Professional Documents
Culture Documents
CASE STUDY
This document specifies the division of responsibility between Cub3 Group and customer´s for the
implementation of the CPD Project at Barcelona.
1
RESPONSIBILITY MATRIX
1. Project Management
Provided by
No. Item
C3G Customer’s
1. Project Management
1.1 Roll out schedule planning and progress control √ Support
1.2 Project organization √
1.3 Resources planning √
1.4 Cost management √
1.5 Quality control √
1.6 Project Documentation and Reporting √
1.7 Management of personnel and office facilities √
1.8 Change order process √
1.9 Management of implementation works √
1.10 Health, Safety, Environmental and Quality (HSEQ) √ Support
requirements
Provided by
No. Item
C3G Customer´s
1 Utility and Permission
1.1 Application of AC power, sewage, water and telecom √
2
RESPONSIBILITY MATRIX
4. Site Preparation
Provided by
No. Item
C3G Sub-contractor
1. Site Preparation
1.1 CPD Layout Design √
The Factory building Design and construction
1.2 √
3
RESPONSIBILITY MATRIX
Provided by
No. Item
C3G Sub-contractor
3.1 Fire protection system √
3.2 Automatic fire alarm system √
3.3 Fire control system √
3 Fire fighting pipe network system √
4. Data Processing Centre Office
4.1 IT rack √
4.2 In-row cooling system √
4.3 PDU √
4.4 UPS and Battery √
4.5 PDB and PDF √
7. Datacenter monitoring system
7.1 Precision air conditioner system monitoring √
7.2 UPS system monitoring √
7.3 UPS input/output power distribution cabinet monitoring √
Precision air conditioner input/output power distribution
7.4 √
cabinet monitoring
7.5 IT equipment power distribution cabinet monitoring √
7.6 IT cabinet PDU monitoring √
7.7 Humidity and temperature monitoring √
7.8 Water monitoring √
7.9 Smoking monitoring √
7.10 Entrance security control system monitoring √
7.11 CCTV monitoring √
Provided by
No. Item
C3G Sub-contractor
1. Delivery of Equipment and Decoration Materials to sites
Delivery of equipment, documentation and tools
1.1 √
according to the contact
1.2 Custom Clearance
a) Provide the import license for equipment and decoration
√
materials
Perform Import Clearance for equipment and decoration
b) √
materials
c) Tax and duties, agent fee misc. charges √
4
RESPONSIBILITY MATRIX
Provided by
No. Item
C3G Sub-contractor
1.3 Storage of Equipment, materials and supplies √
1.4 Warehouse Management √
1.5 Delivery of equipment/supplies and installation materials
from port to warehouse, √
Provided by
No. Item
C3G Customer’s
1. Commissioning and Integration
1.1 Installation of the provided telecom equipments √
1.2 Planning, test plans/procedures √
1.3 Commissioning of equipment √
Provided by
No. Item
C3G Customer’s
1 Supervision and quality control
1.1. Subcontractor training √
1.2. Installation supervision √
1.3. Perform acceptance test with subcontractor √
1.4. Hand over site to GOS with site keys √
1.5. Provide inventory data in external disc. √
1.6. Perform site inspection according to PAT/FAT checklist √ √
1.7. Issue PAC/FAC certificate √
1.8. Site folder √
8. Acceptance test
Provided by
No. Item
C3G Customer´s
1. Acceptance test
Define test cases and fault category within agreed time
1.1 √
frame
5
RESPONSIBILITY MATRIX
Provided by
No. Item
C3G Customer’s
Acceptance tests completed within pre-agreed time
1.2 √
limits
1.3 Acceptance Support √
1.4 Approval of Preliminary Acceptance Certificate - (PAC) √
1.5 Approval of Final Acceptance Certificate (FAC) √
9. Miscellaneous Services
Provided by
No. Item
C3G Customer´s
1. Miscellaneous Services
1.1 Offer Training √
1.2 Operational Knowledge Transfer √
1.3 Documentation √