by
providing an opening at each landing of an area 0.5 sq. m. in the external wall while staircase
with no external wall will be mechanically pressurized by providing an axial flow fan. Upon
activation of any fire alarm within the building, the pressurization fans will be energized and
lift well & staircases will be pressurized with the help of BMS.

10. Items to be provided by other Agencies

The following items of works shall be provided by other agencies. The HVAC contractor
shall be responsible for the adequacy and accuracy of these works and shall ensure that
these are completed as per the required time schedule.

10.1 Provision of 230v/ 1 PH / 50 Hz electric supply upto each indoor unit.


10.2 Provision of 415 V (+10% to -15%)/3 Ph/50 Hz electric supply with MCB upto outdoor unit.
10.3 Finishing of wall chases.
10.4 Sleeves in masonry walls and sealing of same.

11 Drawings

Tender drawings are diagrammatic only and indicate arrangement of system and the
extent of work covered in the contract. These drawings indicate point of supply and point
of termination and suggest the route to the followed. The architectural drawings and
details shall be examined for exact location of equipment, cutouts etc. The contractor
shall first prepare detailed heat load calculations and submit copies of the same for
approval. Based on the approved heat loads, Contractor shall follow the tender drawings
in preparation of shop drawings and for subsequent installation work and will coordinate
with other services also. The contractor shall submit shop drawings prior to
commencement of low side work for the approval of the Consultant/Client. As built
drawings shall be submitted as part of acceptance of work.

12. Test data

The whole system shall be tested as per specifications given elsewhere and complete test
data shall be furnished on prescribed data sheet.

13. Deviation from specifications

Deviation from specifications may be accepted, provided such deviations are found
necessary and appropriate, in order to conform to the design of established foreign
collaborators/manufacturers.

14. Completeness of Items

The prices of each equipment shall include the cost of all accessories or miscellaneous
items listed in the respective section, except for the items where “Price Separately “ is
indicated. The item shall be complete regardless of whether or not it is listed in the BOQ.

Technical specifications Page -9


Belvedere Club, Gurgaon

15. Technical data

Each tenderer must submit along with the tender the technical data for all items listed
herein in the indicated format. Failure to furnish technical data with tenders may result in
summary rejection of the tender.

16. Performance guarantee

16.1 The contractor shall guarantee that the air conditioning system shall maintain the design
inside temperature within  1.0oC tolerance under the worst ambient condition specified
and the relative humidity shall not exceed the specified limit.

16.2 The contractor shall guarantee that the capacity of various components as well as the
whole system shall not be less than specified.

16.3 The contractor shall ensure that the system shall be free of all objectionable vibrations
and disturbing sounds under all conditions of operation.

***********

Technical specifications Page -10


Belvedere Club, Gurgaon

Section 2 VRV / VRF System

1. General

1.1 The equipment for variable refrigerant volume/flow (VRV/VRF) system shall be air-cooled
consisting of Outdoor units and multiple Indoor units for cooling the space in summer and
heating in winter (whenever Heat pumps are specified)

1.2 The system shall consist of suitable Outdoor units, Indoor units as required, interconnecting
refrigerant piping, control cabling and accessories as required. (All BMS Compatible)

1.3 It shall be possible to connect multiple Indoor units on a single refrigerant circuit. The Indoor
units on any circuit may be of different type and should allow individual control.

1.4 The minimum length of Refrigerant piping in a branch circuits or all circuits shall be as per
chart given later on but the total piping length shall not be less than 300 m.

2. Outdoor Unit

2.1 The Outdoor unit shall be a factory assembled unit housed in a sturdy weather proof casing,
constructed form rust-proofed mild steel panels complete with powder coated finish.

2.2 Each module of Outdoor units shall consist of scroll compressor(s), air-cooled condenser as
Heat Exchanger, high efficiency propeller fans with low noise motor, internal Refrigerant
piping, safety controls, Air Inlet grilles, fan protection grille etc. all enclosed in weather proof
housing.

2.3 The Outdoor unit shall have single/ multiple scroll compressors as per the manufacturers’
standard design. The multiple compressor modules shall be able to operate even in case of
breakdown of one of the compressors.

2.4 The Outdoor unit shall be suitable for mix and match connection of various types and
capacities of Indoor units as per demand.

2.5 The noise level shall not be more than 62 dB(A) under normal operation, measured
horizontally, 1 m away and 1.5m above ground.

2.6 The Outdoor unit shall be modular in design and shall allow for side by side installation of
multiple Outdoor units, to match the requirement..

2.7 All the units shall be provided with built-in microprocessor control panel, for automatic
operation and capacity control.

2.8 The units shall be suitable for Refrigerant R-410A.


Technical specifications Page -11
Belvedere Club, Gurgaon

3. Compressor

3.1 Each unit shall have single/multiple hermetically sealed scroll compressor.

3.2 The scroll compressor shall consist of two spiral disc, where one is fixed and the other
rotate. The disc shall be mounted eccentrically to allow orbital movement. This shall permit
compression of Refrigerant gas, as it move up between the eccentric discs.

3.3 Both the spiral disc out rotor shall be mounted on a common shaft with antifriction bearing,
suitable for handling both radial and axial thrust.

3.4 The compressor casing shall be fabricated from mild steel of thickness capable of
withstanding the working pressures. The casing shall have built-in oil reservoir with a sump
of adequate capacity.

3.5 The compressor shall be complete with a suitable High efficiency motor hermetically sealed
within the compressor housing.

3.6 The compressor housing shall also have oil reservoir for lubrication and suitable means like
an oil pump or pressure differential device shall be provided to lubricate all moving parts.

3.7 One or more compressor shall be provided with suitable sine wave or equivalent DC Inverter
for capacity modulation.

4. Condenser / Heat Exchanger and Fans

4.1 The condenser shall be air-cooled type, where heat exchanger shall be fabricated from
copper tubes, mechanically bonded to aluminum fins to form a cross fin coil. The aluminum
fins shall be given anti-corrosion treatment. This treatment shall be suitable for areas of high
pollution, moisture and salt laden air.

4.2 The condenser fans shall be with multi blades of aerofoil design for low noise level, high
efficiency and fitted with an high efficiency fan motor.

4.3 The fan outlet outlet shall be protected by a suitable wire guard on the outside.

4.4 Suitable devices and heat exchanger means shall be built-in the unit to provide maximum
super-cooling of refrigerant to increase system efficiency.

4.5 The unit shall be complete with safety controls and suitable microprocessor based master
control module.

4.6 The module should be capable of connecting to web or to other devices through common
Bacnet or Lan networks.
Technical specifications Page -12
Belvedere Club, Gurgaon

4.7 All the above component shall be housed in a compact mild steel cabinet having air Inlet
louvers, safety guard on the condenser fan. The ambient shall be mode weather proof using
suitable anti corrosion treatment and finishing point.

5. Indoor Units (IDU)

5.1 The system shall permit connection of a variety of non ductable or ductable Indoor units on
to single refrigerant piping circuits, as per description given later.

5.2 The capacity of the IDU shall vary as per the requirement of the given area.

5.3 The types of IDU which may be connected may be any of these given below:

5.3.1 High Wall mounted Unit.


5.3.2 Cassette type.
5.3.3 Concealed Ceiling suspended units
5.3.4 Ceiling Suspended High static Unit.
5.3.5 Ceiling Mounted Exposed unit.
5.3.6 Floor standing (exposed or concealed) units.
5.3.7 Ductable ceiling mounted High Capacity units.

5.4 Common features of Indoor Units

5.4.1 The cooling / heating evaporator coils of the various types of Indoor Units shall be of direct
expansion type.

5.4.2 The coils shall be fabricated from copper tubes of min 8 mm dia. with extended aluminium
fins and designed for low velocity..

5.4.3 The fins shall be bonded to the tube using hydraulic expansion of tubes ensuring tight
bonding between tube and fins for efficient heat transfer.

5.4.4 The coils shall be complete with well designed tube circuiting and liquid distributor.

5.4.5 All types of units shall have a built in electronic expansion valve and suitable control units.

5.4.6 The control units shall control temperature, fan speed and features specific to each unit such
as night mode, set back, etc.

5.4.7 Suitable drain pan and drain arrangement shall be part of all IDUS. The Cassette units shall
also be provided with drain pumps.
The drain line and connections till floor traps shall be provided by the HVAC contractor.
However, at points where the drain pipe has to be connected with rain water pipes, the
plumbing contractor shall provide the saddle connector and the HVAC contractor would
connect the drain to the saddle and verify if all the connections are proper, leak proof and
working.

Technical specifications Page -13


Belvedere Club, Gurgaon

5.4.8 The control units shall permit control from a corded or a wireless remote controller.

6. High Wall Mounted units

6.1 The high wall mounted units will be complete with cross flow fan, vertical DX coil, filters,
control units and plastic outer cabinet.

6.2 The cross flow fan should be of generous dia. and length to deliver the required air quantity
at high speed and be very quiet with Noise level below 41 dbA .(The sound level can be
tested in the factory as per standard testing norms)

6.3 The fan assembly shall be directly mounted on a low noise, high efficiency motor.

6.4 The DX evaporator coil and other common features shall be as given under para 5.3

6.5 The air filter shall be electrostatic type to remove dust, polan and other impurities.

6.6 The outer casing shall be made of high grade plastic, complete with return air grille,
motorized supply air louvered opening and suitable metallic back panel for mounting all
items.

7. Cassette type units

7.1 The cassette type Indoor Units may be of any of the three configurations, as given below and
as may be mentioned in Bills of quantity.

7.1.1 Four way or circular air distribution arrangement which ever is specified or is available.
7.1.2 2-way air distribution arrangement.
7.1.3 1-way or corner type air distribution arrangement.

7.2 The unit shall be complete with turbo fans of multiblade type, duly statically and dynamically
balanced to give the required air flow.

7.3 The filter shall be of synthetic type to suit the configuration.

7.4 The unit housing shall have provision for connecting fresh air duct, wherever required.

7.5 The unit shall be complete with built-in high head fail-safe pump with safety cutouts.

7.6 The unit shall include all items as given in 5.3

7.7 Each type of unit shall be supplied complete with Air distribution panel whether specified or
not.

7.8 The panel shall have removable return air core for cleaning air filter and maintaining motor
etc.

8. Concealed ceiling suspended unit

Technical specifications Page -14


Belvedere Club, Gurgaon

8.1 The concealed units shall be complete with fan assembly, DX evaporator coil, air filter, outer
casing and control unit.

8.2 The fan shall be centrifugal type with housing and mounted directly on the motor shaft.

8.3 The air filter shall be preferably electrostatic type.

8.4 The outer casing shall be of heavy gauge G.I. sheet duly treated for long life and shall be
complete with 25 mm deep duly insulated drain pan.

8.5 The unit shall include all other items as listed in Para 5.3
9. Ceiling Suspended High Static Unit

9.1 The unit shall be complete as described in Para 8, except for the fan section.

9.2 The fans shall be selected and designed for highest air static pressure, to allow for at least 5
to 6 m of ducting with grilles.

10. Ceiling Mounted Exposed Unit

10.1 The exposed type unit shall be similar to the concealed type as described in Para 8, except
for the outer casing.

10.2 The unit shall have a decorative outer casing with built-in supply air grilles and return grilles.

10.3 The casing shall be with anti-corrosive treatment and finished with powder coated paint in
attractive finish.

11. Floor Standing Units

11.1 The floor standing units shall be vertical in design and may be suitable for concealed furred
in installation or cabinet type for exposed installation.

11.2 The fans shall be centrifugal type mounted directly on the motor shaft.

11.3 The air filter shall be cleanable electrostatic type.

11.4 The concealed type of vertical unit casing shall be of heavy gauge galvanized sheet with anti-
corrosive paint.

11.5 It should be complete with deep drawn insulated drain pan and shall permit easy access for
filter cleaning and maintenance of coil and fan motor.

11.6 The cabinet type of exposed vertical units shall in addition have a decorative cover with built
in supply and return air grilles.

11.7 All other components in both type shall be as in para 5.3

Technical specifications Page -15


Belvedere Club, Gurgaon

12. Ductable Units

12.1 The ductable indoor units shall be ceiling suspended type, complete with fan assembly, DX
coil, air filters, control units and outer casing.

12.2 The fan shall be centrifugal suction type with fan casing and direct driven motor. The fan
shall have a minimum external static pressure of 100 Pa.

12.3 The air filter shall be cleanable type with mold resistant resin net fixed to an integrally
moulded plastic frame. The filter shall be sliding type with frame for ease of insertion and
removal.
12.5 The outer casing shall be of heavy gauge galvanized duly treated for corrosion resistance and
finished with powder coated paint. It should have internal insulation to prevent
condensation and absorb fan noise.

12.6 There shall be suitable deep drawn insulated drain pan.

12.7 All other component shall be as in para 5.3

13. Indoor Control Unit

13.1 All types of indoor unit shall have one of the following controllers:

13.1.1 Cordless Type

13.1.2 Corded Type

13.2 Unless otherwise specified the controller to be provided shall be as follows:

13.2.1 Cordless Remote: Wall units or other units which are located in an enclosed cabin.

13.2.2 Corded Remote: in open offices or and areas not covered above.

13.3. A Computerized DIP control shall be used to maintain room temperature.

13.4 The unit shall be equipped with a self-diagnosis for easy and quick maintenance and service.

13.5 The LCD (Liquid Crystal Display) remote controller shall memorize the latest malfunction
code for easy maintenance.

13.6 It shall be able to control up to 16 Indoor units and change fan speed individually in the
group.

14. Refrigerant Piping Capabilities

14.1 The unit shall be capable of long length of piping and for providing lift of Refrigerant due to
level difference between the Outdoor unit and Indoor units at the highest levels.

14.2 The minimum distance capability of the unit shall be as follows:


Technical specifications Page -16
Belvedere Club, Gurgaon

14.2.1 Total Piping length of system Min. 300 m.

14.2.2 Actual length in any circuit Min. 150 m.

14.2.3 Equivalent piping length any circuit Min. 175 m.

14.2.4 Level difference between ODU and IDU Min. 50 m.

15. Refrigerant Piping


15.1 All refrigerant piping for the VRV/VRF system shall be carried out using hard drawn seamless
copper pipe using either soft, half hard or hard pipes as per chart below:

15.1.1 The piping thickness shall be as follows:

OD(Inch) OD(mm) Min. Wall Thickness (mm) Soft Half Hard or Hard
1/4” 6.35 0.80 √ √
3/8” 9.52 0.80 √ √
1/2” 12.70 0.80 √ √
5/8” 15.88 1.00 √ √
3/4” 19.05 1.00 √ √
7/8” 22.20 1.00 X √
1.1/8” 28.58 1.00 X √
1.3/8” 34.92 1.10 X √
1.5/8” 41.28 1.25 X √

15.2 The branching of refrigerant piping from the main line shall be carried out using either
specially designed ‘Tee’ connectors or ‘Y’ joints. These joint should ensure that each branch
receives the required refrigerant flow.

15.3 All pipe sizing shall be on the basis of sizing data of the concerned manufacturer and should
ensure adequate oil return back upto the compressor.

16. Pipe Insulation


16.1 Refrigerant Pipe Insulation

16.1.1 The whole of the liquid and suction refrigerant lines including all fittings, valves and strainer
bodies, etc. shall be insulated with 19mm thick Nitrile close cell rubber tubular insulation
with class 'O' , FM approved, so that condensation does not occur.
16.1.2 The joints shall be properly sealed with synthetic glue to ensure proper bonding of the ends.

17. Drain pipe insulation

Technical specifications Page -17


Belvedere Club, Gurgaon

17.1 Drain pipe carrying condensate water shall be insulated with 6 mm nitrile rubber insulation
having K valve 0.037 W/mk at a mean temperature of 20oC at min. density of 55 kg./m3.

17.2 The joint shall be properly sealed with synthetic glue to ensure proper bonding of the ends.

18. Centralized Intelligent Touch Remote controller


18.1 A multifunctional compact centralized controller shall be provided with the system.

18.2 The Graphic controller shall act as an advanced air conditioning management system to
given complete control of VRV air conditioning equipment. It shall have ease of use for the
user through its touch screen. Icon display and colour LCD display.

18.3 It shall be able to control up to 64 groups of Indoor Units with the following functions:

18.3.1 Starting/stopping of air-conditioning as a zone or group of individual units.

18.3.2 Temperature setting for each Indoor units of zone.

18.3.3 Switching between temperature controls modes, switching of the fan speed and direction of
airflow, enabling/disabling of individual remote controller operation.

18.3.4 Monitoring of operation status such as operation mode & temperature setting of individual
indoor units, maintenance information, and trouble shooting information.

18.3.5 Display of air conditioner operation history.

18.3.6 Daily management automation through yearly schedule function with possibility of varying
schedules.

18.4 The controller shall have wide screen, user friendly colour LCD display which could be wired
by a non polar 2 wire transmission cable to a distance of 1 km. away from the Indoor unit.

*******

Technical specifications Page -18


Belvedere Club, Gurgaon

Section-3 Air Handling Units


(Sectional Floor Mounted Double Skin)

1. General

The air handling units shall be complete in all respects and shall generally comply with the
specifications as given in the following paragraphs. (All BMS Compatible)

2. Air Handling Units

2.1 The air handling units shall be double skin sectional, draw through type with extruded
aluminium profile and shall include pre filter section, fan and coil section.

2.2 Fan and Accessories

The fan shall be backward curved plug type. The wheel & housing shall be fabricated from
heavy gauge galvanized steel. The fan impeller shall be mounted on a solid shaft supported
on angle iron heavy duty ball bearing. The fan shall be selected for a speed not exceeding
1100 RPM. The impeller & fan shaft shall be statically and dynamically balanced. The fan
outlet velocity shall not exceed 1800 FPM. Fan housing with motor shall be mounted on a
common extruded aluminum base mounted inside the fan section on anti-vibration spring’s
mounts or cushy foot mount. The fan outlet shall be connected to casing with the fire
retardant double canvass. The belt driven fan shall be complete with multi ‘V’ belt drive and
adjustable motor mounting base. The opening for the access of the fan section shall be
provided with micro-switch and galvanized iron mesh.

2.3 Cooling/Heating coil

The cooling coil shall be of seamless copper tubes, not less than 0.4 mm thick and 12 mm
O.D. The bends shall be ready made with solder rings on both ends. The coil shall have
continuous aluminium dual sine wave fins. The fins shall be spaced by collars forming
integral part of the fins. The tubes shall be staggered in the direction of air flow. The fins
shall be uniformly bonded to the tubes by mechanical expansion of the tubes. The coils shall
be tested against leaks at a pressure of 10 kg/ cm2. This pressure shall be maintained for a
period of 24 hours. The refrigerant headers shall be of copper pipes, to connect all the tubes.
The headers shall be complete with refrigerant In/Out connections. The coil size shall be
designed at an operating air velocity of 500 FPM (2.5 M/S).
Technical specifications Page -19
Belvedere Club, Gurgaon

2.4 Filtration
Each AHU shall have one type of filters and conforming to the specifications given under and
as given subsequently.

2.4.1 Pre-filters of 90% efficiency by weight with aluminum frame and synthetic media.

2.5 Drain pan


The drain pan shall be sandwiched type with SS sheet on inside and G.I. sheet on outside,
welded joints and drain connection of suitable size complete with PUF injection tray. The
drain pan shall be min. 25 mm deep. Drain outlet shall be of S.S.

2.6 Coil and filter housing

The cooling coils, special and standard filters, etc., shall all be housed in a separate enclosure
of suitable size and length. The inspection doors shall have neoprene rubber T-section,
rubber seals, hinges and locking arrangements. The gaps between filter frames and housing
shall have synthetic rubber packing, to eliminate any air leakage. All filter frames shall be
epoxy painted. The flat filter section shall be suitable for mounting filters vertically.

2.7 AHU Enclosure/Housing

2.7.1 The AHU enclosure shall either be of non-skeleton construction with whole C-shape panel
and labyrinth module connections or shall be constructed with frame work made of
extruded aluminium thermal break profile structural sections.

2.7.2 The panels shall be double sandwich type with 0.60 MM pre-coated galvanized sheet on the
outside and 0.50 MM galvanized sheet on the inside. The insulation shall be 25 MM thick
injected with polyurethane foam of density and K-value as given under.

2.7.3 Each section shall be provided with separate access panel of suitable size. The access panel
shall be hinged type with heavy duty hinges and handles made of nylon. The handles shall be
self tightening type to ensure leak proof closing.

2.7.4 The opening for access doors and gaps between sections shall be provided with the
neoprene rubber T-gaskets fixed in grooves in the extruded sections.

2.7.5 The sandwich panels shall be fixed to the frame work with self and tapping stainless screws
and both ends of the screw shall be provided with rubber caps.

2.8. Insulation

2.8.1 The panels of Double Skin AHU'S shall be sandwiched with 25 mm thick polyurethane foam
insulation of 40 KG/CUB.MT density having a K value of 0.014 Kcal/Mhr oC.

2.9 Fan motor & starter

Technical specifications Page -20


Belvedere Club, Gurgaon

2.9.1 The fan shall be provided with a totally enclosed fan cooled squirrel cage motor suitable for
VFD operation and shall have a minimum rating as given under “Schedule of Equipment”.
The starter rating shall match the motor rating and will conform to specifications under
“motor and switch gears. All Fan Motors should be IE 2 Type.

2.10 Fresh air controls

An adjustable damper of G.I. Sheet along with extruded aluminium louver, bird screen and
80% efficiency cleanable metallic filter shall be provided in the fresh air duct opening at
AHU. (Priced Separately)

3. Accessories

3.1 Each air handling unit shall be complete with the following accessories:

3.1.1 Drain line from the unit up to floor trap. (Priced Separately)
The drain line and connections till floor traps shall be provided by the HVAC contractor.
However, at points where the drain pipe has to be connected with rain water pipes, the
plumbing contractor shall provide the saddle connector and the HVAC contractor would
connect the drain to the saddle and verify if all the connections are proper, leak proof and
working.
3.1.2 Fire retardant Flexible connection between the fan outlet and duct.

3.1.3 Vibration isolators of 90% efficiency between AHU and foundation.

3.1.4 Motorized fire Type dampers at supply and return.

4. Testing
The air handling unit shall be tested to measure air quantity and coil performance by
measuring temperature difference, refrigerant pressure drop across coil and then calculating
the capacity.

5. Limitations

5.1 The air velocity across the cooing coil shall not exceed 550 FPM (2.79 m per sec.).

5.2 The fan outlet velocity shall not exceed 1800 FPM. (9.15 M per sec.), subject to fan noise
level not exceeding 75 dBA at 1.5m distance.

5.3 The air velocity across the filters shall not exceed 500 FPM. (2.54 m per sec.)

Technical specifications Page -21


Belvedere Club, Gurgaon

**********

Technical specifications Page -22


Belvedere Club, Gurgaon

Section-4 Air Handling Units (Double Skin)


(Ceiling Suspended Type)
1. General:

The air handling units shall be of as per drawing and complete in all respects and shall
generally comply with the specifications as given in the following paragraphs. (All BMS
Compatible)

2. Air Handling Units

2.1 The air handling units shall be double skin Sectional/Unitary, draw through type and
extruded aluminium profile and shall include pre-filter section, fan section, coil section,
mixing box wherever required.

2.2 Fan section

The fan shall be backward curved plug type. The wheel & housing shall be fabricated from
heavy gauge galvanized steel. The fan impeller shall be mounted on a solid carbon steel
shaft supported to housing with angle iron frame & pillow block heavy duty ball. The fan
shall be selected for a speed not exceeding 1000 RPM. The impeller & fan shaft shall be
statically and dynamically balanced. The fan outlet velocity shall not be more than 1800
FPM. Fan housing with motor shall be mounted on a common aluminum base mounted
inside the air handling housing on and vibration springs mounts or cushy foot mount. The
fan outlet shall be connected to casing with the help of fire retardant flexible canvass. The
belt driven Fan shall be complete with multi ‘V’ belt drive and adjustable motor mounting
base. Inspection door shall be installed with micro switch arrangement with lighting within
the fan section. Micro switch shall be interlocked with blower & light with resetting
arrangement.

2.3 Cooling coil

2.3.1 The cooling coil shall be of seamless copper tubes, not less than 0.4 MM thick and 12 MM
O.D. the coil shall have continuous aluminum fins. The fins shall be spaced by collars forming
integral part of the fins. The tubes shall be staggered in the direction of air flow. The fins
shall be uniformly bonded to the tubes by mechanical expansion of the tubes. The coils shall
be tested against leaks at a pressure of 10 KG/SQ.CM. This pressure shall be maintained for a
period of 2 hours. The refrigerant headers shall be of copper pipes with M.S. pipe
connection, to connect all the tubes. The headers shall be complete with refrigerant in/out
connections.

2.4 Filter
Each AHU shall have pre-filter of 90% down to 10 micron efficiency by weight and have
synthetic media and aluminum frame as given subsequently.

2.5 Drain pan


2.5.1 The drain pan shall be sandwiched type with S.S. sheets on top and GI sheet on the bottom
complete with PUF injected tray.

Technical specifications Page -23


Belvedere Club, Gurgaon

2.5.2 The drain pan shall be a minimum of 25 mm deep. Drain outlet shall be of S.S. and of 25 mm
dia.

2.6 Coil and filter housing

The cooling coils, special and standard filters, etc., shall all be housed in a separate enclosure
of suitable size and length. The inspection doors shall have double synthetic rubber seals
doors and locking arrangements. The gaps between filter frames and housing shall have
synthetic rubber packing, to eliminate any air leakage. All filter frames shall be epoxy
painted. The flat filter section shall be suitable for mounting filters vertically.

2.7 AHU Enclosure/Housing

2.7.1 The AHU enclosure shall either be of non-skeleton construction with whole C-shape panel
and labyrinth module connections or shall be constructed with frame work made of
extruded aluminium thermal break profile structural sections.

2.7.2 The panels shall be double sandwich type with 0.50 MM pre-coated galvanized sheet on the
outside and 0.50 MM galvanized sheet on the inside. The insulation shall be 25 MM thick
foam injected polyurethane foam of density and K-value as given under.

2.7.3 The front panels shall be easily open able for servicing the fan and coil sections. It should
provide easy access to remove air filters for cleaning.

2.7.4 The opening for access doors and gaps between sections shall be provided with the
neoprene rubber T-gaskets fixed in grooves in the extruded sections.

2.7.5 The sandwich panels shall be fixed to the frame work with self tapping stainless steel screws
and both ends of the screw shall be provided with rubber caps.

2.7.6 The access door to fan section is to be provided with a switch to shut the fan when the door
is open.

2.8. Insulation

2.8.1 The panels of Double Skin AHU'S shall be sandwiched with 25 mm thick polyurethane foam
insulation of 40 KG/CUB.MT density having a K value of 0.014 Kcal/Mhr oC.

2.9 Fan Motor & Starter

2.9.1 The totally enclosed fan cooled squirrel cage fan motor shall be suitable for VFD operation
have a minimum rating as given under “Schedule of Equipment”. The starter rating shall
match the motor rating and will conform to specifications under “Control Panel Motor and
Switchgears". All Fan Motors should be IE 2 Type.

2.11 Fresh air controls

Technical specifications Page -24


Belvedere Club, Gurgaon

An adjustable damper of GSS Sheet along with bird screen, air inlet louvers and air filters
shall be provided in the wall of AHU room, for fresh air entry. (Priced Separately).

Technical specifications Page -25


Belvedere Club, Gurgaon

3. Accessories

3.1 Each air handling unit shall be complete with the following as part of AHU price.

3.1.1 Flexible connection between the fan outlet and duct.


3.1.2 Vibration isolators of 90% efficiency.

3.2 Drain line from the unit up to drain trap.


The drain line and connections till floor traps shall be provided by the HVAC contractor.
However, at points where the drain pipe has to be connected with rain water pipes, the
plumbing contractor shall provide the saddle connector and the HVAC contractor would
connect the drain to the saddle and verify if all the connections are proper, leak proof and
working.

4. Testing

The air handling unit shall be tested to measure air quantity and coil performance by
measuring temperature difference, refrigerant pressure drop across coil and then calculating
the capacity.

5. Limitations

5.1 The air velocity across the cooing coil shall not exceed 550 F.P.M. (2.79 M per sec.).

5.2 The fan outlet velocity shall not exceed 1800 FPM. (10.17 M/Sec.) Subject to Fan Noise Level
not exceeding 75 dBA.

5.3 The air velocity across the filters shall not exceed 500 FPM (2.5 M per sec.)

***********

Technical specifications Page -26


Belvedere Club, Gurgaon

Technical specifications Page -27


Belvedere Club, Gurgaon

Section-5 Treated Fresh Air Units


(DX Type Floor mounted Double skin)

1. General

The treated fresh air units shall be complete in all respects and shall generally comply with
the specifications as given in the following paragraphs. (All BMS Compatible)

2. Treated Fresh Air Units

2.1 The treated fresh air units shall be double skin Floor Mounted, draw through type and shall
include pre filter, fan and coil.

2.2 Fan and Accessories

The fan shall be forward curved, double inlet double width type. The wheel & housing shall
be fabricated from heavy gauge galvanized steel. The fan impeller shall be mounted on a
solid shaft supported on an area mount with taper block bearing. The fan shall be selected
for a speed not exceeding 1400 RPM. The impeller & fan shaft shall be statically and
dynamically balanced. The fan outlet velocity shall not exceed 1800 FPM. Fan housing with
motor shall be mounted on a common extruded aluminum base mounted inside the fan
section on anti-vibration springs mounts or cushy foot mount. The fan outlet shall be
connected to casing with the fire retardant double canvass. The fan shall be complete with
multi ‘V’ belt drive and adjustable motor mounting base. The opening for the access of the
fan section shall be provided with micro-switch and galvanized iron mesh. The fan outlet
shall be provided with a VCD.

2.3 Cooling coil

The cooling coil shall be of seamless copper tubes, not less than 0.5 mm thick and 12 mm
O.D.. The bends shall be ready made with solder rings on both ends. The coil shall have
continuous aluminum dual sine wave fins. The fins shall be spaced by collars forming integral
part of the fins. The tubes shall be staggered in the direction of air flow. The fins shall be
uniformly bonded to the tubes by mechanical expansion of the tubes. The coils shall be
tested against leaks at a hydraulic pressure of 10 kg/ cm2. This pressure shall be maintained
for a period of 2 hours. No drop should be observed indicating any leaks. The water headers
shall be of M.S. pipes, to connect all the tubes. The headers shall be complete with water
In/Out connections, vent plug on top and drain at the bottom, and designed to provide
water velocity between 0.6 to 1.8 m/s (2 to 6 FPS). The coil size shall be designed at an
operating air velocity of 500 FPM (2.5 M/S).

2.4 Filtration

Each TFA shall have one or two types of filters and conforming to the specifications given
under :

2.4.1 Pre-filters of 80% efficiency by weight with aluminium frame and synthetic media.

Technical specifications Page -28


Belvedere Club, Gurgaon

2.4.2 High Efficiency filters of 90% efficiency down to 10 micron particle size (wherever specified
in “Schedule of Prices”).
2.5 Drain pan :

The drain pan shall be construction of 18 Gauge stainless steel sheets, externally insulated
with 12 MM thick closed cell polyethylene foam insulation with necessary slope to facilitate
fast removal of condensate.

2.6 Coil and filter housing

The cooling coils, special and standard filters, etc., shall all be housed in a separate
enclosure of suitable size and length. The inspection doors shall have neoprene rubber T-
section , rubber seals, hinges and locking arrangements. The gaps between filter frames and
housing shall have synthetic rubber packing, to eliminate any air leakage. All filter frame
shall be epoxy painted. The flat filter section shall be suitable for mounting filters vertically.

2.7 TFA Enclosure/Housing

2.7.1 The TFA enclosure shall be double skin design with the main frame work made of extruded
aluminium structural section.

2.7.2 The panels shall be double sandwich type with 0.80 MM precoated galvanised sheet on the
outside and 0.80 MM galvanised sheet on the inside. The insulation shall be 43 MM thick
foam injected polyurethene foam.

2.7.3 Each section shall be provided with separate access panel of suitable size. The access panel
shall be hinged type with heavy duty hinges and handles made of nylon. The handles shall be
self tightening type to ensure leak proof closing.

2.7.4 The opening for access doors and gaps between sections shall be provided with the
neoprene rubber T-gaskets fixed in grooves in the extruded sections.

2.7.5 The sandwich panels shall be fixed to the frame work with self and tapping stainless screws
and both ends of the screw shall be provided with rubber caps.

2.7.6 The access door for section shall be installed with a micro switch & light to shut the fan &
switch on the light.

2.8 Fan motor & starter

2.8.1 The fan shall be provided with a totally enclosed fan cooled squirrel cage motor which shall
have a minimum rating as given under “Schedule of Equipment”. The starter rating shall
match the motor rating and will conform to specifications under “motor and switch gears.

2.8.2 The fan motors may be of 2 speed, where specifically mentioned in the “Schedule of Prices”

2.9 Fresh air controls

Technical specifications Page -29


Belvedere Club, Gurgaon

An adjustable damper of G.I. Sheet along with bird screen, air inlet louvers and pre-filter
shall be provided in the AHU rooms along with the TFA.

3. Accessories

3.1 Each air handling unit shall be complete with the following accessories:

3.1.1 Stem type thermometers at coil inlet and outlet, with tubing and gauge cocks.
(Priced Separately)

3.1.2 Pressure gauge with cock at inlet of the coil, with tubing and gauge cocks.
(Priced Separately)

3.1.3 Butterfly valves at inlet of the coil and balancing valve at outlet of coil.
(Priced Separately)

3.1.4 Drain line from the unit upto floor trap. (Priced Separately)
The drain line and connections till floor traps shall be provided by the HVAC contractor.
However, at points where the drain pipe has to be connected with rain water pipes, the
plumbing contractor shall provide the saddle connector and the HVAC contractor would
connect the drain to the saddle and verify if all the connections are proper, leak proof and
working.

3.1.5 Automatic air Vent Valves on pipes. (Priced Separately)

3.1.6 Fire retardant Flexible connection between the fan outlet and duct.

3.1.7 Vibration isolators of 90% efficiency between AHU and foundation.

4. Testing

The treated fresh air unit shall be tested to measure air quantity and coil performance by
measuring temperature difference, water pressure drop across coil and then calculating the
capacity.

5. Limitations

5.1 The air velocity across the cooing coil shall be as specified in schedule of equipment but in
any case shall not exceed 550 FPM (2.75 m per sec.).

5.2 The fan outlet velocity shall not exceed 1800 FPM. (9.15 M per sec.).

5.3 The air velocity across the filters shall not exceed 500 FPM. (2.54 m per sec.)

6. Air Cooled Condenser

6.1 Remote air cooled condensing unit shall have efficient condenser coils made out of copper
tubing with extended aluminium fins.

Technical specifications Page -30


Belvedere Club, Gurgaon

6.2 Tubes shall be arranged in a staggered design for better efficiency.

6.3 Condenser fans shall be selected to operate quietly for required CFM to keep condensing
temperature low.

6.4 The compressor shall be capable of operating continuously even at high ambient of 46 deg.C
(115 deg.F).

6.5 The condensing unit shall be installed with MS base frame with neoprene rubber pads.

6.6 The compressor units shall be hermetically sealed scroll type.

7. Miscellaneous

7.1 Interconnected refrigerant piping between outdoor unit and indoor unit shall be of heavy
gauge copper complete with insulation.

7.2 The units shall be tested in accordance with IS 1392.

7.3 The power supply shall be provided at outdoor/indoor unit as per manufacturer’s
requirement.

**********

Technical specifications Page -31


Belvedere Club, Gurgaon

Section 6 SPLIT UNIT


DUCTABLE TYPE

1. General

1.1 The Split A.C. system shall be air-cooled consisting of Outdoor units and single/ twin Indoor
units for cooling the space in summer and heating in winter (whenever Heat pumps are
specified).

1.2 The system shall consist of suitable Outdoor units and Indoor units as required,
interconnecting refrigerant piping, control cabling and accessories as required. (All BMS
Compatible)

1.3 The minimum length of Refrigerant piping in any system shall not be less than 25 m and
permit level difference of 10 m between Outdoor and Indoor unit.

3. Outdoor Unit (ODU)

3.1 The Outdoor unit shall be a factory assembled unit housed in a sturdy weather proof casing,
constructed from rust-proofed mild steel panels complete with powder coated finish.

3.2 Each Outdoor shall consist of rotary/ scroll compressor(s), air-cooled condenser as Heat
Exchanger, high efficiency propeller fans with low noise motor, internal Refrigerant piping,
safety controls, Air Inlet grilles, fan protection grille etc. all enclosed in weather proof
housing.

3.3 The Outdoor unit may have single /multiple, Rotary /scroll compressors and shall be able to
operate even in case of breakdown of one of the compressors.

3.4 There shall be a separate refrigerant circuit for each compressor designed to connect with a
matching Indoor unit in case of multiple compressor ODU.

3.5 The Outdoor unit shall be suitable for connection to various types of Indoor units to match
the outdoor units.

3.6 The noise level shall not be more than 62 dB(A) under normal operation, measured
horizontally, 1 m away and 1.5m above ground.

3.7 All the units shall be provided with built-in control panel, for automatic operation.

3.8 The units shall be suitable for Refrigerant R -22.

3.9 The ODU may be with either single compressor or multiple compressor.

Technical specifications Page -32


Belvedere Club, Gurgaon

3.10 Compressors with Inverter will be used whenever specified in Bills of quantity.

3. Compressor
3.1 Compressor (Rotary type)

3.1.1 The rotary compressor shall consist of a rotor mounted in concentric housing and on
antifriction bearing.
3.1.2 Both the spiral disc and rotor shall be mounted on a common shaft with antifriction bearing,
suitable for handling both radial and axial thrust.

3.1.3 The compressor casing shall be fabricated from mild steel of thickness capable of
withstanding the working pressures. The casing shall have built-in oil reservoir with a sump
of adequate capacity.

3.1.4 The compressor shall be complete with a suitable High efficiency motor hermetically sealed
within the compressor housing.

3.1.5 The compressor housing shall also have oil reservoir for lubrication and suitable means like
an oil pump or pressure differential device shall be provided to lubricate all moving parts.

3.1.6 Rotary compressors shall be used in small units with capacities between 1 ton to 2 Tons
capacity.

3.2 Compressor (Scroll type)

3.2.1 The scroll compressor shall consist of two spiral disc, where one is fixed and the other
rotate. The disc shall be mounted eccentrically to allow orbital movement. This shall permit
compression of Refrigerant gas, as it move up between the eccentric discs.

3.2.2 The spiral disc of rotor shall be mounted on a shaft with antifriction bearing, suitable for
handling both radial and axial thrust.

3.2.3 The compressor casing shall be fabricated from mild steel of thickness capable of
withstanding the working pressures. The casing shall have built-in oil reservoir with a sump
of adequate capacity.

3.2.4 The compressor shall be complete with a suitable High efficiency motor hermetically sealed
within the compressor housing.

3.2.5 The compressor housing shall also have oil reservoir for lubrication and suitable means like
an oil pump or pressure differential device shall be provided to lubricate all moving parts.

3.2.6 Scroll compressors shall be used in all units larger then 2 Tons capacity and upto 8.5 Tons
capacity.

Technical specifications Page -33


Belvedere Club, Gurgaon

4. Condenser / Heat Exchanger and Fans

4.1 The condenser shall be air-cooled type, where heat exchanger shall be fabricated from
copper tubes, mechanically bonded to aluminum fins to form a cross fin coil. The aluminum
fins shall be given anti-corrosion treatment. This treatment shall be suitable for areas of high
pollution, moisture and salt laden air.

4.2 The condenser fans shall be with multi blades of aerofoil design for low noise level, high
efficiency and fitted with an high efficiency fan motor.

4.3 The fan outlet shall be protected by a suitable wire guard on the outside.

4.4 Suitable devices and heat exchanger surface shall be built-in the unit to provide maximum
super-cooling of refrigerant to increase system efficiency.

4.5 The unit shall be complete with master control module.

4.6 All the above component shall be housed in a compact mild steel cabinet having air Inlet
louvers, safety guard on the condenser fan. The outer covering shall be made) weather proof
using suitable anti corrosion treatment and finishing paints.

5. Indoor Units (IDU)

5.1 The unit shall permit connection to a variety of ductable Indoor units as per description
given later.

5.2 The capacity of the IDU shall match the capacity of the outdoor unit.

5.3 The types of IDU which may be connected may be one of these given below:

5.4.9 Ceiling Suspended High static Unit.


5.4.10 Ceiling Suspended large ductable type.

5.5 Common features of Indoor Units

5.5.1 The cooling / heating evaporator coils of the various types of Indoor Units shall be of direct
expansion type.

5.5.2 The coils shall be fabricated from copper tubes of min 8 mm dia. with extended aluminium
fins and designed for low velocity.

5.5.3 The fins shall be bonded to the tube using hydraulic expansion of tubes ensuring tight
bonding between tube and fins for efficient heat transfer.

5.5.4 The coils shall be complete with well designed tube circuiting and liquid distributor.

5.5.5 The control units shall control temperature, fan speed and features specific to each unit such
as night mode, set back, etc.

Technical specifications Page -34


Belvedere Club, Gurgaon

5.5.6 Suitable drain pan and drain arrangement shall be part of all IDUS.

5.5.7 The control units shall permit control from a corded or a wireless remote controller.

6. Concealed ceiling suspended High static unit

6.1 The concealed units shall be complete with fan assembly, DX evaporator coil, air filter, outer
casing and control unit.

6.2 The unit shall have centrifugal fan with suitable housing and mounted directly on the motor
shaft. The fan should be designed to allow atleast a 6m. long duct.

6.3 The fan shall be centrifugal type with housing and mounted directly on the motor shaft.

6.4 The air filter shall be preferably electrostatic synthetic anti mold type.

6.5 The outer casing shall be of heavy gauge G.I. sheet duly treated for long life and shall be
complete with 25 mm deep duly insulated drain pan.

6.6 The unit shall include all other items as listed in Para 5.3.

7. Ceiling suspended large ductable type

7.1 The indoor cooling unit shall be ceiling suspended ductable type and shall be matched to the
respective condensing unit. Each unit shall consist of cooling coil, fan and motor, air filters, outer
casing, drain pan, accessories etc.

7.2 The fan section of ductable units shall consist of forward curved blower with housing, motor,
mounting frame, drive arrangement all enclosed in a sheet metal casing duly insulated & powder
coated.

7.3 The air filter shall be cleanable type with mold resistant resin net fixed to an integrally moulded
frame. The filter shall be sliding type with suitable frame for ease of removal and insertion.

7.4 The outer casing shall be heavy gauge galvanized sheet duly treated for corrosion resistance and
finished with powder coated paints. It shall have internal insulation to prevent condensation.

7.5 There shall be a suitable deep drawn insulated drain pan.

7.6 All other components shall be as in para 5.3

8. Indoor Control Unit

8.1 All types of indoor unit shall have one of the following controllers:

8.1.1 Cordless Type


8.1.2 Corded Type

8.2 Unless otherwise specified the controller to be provided shall be as follows:


Technical specifications Page -35
Belvedere Club, Gurgaon

8.2.1 Cordless Remote: Wall units or other units which are located in an enclosed cabin.

8.2.2 Corded Remote: in open offices or and areas not covered above.

8.3. A Computerized DIP control shall be used to maintain room temperature.

9. Refrigerant Piping

9.1 The condensing unit and evaporator unit shall be interconnected by type ‘l’ seamless copper
refrigerant liquid and suction lines using flared or brazed fittings. Necessary accessories shall be
incorporated in the circuit.

9.2 The suction line shall be insulated with 6 mm closed cell foam insulation.

9.3 The specifications of refrigerant piping are given in subsequent section.

10. Miscellaneous

10.1 The unit shall have a corded electronic remote control housing ON/OFF and speed control,
temperature control and digital display.

10.2 Isolation spring shall be provided to hang the Indoor units and isolation pad to be provided for the
outdoor units.

10.2 Drain line shall be provided from Indoor unit upto drain trap. (To be priced separately).
The drain line and connections till floor traps shall be provided by the HVAC contractor.
However, at points where the drain pipe has to be connected with rain water pipes, the
plumbing contractor shall provide the saddle connector and the HVAC contractor would
connect the drain to the saddle and verify if all the connections are proper, leak proof and
working.

10.4 Suitable M.S. angle iron supporting frame shall be provided for the condensing unit and ceiling
suspended arrangement for the indoor units.

10.5 Interconnecting power and control cabling shall be provided between condensing unit and
evaporator unit.

*******

Technical specifications Page -36


Belvedere Club, Gurgaon

Section 7 Split Unit


Non-Ductable Type

1. General

1.1 The Split A.C. system shall be air-cooled consisting of Outdoor units and single/ twin Indoor
units for cooling the space in summer and heating in winter (whenever Heat pumps are
specified).

1.2 The system shall consist of suitable Outdoor units and Indoor units as required,
interconnecting refrigerant piping, control cabling and accessories as required. (All BMS
Compatible)

1.3 The minimum length of Refrigerant piping in any system shall not be less than 25 m and
permit level difference of 10 m between Outdoor and Indoor unit.

2. Outdoor Unit (ODU)


2.1 The Outdoor unit shall be a factory assembled unit housed in a sturdy weather proof casing,
constructed form rust-proofed mild steel panels complete with powder coated finish.

2.2 Each Outdoor shall consist of rotary/ scroll compressor(s), air-cooled condenser as Heat
Exchanger, high efficiency propeller fans with low noise motor, internal Refrigerant piping,
safety controls, Air Inlet grilles, fan protection grille etc. all enclosed in weather proof
housing.

2.3 The Outdoor unit may have single /multiple, Rotary /scroll compressors and shall be able to
operate even in case of breakdown of one of the compressors.

2.4 There shall be a separate refrigerant circuit for each compressor designed to connect with a
matching Indoor unit in case of multiple compressor ODU.

2.5 The Outdoor unit shall be suitable for connection to various types of Indoor units to match
the outdoor units.

2.6 The noise level shall not be more than 62 dB(A) under normal operation, measured
horizontally, 1 m away and 1.5m above ground.

2.7 All the units shall be provided with built-in control panel, for automatic operation.

Technical specifications Page -37


Belvedere Club, Gurgaon

2.8 The units shall be suitable for Refrigerant R -22.

2.9 The ODU may be with either single compressor or multiple compressors.

2.10 Compressors with Inverter will be used whenever specified in Bills of quantity.

3. Compressor
3.1 Compressor (Rotary type)

3.1.1 The rotary compressor shall consist of a rotor mounted in concentric housing and on
antifriction bearing.
3.1.2 Both the spiral disc and rotor shall be mounted on a common shaft with antifriction bearing,
suitable for handling both radial and axial thrust.

3.1.3 The compressor casing shall be fabricated from mild steel of thickness capable of
withstanding the working pressures. The casing shall have built-in oil reservoir with a sump
of adequate capacity.

3.1.4 The compressor shall be complete with a suitable High efficiency motor hermetically sealed
within the compressor housing.

3.1.5 The compressor housing shall also have oil reservoir for lubrication and suitable means like
an oil pump or pressure differential device shall be provided to lubricate all moving parts.

3.1.6 Rotary compressors shall be used in small units with capacities between 1 ton to 2 Tons
capacity.

3.2 Compressor (Scroll type)

3.2.1 The scroll compressor shall consist of two spiral disc, where one is fixed and the other
rotate. The disc shall be mounted eccentrically to allow orbital movement. This shall permit
compression of Refrigerant gas, as it moves up between the eccentric discs.

3.2.2 Both the spiral disc of rotor shall be mounted on a common shaft with anti-friction bearing,
suitable for handling both radial and axial thrust.

3.2.3 The compressor casing shall be fabricated from mild steel of thickness capable of
withstanding the working pressures. The casing shall have built-in oil reservoir with a sump
of adequate capacity.

3.2.4 The compressor shall be complete with a suitable High efficiency motor hermetically sealed
within the compressor housing.

3.2.5 The compressor housing shall also have oil reservoir for lubrication and suitable means like
an oil pump or pressure differential device shall be provided to lubricate all moving parts.

3.2.6 Scroll compressors shall be used in all units larger than 2 Tons capacity and up to 8.5 Tons
capacity.

Technical specifications Page -38


Belvedere Club, Gurgaon

4. Condenser / Heat Exchanger and Fans

4.1 The condenser shall be air-cooled type, where heat exchanger shall be fabricated from
copper tubes, mechanically bonded to aluminum fins to form a cross fin coil. The aluminum
fins shall be given anti-corrosion treatment. This treatment shall be suitable for areas of high
pollution, moisture and salt laden air.

4.2 The condenser fans shall be with multi blades of aerofoil design for low noise level, high
efficiency and fitted with an high efficiency fan motor.

4.3 The fan outlet outlet shall be protected by a suitable wire guard on the outside.

4.4 Suitable devices and heat exchanger means shall be built-in the unit to provide maximum
super-cooling of refrigerant to increase system efficiency.

4.5 The unit shall be complete with master control module.

4.6 All the above component shall be housed in a compact mild steel cabinet having air Inlet
louvers, safety guard on the condenser fan. The ambient shall be mode weather proof using
suitable anti corrosion treatment and finishing point.

5. Indoor Units (IDU)

5.1 The unit shall permit connection to a variety of non ductable Indoor units as per description
given later.

5.2 The capacity of the IDU shall match the capacity of the outdoor unit.

5.3 The types of IDU which may be connected may be any of these given below:

5.5.8 High Wall mounted Unit.


5.5.9 Cassette type of different configuration.
5.5.10 Concealed Ceiling suspended units
5.5.11 Ceiling Suspended High static Unit.
5.5.12 Ceiling Mounted Exposed unit.
5.5.13 Floor standing (exposed or concealed) units.

5.6 Common features of Indoor Units

5.6.1 The cooling / heating evaporator coils of the various types of Indoor Units shall be of direct
expansion type.

5.6.2 The coils shall be fabricated from copper tubes of min 8 mm dia. with extended aluminium
fins and designed for low velocity..

5.6.3 The fins shall be bonded to the tube using hydraulic expansion of tubes ensuring tight
bonding between tube and fins for efficient heat transfer.

Technical specifications Page -39


Belvedere Club, Gurgaon

5.6.4 The coils shall be complete with well designed tube circuiting and liquid distributor.

5.6.5 The control units shall control temperature, fan speed and features specific to each unit such
as night mode, set back, etc.

5.6.6 Suitable drain pan and drain arrangement shall be part of all IDUS.

5.6.7 The control units shall permit control from a corded or a wireless remote controller.

6. High Wall Mounted units

6.7 The high wall mounted units will be complete with cross flow fan, vertical DX coil, filters,
control units and plastic outer cabinet.

6.8 The cross flow fan should be of generous dia. and length to deliver the required air quantity
at high speed and be very quiet with Noise level below 41 dbA .(The sound level can be
tested in the factory as per standard testing norms)

6.9 The fan assembly shall be directly mounted on a low noise, high efficiency motor.

6.10 The DX evaporator coil and other common features shall be as given under para 5.3.

6.11 The air filter shall be electrostatic type to remove dust, polan and other impurities.

6.12 The outer casing shall be made of high grade plastic, complete with return air grille,
motorized supply air louvered opening and suitable metallic back panel for mounting all
items.

7. Cassette type units

7.9 The cassette type Indoor Units may be of any of the three configurations, as given below and
as may be mentioned in Bills of quantity.

7.9.1 Four way or circular air distribution arrangement which ever is specified or is available.

7.9.2 2-way air distribution arrangement.

7.9.3 1-way or corner type air distribution arrangement.

7.10 The unit shall be complete with turbo fans of multiblade type, duly statically and dynamically
balanced to give the required air flow.

7.11 The filter shall be of synthetic type to suit the configuration.

7.12 The unit housing shall have provision for connecting fresh air duct, wherever required.
Technical specifications Page -40
Belvedere Club, Gurgaon

7.13 The unit shall be complete with built-in high head fail-safe pump with safety cutouts.

7.14 The unit shall include all items as given in 5.3

7.15 Each type of unit shall be supplied complete with Air distribution panel whether specified or
not.

7.16 The panel shall have removable return air core for cleaning air filter and maintaining motor
etc.

8. Concealed ceiling suspended unit

8.1 The concealed units shall be complete with fan assembly, DX evaporator coil, air filter, outer
casing and control unit.

8.2 The fan shall be centrifugal type with housing and mounted directly on the motor shaft.

8.3 The air filter shall be preferably electrostatic type.

8.4 The outer casing shall be of heavy gauge G.I. sheet duly treated for long life and shall be
complete with 25 mm deep duly insulated drain pan.

8.5 The unit shall include all other items as listed in Para 5.3.

9. Ceiling Suspended High Static Unit

9.1 The unit shall be complete as described in Para 8, except for the fan section.

9.2 The fans shall be selected and designed for highest air static pressure, to allow for at least 5
to 6 m of ducting with grilles.

10. Ceiling Mounted Exposed Unit

10.1 The exposed type unit shall be similar to the concealed type as described in Para 8, except for
the outer casing.

10.2 The unit shall have a decorative outer casing with built-in supply air grilles and return grilles.

10.3 The casing shall be given anti-corrosive treatment and finished with powder coated paint in
attractive finish.

11. Floor Standing Units

11.1 The floor standing units shall be vertical in design and may be suitable for concealed furred
in installation or cabinet type for exposed installation.
Technical specifications Page -41
Belvedere Club, Gurgaon

11.2 The fans shall be centrifugal type mounted directly on the motor shaft.

11.3 The air filter shall be cleanable electrostatic type.

11.4 The concealed type of vertical unit casing shall be of heavy gauge galvanized sheet with anti-
corrosive paint.

11.5 It should be complete with deep drawn insulated drain pan and shall permit easy access for
filter cleaning and maintenance of coil and fan motor.

11.6 The cabinet type of exposed vertical units shall in addition have a decorative casing with
built in supply and return air grilles.

11.7 The casing shall be given anti-corrosive treatment and finished with powder coated paint in
attractive finish.

11.8 All other components in both type shall be as in para 5.3

12. Indoor Control Unit

12.1 All types of indoor unit shall have one of the following controllers:

12.1.1 Cordless Type


12.1.2 Corded Type

12.2 Unless otherwise specified the controller to be provided shall be as follows:

12.2.1 Cordless Remote: Wall units or other units which are located in an enclosed cabin.

12.2.2 Corded Remote: in open offices or and areas not covered above.

12.3. A Computerized DIP control shall be used to maintain room temperature.

13. Refrigerant Piping

13.1 The condensing unit and evaporator unit shall be interconnected by type ‘l’ seamless copper
refrigerant liquid and suction lines using flared or brazed fittings. Necessary accessories shall be
incorporated in the circuit.

13.2 The suction line shall be insulated with 6 mm closed cell foam insulation.

13.3 The specifications of refrigerant piping are given in subsequent section.

14. Miscellaneous

14.1 The unit shall have a corded electronic remote control housing ON/OFF and speed control,
temperature control and digital display.

Technical specifications Page -42


Belvedere Club, Gurgaon

14.2 Isolation spring shall be provided to hang the Indoor units and isolation pad to be provided for the
outdoor units.

14.3 Drain line shall be provided from Indoor unit upto drain trap. (To be priced separately).

14.4 Suitable M.S. angle iron supporting frame shall be provided for the condensing unit and ceiling
suspended arrangement for the indoor units.

14.5 Interconnecting power and control cabling shall be provided between condensing unit and
evaporator unit.

*******

Section-8 Ventilation System

1. General

The air washers, kitchen scrubbers, ventilation fans/blowers shall be complete in all respects
and shall generally comply with the specifications given below: (All BMS Compatible)

2. Kitchen Scrubber (Dry Type)

The Dry type kitchen scrubber shall be complete in all respects and shall generally comply
with the following specifications given below:

2.1 Exhaust Air System:

Supply, Installation, Testing and Commissioning of Exhaust Air System each comprising of
extract air intake section, electrostatic precipitation technology based dry type air cleaner to
remove Oil, Smoke & fumes from the exhaust air, fan section with floor standing forward
curved DIDW centrifugal fan/s, TEFC squirrel cage induction motor, belt drive package.

2.2 Electrostatic Section:

2.2.1 Made of 16 gauge galvanized sheet, High bake epoxy powder coated, Washable type
aluminum mesh pre-filter, Washable type aluminum mesh post filter, Stainless steel spiked
ionizers to create high voltage DC field, aluminum collector plates which should be
alternatively charged positive & negative with large collecting area with 14” deep cell, to
work as magnet for charged smoke & oil particles.

2.2.2 Average efficiency of 90-95% in single pass as per DOP test method. Electrostatic
Precipitator should be able to charge particles from 0.01 micron to 10 micron through solid
state power supply. Collector cell should be of permanent type and slide out facility for easy
removal for cleaning. Operating Voltage: 220V/1Ph/ 50Hz, Power consumption: 50 watts
Technical specifications Page -43
Belvedere Club, Gurgaon

each unit. Ionizing Voltage: 12.5 – 13.0 kVDC, Collector Cell Voltage: 6.0 – 6.5 kVDC, System
should be fitted with interlock switch for safety, The system should be able connected to a
fan section to achieve airflow of 500 FPM across the air cleaner. The filter should have a
constant pressure drop.

2.3 Enclosure/Housing

2.3.1 Enclosure shall be made of powder coated 16 gauge GI sheet with riveted and soldered lap
joints casing angles shall also be of 40mm x 40mm. Angle shall be riveted and soldered to
the casing.

2.3.2 The front panels shall be easily open-able for servicing the fan sections. It should provide
easy access to remove air filters for cleaning.

2.3.3 The opening for access doors and gaps between sections shall be provided with the
neoprene rubber gaskets.

2.3.4 The panels shall be fixed to the frame work with self tapping stainless steel screws and both
ends of the screw shall be provided with rubber caps.
2.3.5 The access door to fan section is to be provided with a switch to shut the fan when the door
is open.

2.4 Fan Section

2.4.1 The fan shall be Imported forward curved, double inlet double width type. The wheel and
housing shall be fabricated from heavy gauge galvanized steel. The fan impeller shall be
mounted on a solid carbon steel shaft supported to housing with angle iron frame and pillow
block heavy duty ball. The fan shall be selected for a speed not exceeding 1000 RPM. The
impeller and fan shaft shall be statically and dynamically balanced. The fan outlet velocity
shall not be more than 1800 FPM. Fan housing with motor shall be mounted on a common
aluminium base mounted inside the air handling housing on anti vibration springs mounts or
cushy foot mount. The fan outlet shall be connected to casing with the help of fire retardant
flexible canvass. The fan shall be complete with multi ‘V’ belt drive and adjustable motor
mounting base. Inspection door shall be installed with micro-switch arrangement with
lighting within the fan section. Micro-switch shall be interlocked with blower and light with
resetting arrangement.

3. Kitchen Scrubber (Spray Type)

3.1 Spray Section

3.1.1 Spray section and tank shall be fabricated from 18 G 304 A stainless steel sheets with bolted
construction having suitable stiffeners.

3.1.2 The section shall be complete with SS 304 water distribution header having ports and sized
for uniform and adequate water flow through perforated SS 304 pipes. The spray nozzles
shall be of brass construction.

3.1.3 The tank shall be fitted 3/4” (20 MM) float valve of commercial grade brass.
Technical specifications Page -44
Belvedere Club, Gurgaon

3.1.4 The spray section shall have provision for fixing one or two sets of air filters as specified
later.

3.2 Water Sump

3.2.1 The water sump below the spray section shall be of 3mm MS plate with welded joints. The
tank shall be complete with makeup, overflow and drain connections. A float valve shall be
provided for makeup water line. The tank shall be given 2 coats of corrosion resistance paint
and final coat of black enamel paint.

3.3 Drift Eliminators

3.3.1 Drift eliminators shall be of PVC supported at the top and bottom fixed to the spray section
by means of GI notched bars. Eliminators shall be a set of vertical plates with a series of
bends and deflections to give large surface area on which water drops and dust shall be
impinge. Eliminators shall be properly stiffened at the sides.

Technical specifications Page -45


Belvedere Club, Gurgaon

3.4 Distribution Plate

3.4.1 Distribution plate shall be GI 18G with sufficient number of circular opening uniformly
spaced for even distribution of air for spray type air washer.

3.5 Pumps

3.5.1 The water distribution pumps shall be of heavy duty, vertical type mounted inside the tank.
It shall be complete with adjustable bleed of arrangement to prevent concentration of
undesirable salts.

4. Air Washers (Packaged Type)

4.1 The packaged air washers shall be of G.I. Sheet metal and Stainless Steel sectionalized
constructions and shall include fan section, cooling pad section, motor drive etc.

4.2 Enclosure/Housing

4.2.1 The enclosure shall be single/double skin as given in BOQ design with the main frame work
made of extruded aluminum structural section.

4.2.2 The panels shall be of 16G pre-coated/powder coated galvanized sheet.

4.2.3 The side panels shall be easily openable for servicing the fan and motor and pad section.

4.2.4 The opening for access doors and gaps between sections shall be provided with the
neoprene rubber gaskets fixed in grooves in the extruded sections.

4.2.5 The panels shall be fixed to the frame work with self tapping stainless steel screws and both
ends of the screw shall be provided with rubber caps.

4.2.6 The access door to fan section is to be provided with a switch to shut the fan when the door
is open.

4.3 Fan Section

4.3.1 The fan shall be forward curved, double inlet double width type.

4.3.1 The wheel and housing shall be fabricated from heavy gauge galvanized steel. The fan
impeller shall be mounted on a solid carbon steel shaft supported to housing with angle iron
frame and pillow block heavy duty ball.

4.3.2 The fan shall be selected for a speed not exceeding 1000 RPM. The impeller and fan shaft
shall be statically and dynamically balanced.

4.3.3 The fan outlet velocity shall not be more than 2000 FPM.

4.3.4 The fan housing with motor shall be mounted on a common aluminum base mounted inside
the air handling housing on anti vibration springs mounts or cushy foot mount.
Technical specifications Page -46
Belvedere Club, Gurgaon

4.3.5 The fan outlet shall be connected to casing with the help of fire retardant flexible canvass.
The fan shall be complete with multi ‘V’ belt drive and adjustable motor mounting base.

4.3.6 Inspection door shall be installed with micro-switch arrangement with lighting within the fan
section. Micro-switch shall be interlocked with blower and light with resetting arrangement.

4.4 Other Items

4.4.1 The other item such as cooling pad, pumps, airfilters etc. shall described earlier in 2.3, 2.4 &
2.5.

4.5 Miscellaneous
Necessary accessories shall be provided for air washers, wherever required for proper
operation and shall also include.

4.5.1 PVC eliminator to avoid water drift fixed to the cooling pad housing and tank.
4.5.2 Necessary PVC piping for water circulation.
4.5.3 Vibration isolators for the pumps.
4.5.4 Nuts, bolts, shims etc., as required for the equipment.
4.5.5 Float valve in the water tank, along with quick fill connection.
4.5.6 Gate valves in drain, make up, quick fill line etc, as required.
4.5.7 Built in isolator switches for the fan and pump motor and wiring from the isolators up to the
respective motors.

4.6 Limitation
The air velocity limits are as follows :-

4.6.1 Velocity across cooling pads shall not exceed 2.54 M/s (500 FPM).
4.6.2 Velocity at blower outlet shall not exceed 9.14 M/s (1800 FPM).

5. Fan Section for Fresh Air/ Exhaust /Pressurization

5.1 The fan section for staircase & lift pressurization should be forward curved fans and for
exhaust applications the fan section should be backward curved type.

5.2 Single skin fan section housing shall be fabricated of 16 G precoated or powder coated
galvanized steel sheet. All supporting frames shall be of Aluminum section. It shall have
suitable size of inlet & outlet.

5.3 The imported Centrifugal fan (DIDW) or imported forward curved fan along with motor shall
be mounted on the common base of Aluminum inside the housing including anti-vibration.
Blower shall confirm to the specifications given earlier.

5.4 The fan outlet shall be connected to the casing with the help of fire retardant double flexible
canvass.

Technical specifications Page -47


Belvedere Club, Gurgaon

5.5 The two sides on the air inlet shall be provided with 20G (powder coated) welded mesh
angle iron frame work for rigidity. The mesh shall not exceed 12.5mm size. It is applicable
only for Air washer and exhaust fan if it is placed in the masonry room.

5.6 The fan shall be complete with motor, belt pulley with all accessories.

5.7 The enclosure shall be provided with access panel and the opening for access doors shall be
provided with the neoprene rubber gasket fixed in the aluminum sections.

5.8 In case of exhaust, the fan outlet shall have Louvers with bird screen.

5.9 In case of fresh air the fan inlet shall have fresh air Louvers with bird screen as well as
removable washable filters.

5.10 In case of lift & Staircase pressurization the fan inlet shall have fresh air louvers with bird
screen.

5.11 In case of smoke exhaust fans the motor, belts and pulleys shall be out of air stream.

6. Accessories for Fan Section

All necessary accessories shall be provided for proper operation and shall also include (As
part of Unit Price).

6.1 Dunlop cushy foot vibration isolators for the blowers.


6.2 Double canvass connections at the outlet of each fan.
6.3 Nuts, bolts, shims etc. as required for the grouting of the equipment.
6.4 Slide rails for mounting the motor and belt adjustments.
6.5 Bird Screens in the Inlet.
6.6 Louvers for Fresh Air and exhaust openings.

6.7 Detachable and washable fresh air of 80% efficiency down to 10 micron filters at the inlet.

7 Limitation for Fan Sections

7.1 The air velocity limits shall be as per Schedule of Equipment and/or BOQ but in no case
exceed:

7.2 Velocity at blower outlet shall not exceed 9.15 M/s (1800 FPM).

7.3 Inlet Velocity shall be limited to 5.08 M/S (1000 FPM).

8. Grease Filter & Carbon filter

8.1 The standard pre-filters shall be with 5 layers of SS-304 wire mesh, fixed in a 16 G GI frame
with handles for ease of removal.

Technical specifications Page -48


Belvedere Club, Gurgaon

8.2 The above set of filters shall be fixed in filter frames made of 16 G.I. sheets, shaped to
prevent air leakage. The filters shall be easily removable. The filter section may from part of
the spray section or may be bolted separately to the spray section.

8.3 Carbon filter shall be installed to eliminate the particles in the smoke.

9. Motors and Starters

9.1 The motor for each blower, shall be totally enclosed, fan cooled, squirrel cage induction
type and conform to specifications as given under section 3.

9.2 The starters shall be “direct on line” type up to 7.5 H.P. All larger starters shall be of fully
automatic star delta type.

9.3 The pumps shall be provided with single phase, self tripping starter.

10. Miscellaneous items for Kitchen Scrubber

Necessary accessories shall be provided wherever necessary for proper operation and shall
also include.

10.1 PVC eliminator fixed to the spray section to avoid water spillage.

10.2 Necessary G I piping for water circulation.

10.3 Vibration isolators for the blowers and pumps.

10.4 Double Canvass connections at the outlet of each fan.

10.5 Zinc coated/Cadmium coated Nuts, bolts, shims etc., as required for the grouting of the
equipment.

10.6 PVC Float valve in the spray tank, along with quick fill connection.

10.7 Heavy Duty as specified in BOQ Gate valves in drain, make up, quick fill line etc, as required.

10.8 Built in isolator switches for the fan and pump motor and wiring from the isolators up to the
respective motors.

11. Limitation
11.1 The air velocity limits are as follows :-
11.1.1 Velocity across scrubber not exceeding 2.54 M/s (500 FPM).
11.1.2 Velocity at blower outlet-not exceeding 9.15 M/s (1800) FPM.

12. Centrifugal blowers (Backward Curved/Forward Curved)

12.1 The imported backward curved centrifugal blowers shall be double/single inlet,
double/single width, non-overloading type, of suitable construction. The blower

Technical specifications Page -49


Belvedere Club, Gurgaon

performance must be rated in accordance with approved test codes and procedures. The
centrifugal fans should conform to and shall be AMCA certified.

12.2 The blower housing comprising of scroll/housing shall be fabricated out of 18 Gauge (min.)
G.I. Sheet, sectional construction with the housing fixed to the side plates in “Pittsburg Lock”
form system. Outlets shall be flanged to assure proper duct connections. Inlet cones shall be
spun venturi type, or curved vane type, to ensure smooth air entry. The frame shall be of
angle iron in welded construction with polyester powder coating.

12.3 Impeller shall be fabricated from sheet steel with backward curved, properly designed.
blades, with heavy C.I. Hub and shall be both dynamically and statically balanced, to a close
tolerance for quiet and vibration free performance.

12.4 Shaft shall be of C45 carbon steel, sized adequately and shall be accurately ground and
polished to a close tolerance. It shall be coated with anti-corrosion varnish after assembly.

12.5 Bearings shall be self aligning, heavy duty deep grooved ball or spherical roller type with
integral dust and grease seals. They shall be mounted on cast iron supports with grease
points.

12.6 The impeller shall be provided with polyester powder coating finish.

12.7 The fan shall be selected for a speed not exceeding 1800 RPM. The fan outlet velocity shall
not exceed 1800 FPM.

12.8 The Imported forward curved fans shall be double inlet double width type.

12.9 The wheel & housing shall be fabricated from heavy gauge galvanized steel. The fan
impeller shall be mounted on a solid C40 carbon steel shaft supported to housing with
angle iron frame & pillow block heavy duty ball.

12.10 The fan shall be selected for a speed not exceeding 1400 RPM. The fan outlet velocity shall
not exceed 1800 FPM.

13. Blower drive assembly


13.1 Drive assembly for each blower shall consist of blower pulley, motor pulley, a set of ‘V’
belts, belt guards, and belt tension adjusting device.

13.2 Pulleys shall be selected to provide the required speed. They shall be multi-groove type, with
section and grooves selected to transmit 33% more load than the required power and shall
be statically balanced.

13.3 The belt guards shall be fabricated of M.S. Sheet (powder coated at factory) with angle iron
reinforcements and expanded metal screen to avoid finger insertion.

14. Motors and starters


14.1 The motor for each blower, shall be squirrel cage induction type and conform to
specifications as given under section on control panel, motors and switchgear. The motor
H.P. Shall be at least 20% more than the limit load of fan and of minimum rating as given
Technical specifications Page -50
Belvedere Club, Gurgaon

under ‘Schedule of Equipments’. The Motors shall be as per IS-325-1996 (Revised to date)
with F-Class of Insulation.

15. Axial flow fans


15.1 The Axial Fan Blades shall be of Cast Aluminum of aerofoil design for high efficiency and high
static pressure. The blades shall be joined together on cast aluminum hub.
15.2 The mounting ring shall be of CRCA/sheet steel with steel brackets to connect the frame,
with the Fan/Motor assembly. Rubber mounts shall be provided between the mounting
frame and the mounting brackets.

15.3 The fan assembly shall be statically and dynamically balanced.

15.4 The fan motor shall be totally enclosed squirrel cage type.

15.5 The axial flow fans should be provided with wire guard and gravity louvre (factory
fabricated).

15.6 Axial Flow fan fans with motor, supporting frame with bird screen, access panel ,with
necessary civil work as per specifications and drawings. (The Axial flow fan should be fire
rated at 250 deg C for 2 hours)

16. Ceiling Exhaust Fans

16.1 The fan shall have corrosion resistant galvanized steel scroll and housing with built in grille.
16.2 The outlet duct collar shall be round with integral back draft damper.
16.3 The fan shall have single inlet forward curved wheel.
16.4 The fan shall have adjustable mounting brackets.

17. In-Line Fans

Inline fans shall be complete with centrifugal impeller, casing, direct driven motor, vibration
isolators, direction of discharge and rotation position shall be as per the job requirement
and shall be marked on the fan assembly.

17.1 Housing shall be constructed of hot rolled GSS sheet metal construction.

Housing metal parts shall be either spot-welded or screwed or mounted together with
rivets. Indication showing rotation arrow and make, model number and duty conditions of
the fan shall be available on the housing.

17.2 Fan wheel shall be forward/backward curved type, fan wheel shall be statically and
dynamically balanced.

17.3 Ball bearings are completely maintenance free and can be used in any mounting position at
maximum indicated temperature. The bearing lubricant is suitable for a minimum ambient
temperature of minus 150C (admissible for a short time without reaching dew point at minus
300C). For applications at maximum indicated ambient temperature life expectancy shall be
40000 hours minimum.

Technical specifications Page -51


Belvedere Club, Gurgaon

17.4 Fan motor, fans shall be supplied with built-in-thermal contact (TK) at the critical high
temperature point (“B” = 1300C or “F” = 1550C). The thermal contact will open and break the
power supply to the fan, Fan motors have insulation class “B” or “F” and protection class
IP44 or IP54.

17.5 Drive of fan shall be direct driven.

************

Section 9 Duct Works and Outlets

1. General

1.1 The work under this part shall consist of furnishing labour materials, equipment and
appliances as specified necessary and required to install all sheet metal and other allied
work to make the air conditioning supply, ventilating, and exhaust system ready for
operation as per drawings.

1.2 Except as otherwise specified all duct work and related items shall be in accordance with
these specifications.

1.3 Duct work shall mean all ducts, casings, dampers, access doors, joints, stiffners and
hangers.

2. Manual Fabricated Duct Work

2.1 The ducts shall be fabricated from galvanized steel sheets class VIII(120 gms/sqm)
conforming to ISS:277-1962 (revised) or aluminium sheets conforming to ISS:737-1955
(wherever aluminium ducts are specified).

2.2 All duct work, sheet metal thickness and fabrication unless otherwise directed, shall strictly
meet requirements, as described in IS: 655-1963 with amendment-I (1971 edition)

The thickness of the sheet shall be as follows:-

Size of Duct Sheet Fastner Type of Joints Bracing if any Support


Thickness Size Angle

2.2.1 Upto 750 mm 0.63 mm 3/8” G.I. Flange 25x25x3 mm

2.2.2 751 mm to 0.80 mm 3/8” 25x25x3 mm 25x25x3 mm at 25x25x3 mm


1000 mm Angle iron the rate of 1m
frame with 8 from joints
mm dia nuts &
bolts

2.2.3 1001 mm to 0.80 mm 5/8” 40x40x5 mm 40x40x5 mm at 40x40x5 mm


Technical specifications Page -52
Belvedere Club, Gurgaon

1500 mm Angle iron the rate of 1 m


frame with 8 from joints
mm dia nuts &
bolts

2.2.4 1501 mm to 1.00 mm 5/8” 50x50x5 mm 40x40x5 mm at 40x40x6 mm


2250 mm Angle iron the rate of angle
frame with 10 1.2m to be
mm dia nuts & Braced from
bolts at 125 joints.
mm centre.

Technical specifications Page -53


Belvedere Club, Gurgaon

2.2.5 2251 mm and 1.25 mm 5/8” 50x50x6 mm 40x40x5 mm at 50x50x6 mm


above Angle iron the rate of 1.2m with MS rods
frame with 10 from joints of 12 mm dia.
mm dia nuts &
bolts at 125
mm centre.

2.3 The gauges, joints and bracings for sheet metal duct work shall further conform to the
provisions as shown on the drawings.

2.4 Ducts larger than 600 mm shall be cross broken, duct sections upto 1200 mm length may be
used with bracing angles omitted.

2.5 Changes in section of duct work shall be affected by tapering the ducts with as long a taper as
possible. All branches shall be taken off at not more than 45 DEG. Angle from the axis of the
main duct unless otherwise approved by the Engineer-In-Charge.

2.6 All ducts shall be supported from the ceiling/slab by means of steel wire system or M.S. Rods of
10mm (3/8") DIA with M.S. Angle at the bottom. The rods shall be anchored to R.C. Slab using
metallic expansion fasteners.

3. Factory Fabricated Duct Work


3.1 Material

3.1.1 All ducting shall be fabricated of LFQ (Lock Forming Quality) grade prime G.I. raw material
furnished with accompanying Mill test Certificates. Galvanizing shall be of 120gms/sq.m. (total
coating on both sides).

3.1.2 In addition, if deemed necessary, samples of raw material, selected at random by owner’s site
representative shall be subject to approval and tested for thickness and zinc coating at
contractor’s expense.

3.1.3 The G.I. raw material should be used in coil-form (instead of sheets) so as to limit the
longitudinal joints at the edges only, irrespective of cross-section dimensions.

3.2 Governing Standards


3.2.1 Unless otherwise specified here, the construction, erection, testing and performanceof the
ducting system shall conform to the SMACNA-1995 standards (“HVAC Duct Construction
Standards-Metal and Flexible-Second Edition-1995” SMACNA)

3.3 Duct Connectors and Accessories


3.3.1 All transverse duct connectors (flanges/cleats) and accessories/related hardware such as support
system shall be zinc-coated (galvanized).

3.4 Fabrication Standards


3.4.1 All ductwork including straight sections, tapers, elbows, branches, show pieces, collars, terminal
boxes and other transformation pieces must be factory-fabricated. Equivalency will require
fabrication by utilizing the following machines and processes to provide the requisite quality of
ducts and speed of supply.
Technical specifications Page -54
Belvedere Club, Gurgaon

3.4.2 Coil lines to ensure location of longitudinal seams at corners/folded edges only to obtain the
required duct rigidity and low leakage characteristics. No longitudinal seams permitted along any
side of the duct.

3.4.3 All ducts, transformation pieces and fittings shall be made on CNC profile cutters for required
accuracy of dimensions, location and dimensions of notches at the folding lines.

3.4.4 All edges shall be machine treated using lock-formers and roller for furning up edges.

3.4.5 Sealant dispensing equipment shall be used for applying built-in sealant in Pittsburgh lock where
sealing of longitudinal joints are specified.

3.5 Selection of G.I. Gauge and Transverse Connectors

3.5.1 Duct Construction shall be in compliance with 1” (250 Pa)w.g. static norms as per SMACNA.

3.5.2 All transverse connectors shall be the 4-bolt slip-on flange system or similar 4-bolt systems with
built-in sealant, if any. To avoid any leakage additional sealant shall be used.

3.5.3 The specific class of transverse connector and duct gauge for a given duct dimensions shall be
1”(250 Pa) pressure class.

3.5.4 Non-toxic, AC-applications grade P.E. or PVC gasketing shall be provided between all mating
flanged joints. Gasket sizes shall conform to flange manufacturer’s specification.

3.6 Duct Construction

3.6.1 The fabricated duct dimensions shall be as per approved drawings and all connecting sections
shall be dimensionally matched to avoid any gaps.

3.6.2 Dimensional Tolerances : All fabricated dimensions shall be within  1.0 mm of specified
dimension. To obtain required perpendicularity , permissible diagonal tolerances shall be  1.0
mm per metre.

3.6.3 Each duct pieces shall be identified by color coded sticker which shall indicate specific part
numbers, job name, drawing number, duct sizes and gauge.

3.6.4 Ducts shall be straight and smooth on the inside. Longitudinal seams shall be airtight and at
corners only, which shall be either Pittsburgh or Snap Button Punch as per SMACNA practice, to
ensure air tightness.

3.6.5 Changes in dimensions and shape of ducts shall be gradual (between 1:4 and 1:7). Turning vanes
or air splitters shall be installed in all bends and duct collars designed to permit the air to make
the turn without appreciable turbulence.
3.6.6 Plenums shall be shop/factory fabricated panel type and assembled at site.

3.6.7 The gauges, joints and bracings for sheet metal duct work shall further conform to the
provisions as shown on the drawings.

Technical specifications Page -55


Belvedere Club, Gurgaon

3.6.8 Ducts larger than 600mm shall be cross broken, duct sections upto 1200 mm length may be
used with bracing angles omitted.
3.6.9 Changes in section of duct work shall be affected by tapering the ducts with as long a taper as
possible. All branches shall be taken off at not more than 45 DEG. Angle from the axis of the
main duct unless otherwise approved by the Engineer-In-Charge.

3.7 Duct Supporting Arrangement

3.7.1 Ducts and accessories such as dampers, slot diffusers, plenums etc. shall be suspended from
the roof slab using steel wire hangers consisting of performed wire rope sling with either a
ferruled loop, permanently fixed threaded M6’(or M8) stup or permanently fixed nipple end
with toggle at one end or hook, eyelet etc. The end fixing and the wire shall be of the same
manufacture. The system shall be secured with self locking grip at the other end.

3.7.2 Twisted wire hangers shall be tested by Lloyds Register, APAVE, TUV, UL, CSA and SMACNA
and also approved by ULC & CSA. It shall comply with the requirements of DW/144 etc. and
shall be manufactured to BSEN 12385: 2002.
3.7.3 Horizontal duct work shall be adequately secured and supported using braided hangers
formed of galvanized wire rope in a cradle support method at maximum distance of 2200
mm centre. Duct support shall be through anchor fastners driven by electrically operated
gun.

3.7.4 The braided wire hanger shall be selected as per suitable working load limit as given in table
1. Ducts shall be supported in accordance with schedule 1 as given under:

Size Minimum Breaking Wire Rope Tensile Strength Working Load Limit
Load of Wire Rope Construction (Nmm2) (kg/Ibs)

NO 1 80 kg/176 Ibs 7 x 7 (6/1) 1770 0-10 kg/0-22 Ibs

NO 2 260 kg/572 Ibs 7 x 7 (6/1) 1770 10-45 kg/23-100 Ibs

NO 3 580 kg/1276 Ibs 7 x 7 (6/1) 1770 45-90 kg/101-200 Ibs

NO 4 1500 kg/3300 Ibs 7 x 19 (12/6/1) 1770 90-225 kg/210-495 Ibs

NO 5 2160 kg/4752 Ibs 7 x 19 (12/6/1) 1770 225-325 kg/496-715 Ibs


Note: Minimum Safety Factor shall be 5:1

Duct Pressure Upto 250 Pa Duct Pressure 251 Pa to 500 Pa


Max. duct Gauge Wire Max. duct Gauge Wire
Size (mm) Hanger No. Size (mm) Hanger No.
1-500 26 2 1-500 mm 26 2
501- 1000 24 3 501-750 mm 24 2
1001-1200 24 3 751-1000 mm 24 3
1201-1500 24 3 1001-1200 mm 22 4
1501-1800 22 4 1201-1300 mm 20 4

Technical specifications Page -56


Belvedere Club, Gurgaon

1801-2100 20 4 1301-2700 mm 18 4
2101-2700 18 4

3.7.5 Factory Fabricated ducts shall have the thickness of the sheet as follows :

Rectangular External Pressure 250 Pa


Ducts G.S. Duct Section Length 1.2 m ( 4 ft)
Maximum Duct Gauge Sheet Fastner Joint Type 4 Bolt Bracing Duct Support of
Size Thickness Size Transverse Duct Spacing with MS angle with
(mm) Connector (TDC ) GI tie Rods GI Threaded
With Built In Rod/ Steel Wire
Sealant (as detailed in
separate chart)

1-500 mm 26 0.5 4 bolt TDC Nil 25x25x3mm


with GI 8 mm
501-750 mm 24 dia threaded rod
3/8" with Factory
fabricated "W"
0.63 bracket/with
Steel wire

751-1000 mm 24 4 bolt TDC 1 No. 12 40x40x5mm


1001-1200 mm 22 4 bolt TDC mm GI with 10 mm dia
0.8 Threaded rod/ with Steel
1201-1300 mm 22 4 bolt TDC
1301-1500 mm 22 4 bolt TDC cross tie rod wire
1501-1800 mm 20 4 bolt TDC for each
piece of duct
50x50x6mm
1801-2100 mm 20 4 bolt TDC 2 No. 12 mm with 10mm dia
0.1 GI threaded rod/with Steel
cross tie rod wire
5/8" for each
piece of duct
2101-2250 mm 20 4 bolt TDC
Min. 3 No. 50x50x6mm
2251-2400 mm 18 4 bolt TDC
12 mm GI with 10mm dia
2401 mm and 18 4 bolt TDC threaded rod/with Steel
above 1.25 cross tie rod wire
for each
piece of duct

Technical specifications Page -57


Belvedere Club, Gurgaon

3.8 Documentation to Measurements

3.8.1 For each drawing, all supply of ductwork must be accompanied by computer-generated
detailed bill of material indicating all relevant duct sizes, dimensions and quantities. In
addition, summary sheets are also to be provided showing duct areas by gauge and duct size
range as applicable.

3.8.2 Measurement sheet covering each fabricated duct piece showing dimensions and external
surface area along with summary of external surface area of duct gauge-wise.

3.8.3 All duct pieces shall have a part number, corresponding to the serial number assigned to it in
the measurement sheet. The above system shall ensure speedy and proper site
measurement, verification and approvals.

3.9 Testing

3.9.1 After duct installation, a part of duct section (approximately 5% of total ductwork) may be
selected at random and tested for leakage. The procedure for leak testing should be
followed as per SMACNA- “HVAC Air Duct Leakage Test Manual: (First Edition).

4. Installations

4.1 During the construction, the contractor shall temporarily close duct openings with sheet
metal covers to prevent debris entering ducts and to maintain opening straight and square,
as per direction of Engineer-In-Charge.

4.2 Great care should be taken to ensure that the duct work does not extend outside and
beyond height limits as noted on the drawings.

4.3 All duct work shall be of high quality approved galvanized sheet steel guaranteed not to
crack or peel on bending or fabrication of ducts. All joints shall be air tight and shall be
made in the direction of air flow.

The ducts shall be re-inforced with structured members where necessary, and must be
secured in place so as to avoid vibration of the duct on its support.

4.4 All air turns of 45 degrees or more shall include curved metal blades or vanes arranged so
as to permit the air to make the abrupt turns without an appreciable turbulence. Turning
vanes shall be securely fastened to prevent noise or vibration.

4.5 The duct work shall be varied in shape and position to fit actual conditions at building site.
All changes shall be subjected to the approval of the Engineer-In-Charge. The contractor
shall verify all measurements at site and shall notify the Engineer-In-Charge of any
difficulty in carrying out his work before fabrication.

Technical specifications Page -58


Belvedere Club, Gurgaon

4.6 Sponge rubber or approved equal gaskets of 6 mm maximum thickness shall be installed
between duct flanges as well as between all connections of sheet metal ducts to walls,
floor columns, heater casings and filter casings. Sheet metal connections shall be made to
walls and floors by means of wooden member anchored to the building structure with
anchor bolts and with the sheet screwed to them.

4.7 Flanges bracings and supports are to be black, mild steel and are to be painted with rust
proof primer on all surfaces before erection. Accessories such as damper blades and access
panels are to be of materials of appropriate thickness and the finish similar to the adjacent
ducting, as specified.

4.8 Joints, seams, sleeves, splitters, branches, takeoffs and supports are to be as per duct
details as specified, or as decided by Engineer-In-Charge.

4.9 Joints requiring bolting or riveting may be fixed by Hexagon nuts and bolts, stove bolts or
buck bolts, rivets or closed centre top rivets or spot welding. Self tapping screws must not
be used. All jointing material must have a finish such as cadmium plating or Galvanized as
appropriate.

4.10 Fire retarding flexible joints are to be fitted to the suction and delivery of all fans. The
material is to be normally double heavy canvass or as directed by Engineer-In-Charge. On all
circular spigots the flexible materials are to be screwed or clip band with adjustable screws
or toggle fitting. For rectangular ducts the material is to be flanged and bolted with a
backing flat or bolted to mating flange with backing flat.

4.11 The flexible joints are to be not less than 75 mm and not more than 250 mm between
faces.

4.12 he duct work should be carried out in a manner and at such time as not to hinder or delay
the work of the other agencies especially the boxing or false ceiling contractors.

4.13 Duct passing through brick or masonary, wooden frame work shall be provided within the
opening. Crossing duct shall have heavy flanges, collars on each side of wooden frame to
make the duct leak proof.

5. Access panel

5.1 A hinged and gasketed access panel measuring at least 450 mm x 450 mm shall be provided
on duct work before each reheat coil and at each control device that may be located
inside the duct work.

6. Miscellaneous

6.1 All duct work joints are to be true right angle and with all sharp edges removed.

6.2 Sponge rubber gaskets also to be provided behind the flange of all grilles.

6.3 Each shoot from the duct, leading to a grille, shall be provided with an air deflector to divert
the air into the grille through the shoot.
Technical specifications Page -59
Belvedere Club, Gurgaon

6.4 Diverting vanes must be provided at the bends exceeding 600 mm and at branches
connected into the main duct without a neck.

6.5 Proper hangers and supports should be provided to hold the duct rigidly, to keep them
straight and to avoid vibrations. Additional supports are to be provided where required for
rigidity or as directed by Engineer-In-Charge.

6.6 The ducts should be routed directly with a minimum of directional change.

6.7 The duct work shall be provided with additional supports/hangers, wherever required or as
directed by the Engineer-In-Charge, at no extra cost.

6.8 All angle iron flanges to be welded electrically and holes to be drilled.

6.9 All the angle iron flanges to be connected to the GSS ducts by rivets at 100 mm centres.

6.10 All the flanged joints, to have a sponge rubber packing stuck to the flanges with suitable
adhesive.

6.11 The G.S.S. ducts should be lapped 6 mm across the flanges.

6.12 The ducts should be supported by approved type supports at a distance not exceeding 2.0
Metres.

7. Testing

7.1 After completion, all duct system shall be tested for air leakage.

7.2 The entire air distribution system shall be balanced to supply the air quantity as required in
various areas and the final tabulation of air quantity through each outlet shall be
submitted to the Engineer-In-Charge for approval.

*****

Technical specifications Page -60


Belvedere Club, Gurgaon

Section 10 Duct Accessories

1. Dampers

1.1 Splitter Dampers

1.1.1 At the junction of each branch duct with main duct and split of main duct, volume dampers
must be provided. Dampers shall be two gauges heavier than the gauge of the large duct and
shall be rigid in construction.

1.1.2 The dampers shall be of an approved type, lever operated and complete with locking devices
which will permit the dampers to be adjusted and locked in any positions and clearly
indicating the damper position.

1.1.3 The dampers shall be of splitter, butterfly or louver type. The damper blade shall not be less
than 1.25 mm (18) Gauge, reinforced with 25 mm angles 3 mm thick along any unsupported
side longer than 250 mm. Angles shall not interfere with the operation of dampers, nor cause
any turbulence.

2. Opposed Blade Dampers (Duct)


2.1 Automatic and manual volume opposed blade dampers shall be complete with frames and
nylon bush as per drawings. Dampers and frames shall be constructed of 1.6 mm steel sheets
and blades shall be of extruded aluminium of aerofoil design. The dampers for fresh air inlet
shall additionally be provided with fly mesh screen, on the outside, of 0.8 mm thickness with
fine mesh.

2.2 Wherever required for system balancing, a balancing opposed blade damper with quadrant and
thumb screw lock shall be provided.

2.3 After completion of the duct work, dampers are to be adjusted and set to deliver air flow as
specified on the drawings.

3. Fire Damper (Motorized)


3.1 All supply and return air ducts shall be provided with approved make fire and smoke dampers of
at least 90 minutes fire rating certified by CBRI Roorkee as per UL 555: 1973.

3.2 Fire Damper blades & outer frame shall be formed of 1.5 mm galvanized sheet steel. The
damper blade shall be pivoted on both ends using chrome plated spindles of self lubricated
bronze bushes. Stop seals will be provided on top and bottom of the damper housing made of
16 G galvanized sheet steel. For preventing smoke leakage side seals will be provided.

In normal position damper blade shall be held in close position with the help of a 220V
operated motorized actuators thereby preventing air passage without creating any noise or
chatter.

3.3 The damper shall be opened through electric actuator. The actuator shall be activated with the
help of a signal from smoke detector. Smoke detector shall also be either provided by A/C
contractor or Fire Fighting agencies. The Fire Damper shall be provided with micro switches

Technical specifications Page -61


Belvedere Club, Gurgaon

with bakelite base to stop fan motor in the event of damper closure. The reopening of damper
shall be manual.

3.4 The Fire Dampers shall be mounted in fire rated wall with a duct sleeve 600 mm long. The
sleeve shall be factory fitted on fire damper. The joints at sleeve end shall be Slip on type
minimum thickness of GI sheet shall be 18 G.

3.5 The damper shall be installed in accordance with the installation method recommended by the
manufacturer.

4. Flexible Ducts

4.1 The flexible ducts shall be machine made of spiral design with aluminium sheets.

4.2 The duct shall be factory insulated.

4.3 The connections shall be complete with adjustable clip bands of G.I.

5. Access panel

5.1 A hinged and gasketed double skin, factory fabricated access panel measuring at least 450 mm
x 450 mm shall be provided on duct work before each fire damper and at each control device
that may be located inside the duct work.

6. Miscellaneous

6.1 All duct work joints are to be true right angle and with all sharp edges removed.

6.2 Sponge rubber gaskets also to be provided behind the flange of all grilles.

6.3 Each chute from the duct, leading to a grille, shall be provided with an air deflector to divert the
air into the grille through the shoot.

6.4 Diverting vanes must be provided at the bends exceeding 600 mm and at branches
connected into the main duct without a neck.

6.5 Proper hangers and supports should be provided to hold the duct rigidly, to keep them straight
and to avoid vibrations. Additional supports are to be provided where required for rigidity or as
directed by Engineer-In-Charge.

6.6 The ducts should be routed directly with a minimum of directional change.

6.7 All angle iron flanges to be welded electrically and holes to be drilled.

6.8 All the angle iron flanges to be connected to the GSS ducts by rivets at 100 mm centres.

6.9 The G.S.S. ducts should be lapped 6 mm across the flanges.

Technical specifications Page -62


Belvedere Club, Gurgaon

6.10 The ducts should be supported by approved type supports at a distance not exceeding 2.0
Metres.

Technical specifications Page -63


Belvedere Club, Gurgaon

7. Standard Grilles

7.1 The supply and return air grilles shall be fabricated from extruded aluminium sections. The
supply air grilles shall have single/double louvers. The front horizontal louvers shall be of
extruded section, fixed/adjustable type. The rear vertical louvers where required shall of
aluminium extruded sections and adjustable type. The return air grille shall have single
horizontal extruded section fixed louvers. The grilles shall have an outer frame on all four sides.

7.2 The damper blades shall also be of extruded aluminium sections. The grill flange shall be
fabricated out of aluminium extruded section. Grilles longer than 450 mm shall have
intermediate supports for the horizontal louvers.

8. Diffusers

8.1 The ceiling type square diffusers shall be of aluminium extruded sections with flush face with
fixed pattern and neck. The diffusers shall be provided with blank plate suitable of grid ceiling
(T-Bar) of size 600 mm x 600 mm.

8.2 All supply diffusers shall be provided with extruded aluminium dampers, with arrangement for
adjustment from the bottom, acoustically lined G.I. plenum, perforated diffusion plate and
circular spigot.

8.3 The slot diffusers shall be of aluminium extruded sections with diffusion plate and sliding
damper. It shall be provided with acoustically lined G.I. plenum box with circular spigot.

8.4 The acoustic lining shall be done with 12mm thick glasswool of 32 Kg/cu.m. density with
64ubberized lining on one face. The acoustic lining shall be fixed with self-adhesive stick pins.

9. Linear Diffusers/Grilles

9.1 The linear diffusers/grilles shall be fabricated from Aluminium extruded sections.

9.2 The diffusion blades shall be extruded, flush mounted type with single or double direction air
flow.

9.3 The frame shall be of aluminium extruded section and shall hold the louvers tightly in fixed
position. The frame shall be provided on all four sides.

9.4 The dampers as described under grilles shall be provided wherever specified.

10. Perforated Diffusers

10.1 The perforated diffusers shall be fabricated from aluminium sheet.


10.2 The sheet shall have uniform perforations to allow minimum 50% free area.
10.3 The supply air diffusers shall be provided with fully adjustable air pattern deflectors.

10.4 The frame shall be of extruded aluminium sections with blanking plate bonded to frame for grid
ceiling (T-bar) application.

Technical specifications Page -64


Belvedere Club, Gurgaon

11. Exhaust Grilles

11.1 The exhaust grilles shall be fabricated from aluminium extruded sections.

11.2 The exhaust grilles shall be horizontal fixed bar grilles with 150 blade inclination.

12. Exhaust / Fresh Air Louvers

12.1 The louvers shall be fabricated from aluminium extruded sections.

12.2 The blades shall be extruded flush mounted type with single horizontal throw.

12.3 The frame shall be of aluminium extruded section and shall hold the louvers tightly in fixed
position.

13. Painting and Vision Barrier

13.1 All grilles, and diffusers shall be powder coated, before installation, in approved colour.

13.2 All ducts immediately behind the grilles/diffusers etc. are to be given two coats of black paint
in matt finish.

13.3 The return air and dummy portion of all linear grilles shall be provided with a vision barrier
made of 24 gauge galvanized sheets. The vision barrier shall be fixed to the false ceiling frame
with self tapping screws and shall be given two coats of black paint in matt finish. Care shall be
taken to ensure that the return air path is not obstructed.

**********

Technical specifications Page -65


Belvedere Club, Gurgaon

Section 11 Control Panel, Motors and Switchgears

1. General

1.1 The motor and switch gears required for various items shall generally be as per
specifications given below. All electric motors shall be suitable for 3 phase, 50 Hz, 415 + 10%
- 15% Volts A.C. supply.

2. L.T. Electric Panel Boards

2.1 The main L.T. Panel board shall be extendible type on both sides, having in it all switches,
starters & accessories and shall be completely factory prewired. It shall be suitable for
voltage systems upto 500 Volts, 3 phase, 50 Hz, 4 wire supply capable of functioning
satisfactorily in temperatures of 450C and rupturing capacity not below 31 mVA at 415
Volts.

2.2 The Panel boards shall be fabricated from 2.0 mm thick, cold rolled M.S. Sheets. The front
opening door panels shall be from 2 mm thick, cold rolled M.S. Sheets. Suitable stiffners
shall be used in fabricating the housing. All steel members shall first be degreased, then
descaled using dilute sulphuric acid and a suitable phosphating process then the boards shall
be given powder coated finish in suitable grey colour. The switch board shall be dust proof
and vermin proof. The panel shall generally conform to IS 8623 (full confirmity not
called for). It shall be flush in front and back. The panel shall have front and rear access.

2.3 Cable compartment of adequate size shall be provided in the main distribution board for
easy termination of all incoming and outgoing cables entering from bottom or top.
Adequate support shall be provided in cable compartment to support cables. All incoming
and outgoing switch terminals shall be brought out to terminal blocks in cable
compartments.

2.4 Items such as ammeters, switches etc. shall be located close to the corresponding
switchgear and otherwise all items shall be arranged in a neat symmetrical pattern.

2.5 The doors of the switch compartments and cable access shall be hinged type and that
of busbars shall be fixed type.

2.6 The panel mounted lock shall be provided with a locking arrangement to prevent them
from falling down when they are unscrewed for opening the doors.

2.7 All panel doors shall have synthetic rubber gaskets with good ageing, compression and
resistance characteristics.

2.8 All the breakers shall be interlocked with door so that the unit cannot be closed unless the
unit door is closed. The interlock shall also prevent opening the unit door unless the
switch/breaker is in OFF position.

2.9 Defeat arrangement shall be provided for deliberate inspection of switch/ breaker without
having to switch OFF the unit.

Technical specifications Page -66


Belvedere Club, Gurgaon

2.10 All the items pertaining to a motor shall be incorporated in one cabin i.e switch,
starter, CTS ammeter, current operated MPRD-2 single phasing preventor, indicating lamps
etc.

2.11 A danger notice plate of 200 mm x 150 mm of mild steel at least 2 mm thick vitreous
enamelled white on both sides and with inscriptions in signal red colour on front side
shall be provided on the panel board.

2.12 Every starter/contactor etc. shall be controlled by an isolating device of adequat rating as
listed later.

2.13 A voltmeter and ammeter shall be provided to indicate incoming voltage and alongwith
rotary phase selection switches.

2.14 Ammeters shall be provided for incoming current for all motors of 10 HP (7.5 kW) and
higher ratings.

2.14.1 Ammeters for all the motors upto 50 HP (37.5 kW) shall be direct reading type.

2.14.2 Ammeters for motors of 50 HP (37.5 kW) and above shall be operated with a selector
switch.

2.15 LED type indicating lamps in approved colours shall be provided for the 3 phases and for
status of all controlled devices.

2.16 All the switchgear shall be earthed to the earth bus.

2.17 Earth shall be extended for each compartment to the door by means of a flexible,
insulated copper conductor with crimped legs on either side.

2.17.1 Each panel shall be provided with suitable size of earth bus at the rear of the panel
and two earth terminals on either side.

2.17.2 Suitable printed PVC ferrules shall be provided for all the conductors for easy identification.

2.18 Etched plastic name plates shall be provided for all the incoming, outgoing switchgears,
ammeter, voltmeter etc.

2.19 All the control and auxiliary wiring shall be carried out with PVC insulated copper
conductor of proper colour code.

2.21 The power wiring from the circuit/air breakers to the starters shall be carried out using
colour coded, PVC insulated copper conductors crimped with lugs.

2.21 The out going wires of starters shall also be pvc insulated colour coded copper conductor
crimped with lugs and terminated on a terminal block of proper rating.

Important Note
All Panel fabrication drawings shall be got approved, before the start of the fabrication work.
Technical specifications Page -67
Belvedere Club, Gurgaon

3. Bus Bars

3.1 The Bus Bar shall be mounted in a separate compartment in the Panel Board.

3.2 The Bus Bars and interconnections shall be of aluminium strips unless otherwise specified.

3.3 The Bus Bar shall have rectangular cross - section of (1) mm2 per Amp. rating for full load
current in the 3 phases as well as for neutral and should be extendable, if mounted
horizontally.

3.4 The Bus Bars shall be insulated with heat shrink sleeves and colour coated. They should be
supported on supports made of glass fibre reinforced thermosetting compound at regular
intervals sufficient to withstand the force of any short circuit.

4. Circuit Breakers

The panel and the bus bars plus outgoing of all devices shall be protected by different types
of circuit breakers as described below and conforming to specification as given later on:

S.No. Type Upto 63 A 80 to 200 A Above 200 to Above


40 Amp. 400 A 630 A

1. Incoming MCB MCCB MCCB MCCB ACB

2. Outgoing MCB MCB MCCB MCCB ACB

4.1 Air Circuit Breaker (ACB)

4.1.1 The air Circuit Breakers shall be Draw out type conforming to I.S: 13947 (Part 2) 1993.

4.1.2 The ACB shall be complete with solid state overload, short circuit and earth fault protection
with adjustable settings.

4.1.3 The current breaking capacity of the ACB shall not be less than 50 kA at 415 Volts, 50 Hz A.C.

4.1.4 Each ACB shall have 4 ‘NO’ and 4 ‘NC’ potential free auxillary contacts, in addition to those
required for its internal operating mechanisms.

4.1.5 There shall be suitable indicators for OPEN/CLOSE/SERVICE/TEST and Spring charged
positions.

4.1.6 It shall be possible to close the door in Test position.

4.1.7 Castle Key and/or other interlocking devices shall be provided as required.

4.2 Moulded Case Circuit Breakers (MCCB)

Technical specifications Page -68


Belvedere Club, Gurgaon

4.2.1 The MCCB shall have TP + NL and be suitable for simultaneous manual opening and closing
with rotary operating handle.

4.2.2 The ON/OFF/TRIP positions shall be clearly marked and easily visible to an operator and
confirm to latest IS: 13947 (Part 2)-1993.

4.2.3 There shall be fixed/adjustable tripping devices with inverse time characteristics for overload
and short circuit protection.

4.2.4 The current breaking capacity of the MCCB shall not be less than 35 kA at 415 Volts, 50 Hz,
A.C.

4.2.5 Suitable Interlocking mechanism shall be provided, where required.

4.2.6 All MCCB shall have phase barrier & extension terminals as required.

4.3 Miniature Circuit Breakers (MCB)


4.3.1 The MCB shall have quick make/break contacts with a heat resistant housing, having high
Impact strength and confirm to IS 8828-1996.

4.3.2 The contacts shall be of silver nickel alloy.

4.3.3 The MCB shall permit over load for short duration, as required for Inductive loads and the
breaking capacity shall not be less than 10 kA at 415 Volt A.C.

4.3.4 It shall be equipped with overload and short circuit protection devices and shall be suitable
for DIN mounting.

4.4 Isolator Switches


4.4.1 Isolator switches are to be provided for equipment located outdoors or for those located in
separate enclosure, other than those Nos. having the Electric Panel.

4.4.2 The Isolator Switch should be of Rotary Load Break type with a weather proof sheet steel
enclosure. Its rating shall be same as the outgoing device in the Electric Panel.

5. Contactors
All non inductive loads shall be provided with suitable sized magnetic contactors.

5.1 The contactors shall have 3/4 poles plus a minimum 2 ‘NO’ and 2 ‘NC’ contacts. All contacts
shall be of solid silver.

5.2 The No volt coil shall generally be suitable for 220 Volts + 10%, - 15% (wide band type) A.C.
supply except when specified or required otherwise.

6. Starters
6.1 The type of starters to be provided for the motors shall be as follows :

6.1.1 Squirrel Cage motors : upto 7.5 HP (5.6 kW) Direct on Line Type
6.1.2 Squirrel Cage motors : Above 7.5 HP (5.6 kW) Automatic Star Delta Type
Technical specifications Page -69
Belvedere Club, Gurgaon

6.1.3 Compressor motor : Above 300 HP (225 kW) Automatic Auto Transformers
(where specified)

6.1.4 All starters shall have auxiliary contacts for interlocking different machines, connecting
indicating lights, controls, alarms, etc.

All starters shall be provided with separate single phasing preventors.

SELECTION CHART (STAR DELTA STARTER)


S. MOTOR Current at 415 V Relay Contactor Ratings Backup
No. H.P. kW Line Phase Range Star Line Delta Fuse
1 7.5 5.5 11.2 6.5 4.5-7.5 12A 16A 16A 20A
2 10 7.5 14.8 8.54 6-10A 12A 16A 16A 20A
3 12.5 9.3 19 11 9-15A 12A 16A 16A 32A
4 15 11 22 12.7 9-15A 16A 25A 25A 32A
5 20 15 29 16.7 14-23 16A 25A 25A 40A
6 25 18.5 35 20.2 14-23 25A 32A 32A 50A
7 30 22.5 40 23 20-33 25A 32A 32A 63A
8 35 26 47 27 20-33 25A 32A 32A 63A
9 40 30 55 31.8 30-50 32A 45A 45A 63A

SELECTION CHART (DOL STARTER)


S. MOTOR Current at 415 V Relay Range Contactor
No. H.P. kW Fuse
1 3 2.25 5 4.5-7.5A 12A 15A
2 5 3.7 7.9 6.10A 12A 20A
3 7.5 5.5 11.2 9-15A 16A 32A
4 10 7.5 14.8 9-15A 25A 32A
5 12.5 9.3 19 14-23A 25A 50A

6.2 Direct On-Line Starters

6.2.1 These starters shall have heavy duty air break contactors of suitable rating.

6.2.2 These starters shall be complete with adjustable overload relays on all three phases, single
phase preventing device and under voltage release. The starters should be “hand reset”
type.

6.2.3 The “No Volt Coil “ of these starters shall be 220 Volts + 10% - 15% (wide band type)
whenever any controls on safety devices are connected in the starters circuits, otherwise
standard 415 Volts coils may be used. There shall be ON-OFF push button for each starter
unless remote operation of the starter is required.

6.3 Automatic Star Delta Starters

Technical specifications Page -70


Belvedere Club, Gurgaon

6.3.1 These starters shall have heavy duty air break contactors of suitable ratings along with an
adjustable timer to automatically switch the motor connections from star to delta
connections.

6.3.2 Each starter shall be complete with adjustable overload relays on all three phases and under
voltage release. The starters should be “hand reset” type.

6.3.3 The “No Volt Coil” shall be of 220 Volts + 10% - 15% (wide band type) rating wherever any
controls of safety device are connected in the starter circuit, otherwise standing 415 volts
coils may be used. There shall be ON-OFF push button for each starter unless remote
operation of the starter is required.

6.4 Automatic Auto -Transformer Starter

6.4.1 These starters will be oil immersed, each one fixed on a separate panel.

6.4.2 Necessary devices shall be provided for the automatic tap setting of the starter.

6.4.3 The starter should have “No Volt Coil” wide band type circuit of 220 Volts to be
connected to control circuits.

6.5 The Motor starter shall be in accordance with IS 1882. The starter shall be totally enclosed
metal clad, dust and vermin proof construction. The starter shall be of continuos rating.

6.6 Contactors shall have the number of poles as required for appropriate duty. The making
capacity of the starters shall be as per AC 23 of ISS.

7. Panel Accessories

7.1 All Voltmeters and Ammeters as specified shall be square of 96 mm x 96 mm, flush mounting
type.

7.2 The Indicating Lamps shall be of LED type with Low Watt Power. The Lamps shall have
translucent covers of following colours.

7.2.1 Red/Yellow/Blue for phase light.

7.2.2 Green/Amber for ON/OFF indication.

7.2.3 Concealed door lock.

8. Subsidiary Panels (With Single Switch)

8.1 Subsidiary panels shall be provided for equipment located away from the plant room, such
as air handling units, blower etc.

8.2 The construction of these panel should be similar to the main panel and shall have all
related accessories, except when specified.

Technical specifications Page -71


Belvedere Club, Gurgaon

8.3 The sub panel shall be wall hung type and as compact as possible.

8.4 Panel fabrication drawings shall be got approved before fabrication.

Technical specifications Page -72


Belvedere Club, Gurgaon

9. Squirrel Cage Motors (High Efficiency)

9.1 The squirrel cage motors shall be either screen protected or totally enclosed fan cooled
(TEFC) depending on the application and as stated in “schedule of equipment”. All motors
shall conform to IS 325/1978, IS : 1231 for foot mounted motors IS:2223 for flange
mounted motors and IS:12615 for Energy efficient motors.

9.2 The stator windings shall be with class ‘F’ insulation and temperature rise limited to class “B’

9.3 Motors shall be provided with ball/ roller bearings. Bearings shall have ample capacity to
deal with any axial thrust. Suitable grease nipple shall be provided for regreasing the
bearings.

9.4 Motors shall be provided with a cable box having min. six terminals, for terminating the
PVC insulated, PVC sheathed armoured aluminium cables.

10. Installation of Motor

10.1 Installation of the motor shall be in accordance with IS-900.

10.2 The motor along with its driven machine or equipment shall be provided with vibration
isolation arrangement motors shall generally be provided with slide rails fixed to the
base units nuts and bolts to facilitate belt installation and subsequent belt tension.

10.3 Motors shall be wired as per the detailed specifications and drawings all the motor frame
shall be earthed with 2 Nos. of earthing conductors.

10.4 Motors shall be tested at works in accordance with the relevant Indian standard
specifications and test certificates shall be furnished in triplicate.

Note : Rubber mats of 1100 Volts capacity shall be laid in front of panel as per site requirement
and no extra shall be paid.

11. Painting

All sheet steel work shall undergo a multi tank process of degreasing, pickling in acid, cold
rinsing, phosphating, passivating and then sprayed with a high corrosion resistant primer.
The primer shall be baked in oven. The finishing treatment shall be by application of
powder coated paint of approved shade and stoved.

--- x.x.x ---

Technical specifications Page -73


Belvedere Club, Gurgaon

Section 12 Electric Cabling

1. General

The electric cable connections of motors and earthing of all equipments shall be carried out, as
per specifications, given hereunder.

2. Cabling
2.1 The cabling of various equipment shall be carried using PVC Insulated and armoured FRLS
cables.

2.2 The PVC armoured FRLS power cable for use on 415 volts system shall be 3 or 3.5 Core with
aluminium conductors and be of 660/1100 volts grade, as per IS 1554 (Part I) 1964. The
cross section of the cable shall be to suit the load and rating of the equipment. The cables shall
be of aluminium conductor, PVC insulated, strip armoured with overall PVC sheathing.

2.2.1 The cables shall be laid as per IS-1255/1967, Indian standard code of practice.

2.2.2 The cables shall be laid, as per drawings in the ducts/pipes/trays etc. along a short and
convenient route between switch board and the equipment, (either in trenches, on wall or
on hangers, supported from the slab). Cable routing shall be checked at the site of work to
avoid interference with structure, equipment etc. Where more than one cables are running
close to each other, proper spacing should be provided between them. (Equivalent to half
the dia. of biggest size of cable, wherever the space permits.)

2.2.3 The radius of bends of the cable should not be less than 12 times the overall dia. of cable in
order to prevent undue stress and damage at the bends, the cables should be supported with
wooden cleats on M.S. Supports, when laid in trenches, or wall/ceiling suspended hangers.
When laid under ground the cables should be covered with fine soft earth and protected with
2nd Class bricks. Suitable G.I. Pipe shall be used wherever cables are laid under the roads etc.

2.2.4 Wooden bushes shall be provided at the ends of pipes through which cables are connected
through.

3. Surface Wiring
3.1 The surface wiring shall be cased in conduits which shall be of 1100 volts grade and conform to
IS 9587-1987 (revised to date)

3.1.1 The conduits used shall be of high quality & all joints shall be made with sockets. The bends
and elbows shall have inspection covers fixed with grease free screws. The joints shall be water
tight. Approved metal saddles shall be used to secure the exposed conduits at a space of 1
meter or less. The connection of the conduits to switches etc., shall be secured by check
nuts and ebonite bushes provided at the ends of conduits.

3.1.2 The G.I conduits shall be heavy duty and rigid type-ISI marked/conforming to IS specifications.
The wall thickness shall not be less than 2 mm. For conduits above 32 mm dia. Metallic conduits
of 20 mm dia. and below shall not be used. Conduit accessories (Boxes etc.) shall conform to IS-
5133-1968 and IS-2667-64 (amended-revised to date). Conduit pipes shall be jointed, wherever
Technical specifications Page -74
Belvedere Club, Gurgaon

necessary by means of screwed couples and screwed accessories only. In Long distance straight,
run of conduits inspection type couplers at suitable intervals shall be provided.

3.1.3 Threads on conduit pipes shall be between 13 mm to 19 mm long.

3.1.4 The wiring shall be carried-out as per IS 732-1989 (Amended and revised to date).

3.2 Flush inspection covers shall be provided in case of Concealed, recessed conduits. The staples
for the conduits shall not be spaced more than 0.60 meters apart. Before filling up the chase
with concrete the conduits should be given a coat of rust proof paint.

3.3 The wires shall be drawn only after all the conduits have been properly fixed in position. Fish
wires (steel wire: 16 SWG) shall be laid in conduits for drawing of wires subsequently.

4. Control Cabling/wiring

4.1 FRLS Control cables shall be1100 volts grade, as per IS 1554, made from copper conductor of
1.5 Sq mm PVC insulated single Core, strip armored with an overall PVC sheathing.

4.2 The cables and conduits wiring shall be carried out as per details given under 2.2 and 2.3 above.

5. Earthing

5.1 All equipment connected with electric supply shall also be provided with double earthing
continuity conductors. The size of Thinned copper . earthing conductors shall be :-

Size of phase wire sq.mm Size of Thinned Copper conductor


Aluminium Tape/Wire (Swg)

185 25 mm x 6 mm (strip)
150 25 mm x 6 mm (strip)
120 25 mm x 6 mm (strip)
95 4 Swg
70 4 Swg
50 6 Swg
35 6 Swg
25-6 6 Swg
4 6 Swg

Note :- Aluminium earthing conductors of equivalent Size may be used in lieu of GSS conductors
mentioned above.

6. Miscellaneous

6.1 The final connections to the equipment shall be through Flexible connections in case of conduit
wiring and also where the equipment is likely to be moved back and forth, such as on slide rails.

Technical specifications Page -75


Belvedere Club, Gurgaon

6.2 An isolator switch shall be provided at any motor which is separated from the main switch
panel by a wall or partition or other barrier or is more than 15 metres away from the main
panel.

6.3 Two separate and distinct earthing conductors shall be Connected from the equipment upto the
main switch board panel.

6.4 The branch lines from the main panel to each equipment shall be separated and should not
criss cross other lines.

6.5 The entire installation shall be tested as per Electricity rules and I.S.S. 732-1973 with
amendments 1,2&3 prior to the commissioning of the plant and a suitable test report
furnished by a competent and authorised person. The test report will be obtain by contractor
himself at his own expenses.

6.6 All exposed switch board panels, conduits, hangers etc. shall be given 2 coats of suitable paint
of approved colour, when all work has been completed.

***********

Technical specifications Page -76


Belvedere Club, Gurgaon

Section 13 Insulation

1. General

The Insulation of refrigerant piping and drain piping etc., shall be carried out as per
specifications given below :

2. Materials

The materials to be used for insulation shall be as follows, unless some other material is
specifically mentioned elsewhere. The detailed specifications of the materials are listed
under respective sub heads.

2.1 Refrigerant & Drain Pipe Insulation : Closed Cell nitrile elastomeric Insulation
insualtion with class 'O' , FM approved
2.2 Duct Insulation : Closed Cell elastomeric insulation
insualtion with class 'O' , FM approved
2.3 Acoustic Insulation : elastomeric nitrile insulation with class
'O' , FM approved

3. Refrigerant Pipe & Drain Pipe Insulation

3.1 The insulation of refrigerant piping shall be carried out from closed cell nitrile elastomeric
insulation with class 'O' , FM approved having a ‘K’ value of 0.037 W/mk at mean
temperature of 20oC and a density of 55 kgs./cubm.

3.2 The thickness of insulation on pipes shall be as follows :

a) Refrigerant piping 19.1 mm and above 19 mm thick

b) Refrigerant piping 15.9 mm and below 13 mm thick

c) Drain pipe all sizes 6 mm thick

4 Duct Insulation

4.1 The materials for duct insulation shall be sheets of closed cell nitrile elastomeric insulation with
class 'O' FM approved. The density of insulation shall not be less than 55 kg/cubm and material
shall be in the form of sheets of uniform thickness. The ‘K’ value at 20o C. shall not be less than
0.037 W/mK. The material shall have fire performance of class 1 of BS 476 Part-7 or equivalent
test method.

4.2 The thickness of duct insulation shall be as follows:

a. Duct in conditioned space - 13 mm thick

b. Duct in unconditioned space - 19 mm thick


Technical specifications Page -77
Belvedere Club, Gurgaon

5. Acoustic Treatment

5.1 The material for acoustic treatment of ducts, rooms, roofs etc. shall be thermally bonded non-
woven polyester fibre wadding. The density of polyester fibre shall be 1000 gsm (gms per m2) for
50 mm thickness or 750 gsm for 25 mm thickness and the material shall be in the form of
blankets of uniform density. The ‘k’ value at 10oC shall not be less than 0.0417 W/mk for 1000
gsm and 0.033 W/mk for 750 gsm. Facing shall be provided with 0.5 mm perforated aluminium
sheet held in place by self adhesive stick pins and screwed at the edge to G.I. box section.

5.2 The thickness of insulation shall be as follow unless otherwise specified elsewhere:

a. Duct Acoustic Lining : 25 mm


b. Room Acoustic Treatment : 50 mm

6. Other Materials

6.1 Cold Adhesive Compound

6.1.1 The Cold adhesive compound for closed cell elastomeric insulation shall be synthetic glue with
glue thinner.

6.2 Tar Felt

6.2.1 The Tar felt used for water proofing shall conform to IS: 1322 Type 3 Grade I.

7. Installation

7.1 Refrigerant Piping

7.1.1 The pipe shall be thoroughly cleaned with a wire brush and rendered free from all rust and
grease.

7.1.2 Two coats of synthetic glue shall be applied on the cleaned pipe surface.

7.1.3 The preformed sections of insulation shall be fixed tightly to the surface to take care to seal
all joints.

7.1.4 All longitudinal joints and circumferential joints shall be sealed with synthetic glue.

7.2 Drain Piping

7.2.1 The pipe shall be thoroughly cleaned with a wire brush and rendered free from all rust and
grease.

7.2.2 All joints shall be insulated with sleeves cut in two sections and fixed to the pipes with cold
adhesive compound.

Technical specifications Page -78


Belvedere Club, Gurgaon

7.3 Duct Insulation

7.3.1 The surface shall be cleaned with a wire brush and make it free from rust and oil.

7.3.2 Then apply two coats of synthetic glue to the surface.

7.3.3 The duct shall be wrapped with insulation sheets of the thickness mentioned above.

7.3.4 The joints shall be sealed with synthetic glue to form a seamless bond. The duct joints shall
be additionally covered with a 150mm strip of insulation material.

7.4 Duct Acoustic Lining

7.4.1 The duct surface shall first be cleaned from inside.

7.4.2 Then a frame of 25 mm square sections, made of 18 Ga (1.2 mm) thick G.I. sheet should be
fixed on both ends of the duct piece.

7.4.3 The insulation blankets/slab should be fixed between these sections of ducts using adhesive
compound and self adhesive stick pins.

7.4.4 The insulation shall the be covered with RP tissue, sealing all joint so that no fibre is visible.

7.4.5 The insulation shall then be covered with 0.5 mm thick perforated aluminium sheets.

7.4.6 The sheet of insulation shall be secured to the duct by means of stick pins as mentioned
above.

7.4.7 The spacing between two STICK PINS shall not be more then 250 mm vertically or
horizontally and 400 mm diagonally.

---- x.x.x ----

Technical specifications Page -79


Belvedere Club, Gurgaon

Technical specifications Page -80


Belvedere Club, Gurgaon

Section 14 Testing and Commissioning

1. General

1. 1 The contractor must perform all inspection and tests of the system as a whole and of
components individually as required, under the supervision of the architect, in accordance
with the provisions of the applicable ASHRAE standards or approved equal in addition to
furnish necessary test certificates from manufacturers.

1.2 The system shall then be commissioned, tested and balanced to fulfill the intent and purpose
for which it is designed.

1.3 In addition continuous Run Tests shall be carried out during peak weather condition.

2. Compressors Condensers/Out Door Units/Evaporators (All the tests to be performed in


factory)

2.1 Hydraulic test for various components and assembled equipments at 1.5 times design
pressure or double the operating pressure, whichever is higher.

2.2 Pneumatic leak test after assemblies at design pressure

2.3 Static and dynamic balancing on electronic precision machine for rotating parts, links,
impeller/ crank shaft assemblies etc.

2.4 Testing of oil passages in compressor at 1.5 times pump discharge pressure.

2.5 Pressure drop test for condenser, chiller and evaporator.

2.6 For compressor assembly, electronic leak, air running test, pneumatic test with dry nitrogen
and leak test in water.

3. Indoor Units

3.1 Performance test as per applicable codes to be performed in factory.

3.2 Coils

3.2.1 Pneumatic test to be performed in factory.

3.3 Filters

3.3.1 Test of filter elements as per B.S. 2831 B.S. 1701 as applicable. This is to ascertain filtration
efficiency by weight at inlet and outlet.

3.3.2 Manufacturer’s test certificates also to be produced for the assembled unit. Final
dimensional check will be done. Inspection may be done during assembly of components
for quality of workmanship, painting etc.

Technical specifications Page -81


Belvedere Club, Gurgaon

3.4 Piping

Materials check for specifications and size.

3.5 Instruments and Controls

Visual examination.

3.6 Special Note

Vendor to note that above procedure is to be followed in addition to the specifications


attached with the tender.

4. Associated Works at Site:

4.1 All electrical items will be subjected to inspection at any stage during manufacturing
activity. Routine electrical test as per relevant codes. Inspection of manufacturer’s test
certificates.

4.2 Inspection of raw materials to be used for fabrication and assembly and inspection of
manufacturer’s certificates.

4.3 Inspection of welding including welders qualification as desired by inspection engineers.


Inspection of fabricated items.

4.4 Pressure testing of pipe fittings used for the refrigerant and water and other services.

4.5 Checking of electrical circuits (power & controls) and checking functioning of controls of
refrigerant systems and other circuits of air conditioning plant.

4.6 Checking of calibration of controls and instrumentation

4.7. Checking of assemblies or electrical control panel, instruments panels, local panels
(dimensional and functional) annunciator panels etc.

4.8 Inspection of complete electrical installation at site.

4.9 Performance testing of completes VRV/VRF system as per specifications.

5. Vendor Responsibility

5.1 The above inspection procedure is given for general guidance and information of vendors.
The inspection of purchaser/consultant is strictly not limited to these.

5.2 The inspection engineer of purchaser/consultant will have full right, to have detailed
inspection at any stage right from placement of order to completion of project, as and
when desired by inspection engineer.
Technical specifications Page -82
Belvedere Club, Gurgaon

5.3 Co-ordination of inspection agency of purchaser/consultant with his factory/sub-vendor’s


factory/erection site will be the sole responsibility of successful vendor, subsequent to
placement of order for complete air conditioning plant, covered under these technical
specifications.

6. Piping System

6.1 In general pressure tests shall be applied to piping only before connection of equipment and
appliances. In no case shall piping, equipment or appliances be subjected to pressure
exceeding their test ratings.

6.2 Tests shall be completed and approved before any insulation is applied.

6.3 After tests have been completed, the system shall be drained and cleaned of all dust and
foreign matter. All strainers, valves and fittings shall be cleaned of all dirt, fittings, and
debris.

7. Electrical Equipment

7.1 All electrical equipment shall be cleaned and adjusted on site before application of power.

7.2 The following tests shall be carried out :

7.2.1 Cables and Wires continuity tests.

7.2.2 Insulation resistance tests, phase to phase and phase to earth, on all circuits and equipment,
using a 500 Volts meggar. The meggar reading shall be not less than one megaohm.

7.2.3 Earth resistance between conduit system and earth must not exceed half (1/2) CMH.

7.2.4 Phasing out and phase rotation tests.

7.2.5 Operating tests on all protective relays to prove their correct operation before enerzising the
main equipment.

7.2.6 Operating tests on all starters, circuit breakers etc.

8. Commissioning of the System

The system shall be commissioned by adopting the following procedure.

8.1 The installation as a whole shall be balanced and tested upon completion, and all
relevant information, including the following shall be submitted to the architects.

8.1.1 Air volume passing through each unit, aperatures.

8.1.2 Differential pressure readings across each filter, fan and coil, and through each pump.
Technical specifications Page -83
Belvedere Club, Gurgaon

8.1.3 Electrical current readings, in amperes of full and average load running and starting,
together with name plate current of each electrical motor.

8.1.4 Continuous recording over a specified period, of ambient wet and dry bulb
temperatures under varying degrees of internal heat loads and use and occupation, in each
zone of each part of the building.

8.2 Daily records should be maintained of hourly readings, taken under varying degrees of
internal heat load and use and occupation, of wet and dry bulb temperatures, upstream
“On-Coil” of each cooling coil. Also suction temperatures and pressures for each
refrigerating unit. The current and voltage drawn by each machine.

8.3 Any other readings shall be taken which may subsequently be specified by the architect.

8.4 If these air quantities cannot be delivered without exceeding the speed range of the pulley
or the available horse power, the architect shall be notify, before proceeding with the
balancing of air distribution system.

8.5 A proper record shall be maintained as per Test Performa given else where.

9. Miscellaneous
9.1 The above tests and procedures are mentioned herein, for general guidance and
information only, but not by way of limitation to the provisions of conditions of contract
and specification.

9.2 The date of commencement of all tests listed above, shall be subject to the approval of
the architect and In accordance with the requirements of this specification.

9.3 The contractor shall supply the skilled/unskilled staff and all necessary instruments and
carry out any test of any kind on a piece of equipment, apparatus, part of system or on a
complete system, if the architect requests such a test for determining specified or
guaranteed data, as given in the specification or on the drawings.

9.4 Any damage resulting from the tests shall be repaired and/or damaged material replaced, to
the satisfaction of the architect.

9.5 In the event of any repair or any adjustment having to be made, other than normal
running adjustment, the tests shall be void and shall be recommenced after the
adjustment or repairs have been completed.

9.6 The contractor must inform the architect when such tests are to be made, giving sufficient
notice, in order that the architect or his nominated representative may be present.

9.7 Complete records of all tests must be kept and 3 copies of these and location drawings
must be furnished to the architect.

9.8 The contractor may be required to repeat the test as required, should the Ambient
conditions at the time, do not give, in the opinion of the architect, sufficient and suitable
Technical specifications Page -84
Belvedere Club, Gurgaon

indication of the effect and performance of the installation as a whole or of any part, as
required.
*************

Section 15 Mode of Measurement

1. Unit Prices in the Schedule of Quantities

1.1 The item description in the schedule of quantities is in the form of a condensed resume. The
unit price shall be held to include every thing necessary to complete the work covered by
this item in accordance with the specifications and drawings. The sum total of all the
individual unit prices shall represent the total price of the installation ready to be handed
over.

1.2 The unit price of the various items shall include the Following :

1.2.1 All equipment, machinery, apparatus and materials required as well as the cost of any tests
which the Consultant/ Engineer-In-Charge may require, in addition to the tests generally
required to prove quality and performance of equipment.

1.2.2 All the labour required to supply and install the Complete installation in accordance with the
specifications.

1.2.3 Use of any tools, equipment, machinery, lifting tackle, Scaffolding, ladders etc. required by
the contractor to carry out his work.

1.2.4 All the necessary measures to prevent the transmission of vibration.

1.2.5 The necessary material to isolate equipment foundations from the building structure,
wherever necessary.

1.2.6 Storage, watch-and-ward and insurance of all equipment apparatus and Materials.

1.3 The contractor’s unit price shall include all equipment, apparatus, material and labour
indicated in the drawings and/or specifications in conjunction with the item in question, as
well as all additional equipment, apparatus, material and labour usual and necessary (within
the system as a whole) to complete the work, even though not specifically shown,
described or otherwise referred to.

2. Measurements of Sheet Metal Ducts, Grilles etc.

2.1 Sheet metal ducts:

2.1.1 All duct measurements shall be taken as per actual Outer duct surface area including bends,
tees, reducers, collars, vanes & other fittings. Gaskets, nuts, bolts, vibration rotation pads
are included in the basic duct items of the BOQ.

2.1.2 The unit of measurements shall be the finished sheet metal surface area in metres squares.
No extra shall be allowed for wastages.
Technical specifications Page -85
Belvedere Club, Gurgaon

2.1.3 All the guide vanes, deflectors in duct elbows, branches, grille collars quadrant dampers etc.
shall be measured for actual sheet metal surface and paid for at the same rate as duct of
same thickness.

2.1.4 The unit duct price shall include all the duct hangers and supports, from concrete
reinforcement and making good of the same as well as any materials and labour required to
complete the duct frame.

2.2 Grilles

All grilles/diffusers as per tender requirements shall be measure as follows:

2.2.1 All measurements of grilles shall be the actual outlet size excluding the outer flanges.

2.2.2 The square or rectangular grilles shall be measured in plain sq.m.

3. Accoustic duct Lining

3.1 In case of accoustic lining of air ducts, measurements of the bare inside duct surface in
square metres, shall be final for billing purposes.

3.2 The insulation/accoustic panels shall include cost of Battens, supports, adhesives, vapour
proofing, finished tile boards/sheets as well as additional labour and materials required for
completing the work.

4. Wall Insulation & Accoustic Treatment

4.1 The unit of measurement for all wall insulation, wall accoustic panel shall be the uninsulated
area of walls, to be treated, in square metres.

4.2 The insulation, accoustic panels shall include cost of battens, supports, adhesives, vapour
proofing, finished tiles/boards/sheets as well as additional labour and materials required for
completion of the work.

***********

Technical specifications Page -86


Belvedere Club, Gurgaon

Section 16 Schedule of Equipment Proposed

S. No. Description Unit Condition of Services

1. VRV / VRF Units

1.1 Outdoor Units

1.1.1 Type --------- VRV/VRF Type -----------


1.1.2 Quantity Nos. 2 1 4 1 2 1 2 1 2 1
1.1.3 Capacity (Cooling) HP 16 18 24 28 36 48 50 52 54 58
1.1.4 Air entering condenser ⁰C DB 43.3
1.1.5 Electric Supply -- 415 V/3 Ph/50 Hz --

1.2 Hi-Static Ductable Unit (Indoor Units )


1.2.1 Type ----- Hi-Static Ductable -------
1.2.2 Capacity (Cooling) TR 1.28 2.02 2.55 3.2 4 4.55 6.4 8
1.1.3 Air Quantity CFM 565 688 883 1130 1377 1624 2047 2542
1.2.4 Quantity of units Nos. 3 11 7 4 5 11 11 26
1.2.5 Electric Supply -- 230 V/1 Ph/50 Hz --

1.3 Cassette Type Units (Indoor Units )


1.3.1 Type -----------Cassette Type Units-----------------
1.3.2 Capacity (Cooling) TR 0.8 1.28 2.02 3.2

1.3.3 Air Quantity CFM 459 530 671 1130


1.3.4 Quantity of units Nos. 3 2 1 1
1.3.5 Electric Supply -- 230 V/1 Ph/50 Hz--

Technical specifications Page -87


Belvedere Club, Gurgaon

S. No. Description Unit Condition of Services

2 Air Handling Units (Double Skin)

2.1 Type ----Floor Mounted with Dx cooling coil-------


2.2 Quantity Nos. 2 1 3 1 1 1
2.3 Air quantity Cum/HR 17000 15300 11900 10200 8500 6800
2.4 Coil area Sqm 1.86 1.67 1.3 1.1 0.92 0.74
2.5 No. of rows Nos. 4 4 6 4 4 6
2.6 No. of fins/cm Nos. 5 5 5 5 5 5
2.7 Fan static pressure MMWG 50 40 40 40 40 40
2.8 Fan motor rating KW 5.5 5.5 3.7 2.3 2.3 1.5
2.9 Type of motor encl. -- TEFC TEFC TEFC TEFC TEFC TEFC
2.10 Drive -- -----------VFD-------------

3. Treated Fresh Air Units (Double Skin)


3.1 Type -- -Floor Mounted type-
3.2 Cooling Capacity TR 3
3.3 Quantity Nos. 1
3.4 Air quantity Cum/HR 2040
3.5 Coil area Sqm 0.22
3.6 No. of rows Nos. 4
3.7 No. of fins/cm Nos. 5
3.8 Fan static pressure MMWG 40
3.9 Fan motor rating KW 1.1
3.10 Type of motor encl. -- TEFC

4. DX Type Ductable Split Unit


4.1 Type -- -Ductable type-
4.2 Cooling Capacity TR 3
4.3 Quantity Nos. 2
4.4 Air quantity Cum/HR 2040
4.5 Electric Supply -- 230 V/1 Ph/50 Hz--

Technical specifications Page -88


Belvedere Club, Gurgaon

S. No. Description Unit Condition of Services

5. DX Type High Wall Split Unit


5.1 Type -- -Ductable type-
5.2 Cooling Capacity TR 1
5.3 Quantity Nos. 1
5.4 Air quantity Cum/HR 680
5.5 Electric Supply -- 230 V/1 Ph/50 Hz--

6. In Line Fan (Toilet Exhaust)


6.1 Type -- --- In Line fan ---
6.2 Application -- Toilet near Toilet at 4th Gents & Toilet in
conference floor Ladies at 2nd Terrace
& 3rd
6.3 Quantity Nos. 1 1 2 1
6.4 Air Quantity Cubm/hr. 528 720 1248 2112
6.5 Static Pressure MMWG 25 25 25 25
6.6 Rated KW of motor KW 0.27 0.37 0.6 1.5
6.7 Motor Speed RPM 1440 1440 1400 960
6.8 Type of Motor -- ------- TEFC --------

7. Axial Flow Fan


7.1 Type Nos. ----------- Axial Flow Fan ----------------------
7.2 Quantity Nos. 2 2 4 1 2 1
7.3 Air Quantity Cubm/Hr. 55,608 43,683 37294 31,141 28,594 23,827
7.4 Static Pressure MMWG 50 50 50 40 40 40
7.5 Wheel Diameter MM 1400 1000 1000 1000 1000 900
7.6 Rated KW of motor KW 15 15 15 7.5 7.5 7.5
7.7 Motor Speed RPM 1440 1440 1440 1440 1440 1440
7.8 Type of Motor -- TEFC TEFC TEFC TEFC TEFC TEFC

7.9 Type Nos. ----------- Axial Flow Fan ----------------------


7.10 Quantity Nos. 1 1 3 4 1 2
7.11 Air Quantity Cubm/Hr. 22,875 17,252 16,786 16,320 15,390 15,282
7.12 Static Pressure MMWG 40 40 40 40 30 50
7.13 Wheel Diameter MM 900 800 800 800 710 710
7.14 Rated KW of motor KW 7.5 5.5 5.5 5.5 3.7 5.5
7.15 Motor Speed RPM 1440 1440 1440 1440 1440 1440
7.16 Type of Motor -- TEFC TEFC TEFC TEFC TEFC TEFC

Technical specifications Page -89


Belvedere Club, Gurgaon

S. No. Description Unit Condition of Services

7.17 Type Nos. ----------- Axial Flow Fan ----------------------


7.18 Quantity Nos. 2 1 1 1 1 1
7.19 Air Quantity Cubm/Hr. 11,913 11,438 10,148 9,532 7,584 7,395
7.20 Static Pressure MMWG 50 40 40 30 40 40
7.21 Wheel Diameter MM 710 710 710 630 630 630
7.22 Rated KW of motor KW 5.5 3.7 2.2 2.5 2.2 2.2
7.23 Motor Speed RPM 1440 1440 1440 1440 1440 1440
7.24 Type of Motor -- TEFC TEFC TEFC TEFC TEFC TEFC

7.25 Type Nos. ----------- Axial Flow Fan ----------------------


7.26 Quantity Nos. 2 2 1 1 2
7.27 Air Quantity Cubm/Hr. 6048 4,914 4,608 2,688 2,040
7.28 Static Pressure MMWG 40 50 40 40 40
7.29 Wheel Diameter MM 630 560 630 560 500
7.30 Rated KW of motor KW 2.2 2.2 1.1 0.75 0.75
7.31 Motor Speed RPM 1440 1440 1440 1440 1440
7.32 Type of Motor -- TEFC TEFC TEFC TEFC TEFC

8. Propellor Fan
8.1 Type Nos. ----------- Propellor Fan ----------------------
8.2 Quantity Nos. 2 1
8.3 Air Quantity Cubm/Hr. 1,890 810
8.4 Static Pressure MMWG 20 20
8.5 Wheel Diameter MM 500 800
8.6 Rated KW of motor KW 0.55 0.35
8.7 Motor Speed RPM 1440 2800
8.8 Type of Motor -- TEFC TEFC

9 Air Washer
9.1 Type ------- Honey /Comb Pad --------
9.2 Application -- ------- Kitchen Fresh Air --------
9.3 Quantity Nos. 1 1 1 1
9.4 Air Qty. (each) CMH 5400 29700 12960 14400
9.5 Static Pressure MMWG 60 60 50 50
9.6 Motor Speed RPM 1400 1400 1400 1400
9.7 Motor Rating kW 2.2 11.5 3.7 5.5
9.8 Phase -- 3 3 3 3

Technical specifications Page -90


Belvedere Club, Gurgaon

9.9 Pad Area Sq.m. 0.59 3.2 1.41 1.57


9.10 Type of Motor -- ------------------- TEFC --------------------------
S. No. Description Unit Condition of Services
Pump
9.11 Quantity Nos. 1 1 1 1
9.12 Motor Rating kW 0.18 0.75 0.37 0.37
9.13 Motor Speed RPM 2900 2900 2900 2900

10 Kitchen Scrubber

10.1 Section Type -- ------------Dry Type-------------


10.2 Application -- --------------Kitchen Exhaust---------------
10.3 Quantity Nos. 1 1 1 1
10.4 Air Qty. (each) CMH 5400 29700 12960 14400
10.5 Static Pressure MMWG 60 60 50 50
10.6 Rated KW of Motor KW 2.2 11.5 3.7 5.5
10.7 Motor speed RPM 1400 1400 1400 1400
10.8 Type of motor -- ---TEFC Squirrel Cage---

**********

Technical specifications Page -91


Belvedere Club, Gurgaon

Section 17 Technical Data

Contractor should furnish technical data as mentioned below, of the equipment and accessories
offered by him as per scheme given in schedule of equipment and bill of quantities.

S.No. Description Unit Condition of Services

1. Variable Refrigerant Volume


System
1.1 Outdoor Units
1.1.1 Make --
1.1.2 Model --
1.1.3 Cooling Capacity --
1.1.3.1 Nominal HP
1.1.3.2 Actual HP
1.1.4 Compressor Motor KW
1.1.5 Sound level at distance of 3m DB(A)
1.1.6 No. of Compressor --
1.1.6.1 Fixed Speed Type Nos.
1.1.6.2 Variable Speed Type Nos.
1.1.6.3 Total No. of compressor Nos.
1.1.7 Power Supply requirement 3Ph/1Ph
1.1.8 Power consumption at rated KW
capacity

1.2 Indoor Units

1.2.1 Make --

1.2.2 Model --

1.2.3 Cooling Capacity --

1.2.3.1 Nominal HP

1.2.3.2 Actual HP

1.2.4 Air Quantity CMH

1.2.5 Sound level at a distance of 1m DB(A)

1.2.6 Power supply requirement 3Ph/1Ph

1.2.7 Power consumption at rated KW


capacity

Technical specifications Page -92


Belvedere Club, Gurgaon

Technical specifications Page -93


Belvedere Club, Gurgaon

S.No. Description Unit Condition of Services

2. Air Handling Units (Double Skin) Sectional FM


(Use separate sheet for details of each AHU)

2.1 Manufacturer Name


2.2 Type (Horizontal/Vertical)
2.3 Operating Weight KGS
2.4 Overall Dimension MxMxM
2.5 Dimension of Coils MxM
2.6 Finned Area Sqm
2.7 Material of coil Header Steel/Copper
2.8 No. of Rows Nos
2.9 Fins per cm Nos.
2.10 Type of fins- Plate/vertical --
2.11 No. of circuits Nos.
2.12 Water velocity in tubes M/s
2.13 Tube Material --
2.14 Tube Dia. MM
2.15 Thickness of tubes MM
2.16 Fin material --
2.17 Water pressure drop M
2.18 Air quantity CUBM/HR
2.19 Make of Fan --
2.20 Fan outlet velocity M/s
2.21 No. of fans Nos.
2.22 Dia of fans MM
2.23 Fan speed RPM
2.24 Total static pressure MM WG
2.25 Whether both Balancing Carried
Out-static and dynamic Yes/No
2.26 Motor Output KW
2.27 Type of motor --
2.28 Type of air filters & efficiency --
2.29 Velocity across filters M/s
2.30 Material and thickness of sheet
2.30.1 Internal MM
2.30.2 External MM
2.31 Material and thickness of Insulation MM
2.32 External finish Yes/No

Technical specifications Page -94


Belvedere Club, Gurgaon

S.No. Description Unit Condition of Services

3. Fan Section

3.1 Make and Model --


3.2 Type --
-Confirming to:
3.3 Air Inlet Single/double
3.4 Air Quantity at design speed CUBM/HR
3.5 Outlet velocity M/Sec.
3.6 Static Pressure MMWG
3.7 Velocity Pressure MMWG
3.8 Total Pressure MMWG
3.9 Wheel Diameter MM
3.10 Rated RPM RPM
3.11 Rated KW of Motor KW
3.12 Motor Conforming to:
3.13 Motor speed RPM
3.14 Type of Motor --
3.15 Whether Balanced
3.15.1 Statically Yes/No
3.15.2 Dynamically Yes/No
3.16 Noise Levels of complete unit. Db
3.17 Material of Construction:
-Impellor --
-Housing --
3.18 Type of Belts. --
3.19 Type of Pulley --
3.20 Bearings:
- TYPE --
- MAKE --
3.21 Overall Dimensions. MM
3.22 Accessories offered. --

4. DX Type Ductable split


4.1 Outdoor Units
4.1.1 Make --
4.1.2 Model --
4.1.3 Cooling Capacity --
4.1.3.1 Nominal HP
4.1.3.2 Actual HP
4.1.4 Compressor Motor KW
4.1.5 Sound level at distance of 3m DB(A)
4.1.6 No. of Compressor --

Technical specifications Page -95


Belvedere Club, Gurgaon

4.1.6.1 Fixed Speed Type Nos.


S.No. Description Unit Condition of Services
4.1.6.2 Variable Speed Type Nos.
4.1.6.3 Total No. of compressor Nos.
4.1.7 Power Supply requirement 3Ph/1Ph
4.1.8 Power consumption at rated KW
capacity
4.2 Indoor Units

4.2.1 Make --

4.2.2 Model --

4.2.3 Cooling Capacity --

4.2.3.1 Nominal HP

4.2.3.2 Actual HP

4.2.4 Air Quantity CMH

4.2.5 Sound level at a distance of 1m DB(A)

4.2.6 Power supply requirement 3Ph/1Ph

4.2.7 Power consumption at rated KW


capacity
5. DX Type High Wall split
5.1.1 Outdoor Units

5.1.1 Make --

5.1.2 Model --

5.1.3 Cooling Capacity --

5.1.3.1 Nominal HP

5..3.2 Actual HP

5.1.4 Compressor Motor KW

5.1.5 Sound level at distance of 3m DB(A)

5.1.6 No. of Compressor --


5.1.6.1 Fixed Speed Type Nos.
5.1.6.2 Variable Speed Type Nos.
5.1.6.3 Total No. of compressor Nos.
5.1.7 Power Supply requirement 3Ph/1Ph

Technical specifications Page -96


Belvedere Club, Gurgaon

5.1.8 Power consumption at rated KW


capacity

S.No. Description Unit Condition of Services


5.2 Indoor Units

5.2.1 Make --

5.2.2 Model --

5.2.3 Cooling Capacity --

5.2.3.1 Nominal HP

5.2.3.2 Actual HP

5.2.4 Air Quantity CMH

5.2.5 Sound level at a distance of 1m DB(A)

5.2.6 Power supply requirement 3Ph/1Ph

5.2.7 Power consumption at rated KW


capacity
6. In-line Fans

6.1 Type --
6.2 Manufacturer Make
6.3 Wheel Size (Dia) MM
6.4 Air quantity CUBM/HR
6.5 Static Pressure MMWG
6.6 Fan speed RPM
6.7 Type of motor --
6.8 Motor Rating KW
6.9 Motor Speed RPM
6.10 Current Characteristic --

7. Axial Flow Fans

7.1 Type --
7.2 Size (Dia) MM
7.3 Air quantity CUBM/HR
7.4 Static Pressure MMWG
7.5 Fan speed RPM
7.6 Current Characterstic --

8. Propellor Fans
8.1 Type --
8.2 Size (Dia) MM
8.3 Air quantity CUBM/HR
Technical specifications Page -97
Belvedere Club, Gurgaon

8.4 Static Pressure MMWG


8.5 Fan speed RPM
8.6 Current Characterstic --
S.No. Description Unit Condition of Services

9. Package Type Air washer


9.1 Make --
9.2 Air Quantity Cubm/hr.
9.3 Pad Area Sqm.
9.4 Pad Thickness MM
9.5 Pad efficiency %
9.6 Size of basin Tank MxM
9.7 Material and thickness of tank --/MM
9.8 Material and thickness of Basin --/MM

9.9 Pump
9.9.1 Make --
9.9.2 Model --
9.9.3 Capacity L/M
9.9.4 Head M
9.9.5 Motor reading KW

10. Kitchen Scrubber (Dry Type)


10.1 Manufacturer Name
10.2 Type --
10.3 Operating Weight Kgs
10.4 Overall dimension MXMXM
10.5 Air quantity Cubm/hr.
10.6 Fan outlet velocity M/s
10.7 No. of Fans Nos.
10.8 Dia. Of fans MM
10.9 Fan speed RPM

10.10 Total static pressure MMWG


10.11 Motor output HP/KW
10.12 Type of motor --
10.13 Material and thickness of sheet MM

11. Electrical Accessories


11.1 Electrical Panel --
11.2 MCCB (whether draw out type) --
11.3 Rotary Switches --
11.4 DOL Starter --
11.5 Star Delta Starter --
11.6 Contactors --
11.7 Current Transformer --

Technical specifications Page -98


Belvedere Club, Gurgaon

11.8 Single Phase Preventors --


11.9 Push Buttons --
11.10 Ammeter & Voltmeter --
11.11 Relays --
S.No. Description Unit Condition of Services

11.12 Indication Lamps --


11.13 MCB --
11.14 Cables --
11.15 Wires --

12. Material proposed for


(Type and Manufacturer)
12.1 Duct insulation Manufacturer
12.2 Pipe insulation (Type - I) Manf. (Type -II)
Manf.
12.3 Acoustic treatment of ducts --
12.4 Acoustic treatment of rooms --

13. Insulation Details Ducts / Piping / Acoustic Lining


13.1 Manufacturer --
13.2 Materials --
13.3 Density KG/Cum.
13.4 Mean ‘K’ value at 10o c --

14. Ancillary Items


(Type and Manufacturer)
14.1 G.I. Sheets --
14.2 Grilles/Diffusers --
14.3 Diffuser with Plenum --
14.4 Fire Damper --
14.5 Volume Control Damper --
14.6 Motorized actuator for fire damper --
14.7 Motorized actuator for F/A damper --

******

Technical specifications Page -99


Belvedere Club, Gurgaon

Section 18 List of Drawings

S. No. Description Drawing No.

1. Basement Ventilation – Ducting & Equipment Layout ADANI/GCA-BV-01


2. Ground Floor – Ducting & Equipment Layout ADANI/GCA- AC-01

3. First Floor – Ducting & Equipment Layout ADANI/GCA-AC-02

4. Second Floor – Ducting & Equipment Layout ADANI/GCA- AC-03

5. Third Floor – Ducting & Equipment Layout ADANI/GCA- AC-04

6. Fourth Floor – Ducting & Equipment Layout ADANI/GCA -AC-05

7. Roof Plan– Ducting & Equipment Layout ADANI/GCA -AC-06

8. Refrigerant Piping Schematic ADANI/GCA –AC-07

9. Electrical SLD ADANI/GCA –ELEC-01

*********

Technical specifications Page -100


Belvedere Club, Gurgaon

Section 19 List of Approved ‘Makes’ (VRV/VRF)

Note : The tenderer must indicate the makes he has used to cost his tender. Owner is at its
liberty to insist on any make mentioned below.

S. No Description of Item Approved Makes

1. High side Equipment


1.1 Split unit ductable Type/ High Daikin/Toshiba/
Wall Hitachi/Samsung/Voltas
2. VRV/VRF System Daikin/Toshiba/
Hitachi/Samsung/Voltas
2.1 Y-Joints Daikin/Toshiba/
Hitachi/Samsung/Voltas
2.2 Air Handling Units VTS/Systemair
3. Fans
3.1 Tube Axial Fans Wolter/Humidin/kruger /Nicotra
3.3 Inline Fans Wolter/Humidin/kruger /Nicotra
4. Air washer Damair/ Humidin/Arctic
5. Scrubber Ryder/ Ambassador/Humidin/ Maharaja/Emerald
6. Fan Section Zeco/Systemair/VTS
7 Refrigerant Pipe
7.1 Copper Pipe Mexflow/ Merchant/ Mandev
8. Cables & Accessories
8.1 Control Cables Finolex/Polycab/Havels/Bonton
8.2 XLPE / PVC Insulated Aluminium Finolex/ Polycab/Havels/Bonton
Conductor Armoured Power
Cables
8.3 Communication Cable Fusion/ Bonton/Finolex
8.4 Cable Gland Double Commet/Gripwell / Dowell's
Compression with Earthing Links
8.5 PVC Insulated Copper Finolex/Polycab/Havels/Bonton
Conductor Stranded Flexible
Wires
8.6 PVC Conduit & Accessories (ISI BEC/ Precision/ AKG
Approved)
8.7 MS/ GI Conduit (ISI Approved) BEC/ AKG/ STEEL KRAFT
8.8 Accessories for MS/GI Conduit Sharma Sales Corporation/ Super Sales Corporation
(ISI Approved)
8.9 Bimettalic Cable Lugs Hax (Brass copper Alloy India Ltd)/ Dowell's (Biller india
Technical specifications Page -101
Belvedere Club, Gurgaon

Pvt. Ltd.)
8.10 Lugs (Tinned Copper) Dowell
8.11. Control Cables Finolex/Polycab/Havels/Bonton
8.12 Power Cables Finolex/Polycab/Havels/Bonton

9 Electrical Equipment
9.1 Electrical Panel Board/ Motor Adlec / Tricolite/Advance panel & switchgear / RM
Control Centre (Power Coated) Controls (Faridabad)/ Indo Asian along with indo Asian
makes switchgear (Sonipat)
9.2 Isolator Panel Adlec / Tricolite/Advance panel & switchgear / RM
Controls (Faridabad)/ Indo Asian (Sonipat)
9.3 Electric Motor (TEFC) Siemens/ Crompton/ ABB

9.4 Starters/ Switch gear ABB/ L&T/ Schneider


9.5 Miniature Circuit Breaker (MCB) ABB/ L&T/ Schneider
9.6 Moulded Case Circuit breaker ABB/ L&T/ Schneider
(MCCB)
9.7 Earth leakage circuit Breaker (ELCB) ABB/ L&T/ Schneider
9.8 Push Button Starter ABB/ L&T/ Schneider
10. Ducting & Grilles
10.1 Grilles/ Diffusers Ravistar /Conaire/System Air
10.2 Fire Dampers Caryaire/ Conaire/System Air
10.3 G.I. Sheet Metal Duct Jindal/National/ Tata
10.4 Factory fabricated duct Zeco/Ductofab/ Waves
10.5 Duct flange Zeco/Ductofab/ Waves
10.6 Self Adhesive Sealing Gasket for Prima Seal/ Air Flow/ Trocellen
Ducts
10.7 Stick Pins Prima Seal/ Air Flow
10.8 VCD/ Gravity louvers/ Exaust & Caryaire/Ravistar/ System Air
fresh air louvers

11. Pipes & Fittings


11.1 GI pipe Medium Class Jindal Hissar/ Star
11.2 Copper Pipe Met Tube/Pancake/ Merchant/Malaysian/ Totaline
11.3 UPVC pipe Finolex/supreme/

12. Accessories/Controls
12.1 Humidistat Honeywell/ Siemens
12.2 Safety Thermostat for heater Anergy Controls/ Honeywell

13. Insulation
13.1 Non Woven polyster Fibre Mikron
13.2 Expanded Polystyrene (TF Quality) Thermolloyd/ Beard Sell/ Styrene Pakagings/ DEBS
(Pre-moulded pipe section/slab) Products/ P R Pakaging/ Coolite/ Indian Pakaging
Services
13.3 Cross Linked Polyethylene Trocellen/Supreme
13.4 Glass Wool Owens Corning/ U.P. Twinga
Technical specifications Page -102
Belvedere Club, Gurgaon

13.5 Closed Cell Elastomeric Insulation K-flex/A-flex/ Armacell


13.6 Aluminium Tape Johnson/ Birla 3M
13.7 Slotted Tray MEM/ Indeana
14 VFD Danfoss/Schneider/ ABB

Technical specifications Page -103

You might also like